PMI-MS-QAM-CRS-BLG-MEPFS-2024-008-0 - Pipe Leak Test

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

PREMIUM MEGASTRUCTURES INC.

PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.


Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

Table of Contents

Section No. Description Page


1.0 Scope 03
2.0 Purpose 03
3.0 Definitions/Abbreviations 03
4.0 Resources 03-04
5.0 Responsibility 04
6.0 Construction Methodology
6.1 Work Methodology 04-05
7.0 Environment, Health, and Safety 06
8.0 Quality Control 06
9.0 Appendices 06

PMI-CM-QAM-01F1 Rev.1 18/04/23 Page 2 of 6


PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

1.0 SCOPE

This document covers the activities for the execution of Pipe Leakage Detection Test for Cerise Tower
Project in accordance with the requirements of Technical Specifications and to the established Safety
and Quality Standards. The scope of works includes the following:
• Document Submittal • Pipe Leak Test Procedures
• Preparatory Works o Bubble Test
o Hydrostatic Test

2.0 PURPOSE

The purpose of this document is to establish and illustrate in detail the activities required for the
execution of Pipe Leakage Detection Tests Procedures for Cerise Tower Project. To deliver a superior
quality works and services in the most cost-effective manner without sacrificing quality and to
environment.

This is also to acquire approval prior to the execution of works on site. Hazards are analyzed and safety
precautions are implemented and that all the Quality Assurance / Quality Control activities are
conducted in a systematic manner, works inspected and documented.

3.0 DEFINITIONS/ABBREVIATIONS

• LGU - A Local Government Unit, which refers to the local council or administrative body for a
geographical area.
• Bubble Test – a method to detect leaks by applying a soap solution to the surface.
• Hydrostatic Test – a way in which pressure vessels such as pipelines, plumbing, gas cylinders,
boilers and fuel tanks can be tested for strength and leaks.

4.0 RESOURCES
4.1 Manpower List
Item Description Quantity
1 Site Engineer 1
2 QA/QC Engineer 1
3 EHS Officer 1
4 Foreman 1
5 Driver/Equipment Operator 1
6 Warehouseman 1
7 Unskilled Workers 2
Note: The number of manpower may vary depending upon the quantity of work and/or from the approved
manpower loading.

4.2 Equipment/Tools List


Item Description Capacity Quantity
1 Water Truck 10,000 cu. m 1
2 Pressure Manifold - 1
3 Lighting Equipment - 1
4 Hand Tools - 1/worker
Note: The number and capacity of the equipment/tools listed above may vary depending upon the quantity of
work and/or from the approved equipment loading.

PMI-CM-QAM-01F1 Rev.1 18/04/23 Page 3 of 6


PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

5.0 RESPONSIBILITY

Personnel responsible for the execution of the work and implementation of this procedure:
Positions Responsibility
Coordinate with Safety Manager relative to Environment,
Health and Safety issues and concerns. Responsible for
assessing risk and possible safety hazards of all aspects of
operations; inspecting construction equipment and processes
to make sure they are safe; Conduct toolbox meetings:
EHS Engineer/Officer Ordering repairs for unsafe and/or damaged equipment for,
scaffolding, safety barricade and equipment inspection and
other relative safety precautions, inspect premises and the
work of personnel to identify issues or non-conformity. Stop
any unsafe acts processes that seem dangerous or unhealthy.
Supervise safety of workers while work is being undertaken.
QA/QC Engineer shall ensure that site workers are aware of
the requirements and that work is completed in accordance
with the project's specifications. They oversee carrying out
associated QA/QC operations for works as outlined in
applicable quality procedures and ITPs. They are also in
QA/QC Engineer charge of any quality control documentation required for
project completion, such as certifications, calibrations, test
reports, inspection work requests, non-compliance reports, site
instructions/observations, permanent material deliveries, and
other key documents.
The Site Engineer should work with the Project In-Charge to
monitor progress and ensure that Technical Specifications and
Safety Standards are met; he will also organize people and
equipment for each operation. Site Engineers should hold daily
Site Engineer briefings with their team leaders for the work status update to
predict any potential delays. Furthermore, he or she is
also accountable for reporting and following up all QA/QC
concerns prior to non-conformity activities.
Warehouseman should be responsible in assisting shipping
and receiving by unloading trucks and checking in items or
Warehouseman materials. Order preparation includes processing requests,
pulling orders, inventory control and sorting and arranging
warehouse products in accordance with organizational norms.

6.0 CONSTRUCTION METHODOLOGY

The relevant construction phases of each item on Scope of Work are hereinafter mentioned.

6.1 Work Methodology


6.1.1 Document Submittals
• Work permits shall be obtained from Client prior to start of any work activities as required.
• All relevant service authorities must be valid for the entire duration of the intended works. If
existing services are observed, the permit of the concerned department shall also be
obtained.
• No further activities shall commence prior to issuance of the Work Clearance for the
preceding operation. All supervisory personnel shall be aware of the permit to work system
and methodology of work activities.
• Material submittals, shop drawings and other submittals must be prepared and submitted
for the Consultant’s approval prior to execution of work.

PMI-CM-QAM-01F1 Rev.1 18/04/23 Page 4 of 6


PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

6.1.2 Preparatory Works


• Prior to execution of leak tests, all pipelines shall be ensured completed and have been
checked of its elevation and alignment.
• A visual inspection of the pipelines shall also be conducted to check for any observable
damage. Any observable abnormalities should be addressed accordingly before proceeding
to the test.
• All the necessary equipment and their appurtenances shall be deployed and set up
accordingly. Their calibration shall be ensured up to date prior to utilization.

6.1.3 Pipe Leakage Test Procedures


a. Bubble Test
• The bubble test shall be conducted for duct and pipelines especially at the joints or
connections.
• A soap and water solution shall be prepared. Mixing of the said material shall be of adequate
ratios to produce bubbles for instances of leakage.
• All openings of the duct and pipeline shall be ensured closed. The duct or pipeline shall
then be loaded with gas and shall have adequate pressure maintained inside the duct or
pipelines.
• After attaining the required pressure for the duct or pipeline, the joints shall be poured with
the soap and water solution.
• Once the soap and water solution has been poured and bubbles have formed at the surface,
it indicates a leak in the area.
• The duct or pipeline shall gradually be depressurized and shall have the leaks rectified in
accordance with the technical specifications.

b. Hydrostatic Test
• Pressure manifold equipment shall be set up at one end of the pipeline. All the other ends
of the pipeline shall be ensured closed and shall be provided with adequate thrust blocks
whenever necessary.
• Water shall then be injected gradually into the pipeline until it is full and until the required
pressure is attained.
• Pressure shall be maintained for a period of time in accordance with the technical
specifications.
• The pipeline shall then be inspected for any leakage. For instances where leakage has
occurred, the area shall be marked and shall be rectified accordingly compliant with the
technical specifications.

Illustration 1: Light Leakage Test Illustration 2: Smoke Leakage Test

PMI-CM-QAM-01F1 Rev.1 18/04/23 Page 5 of 6


PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

7.0 ENVIRONMENT, HEALTH, AND SAFETY

All operations will be carried out in a safe working manner and in every case, the practices adopted
shall be fully in accordance with the approved PMI Site Specific Safety Plan, PMI Safety and
Environmental Policy and PMI Health & Safety Manual.

Wherever necessary, additional safety precautions shall be adopted in accordance with the regulations
and reasonable instructions from the Client.

Personal Protective Equipment


Head Hand Foot Eye Hearing Fall
Body Protection Others
Protection Protection Protection Protection Protection Protection

YES YES YES YES YES YES YES YES YES

8.0 QUALITY CONTROL

All stages of activities shall be checked by the QA/QC Engineer and the final inspections & approval
by Client’s Representative. Check sheets may be used for ensuring proper inspection.

Quality Control for the works shall be operated in accordance with the Inspection Test Plan as attached
in the Appendix 9.2 and Site-Specific Work Procedures as defined in the Project Quality Plan.

9.0 APPENDICES

• Appendix 9.1 – Construction Work Sequence


• Appendix 9.2 – Inspection and Test Plan
• Appendix 9.3 – Inspection Checklist

PMI-CM-QAM-01F1 Rev.1 18/04/23 Page 6 of 6


PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

APPENDIX 9.1
Construction Work Sequence
PIPE LINE

SPRAY BOTTLE WORKER PREPARING


WITH A A SOLUTION
SOLUTION

SOAP

SOAP

SINK

1 Mix the soap and water solution with a proper ratio to produce bubbles. 2 Make sure all the opening of the pipeline shall be insured closed and set the required pressure.

PIPE LINE
SPRAY BOTTLE
PIPE LINE WITH A SOLUTION

WORKER POURED WORKER POURED


THE SOLUTION TO THE SOLUTION TO
ALL THE ALL THE
CONNECTION CONNECTION
JOINTS JOINTS AND
OBSERVED

After attaining the required pressure for the pipeline.poured the solution to the area were the Once the soap and water solution has been poured and if no leaks observed the pipeline system is
3 connection joints is. 4 passed the test.
NO. DATE REVISION (S) :
PROJECT TITLE : WORK SEQUENCE : DESIGNED BY : SHEET NO. :
0 5/2/24 NEW ESTABLISHMENT
DRAWN BY : A.M.E

CERISE TOWER LEAK TESTS PROCEDURES CHECKED BY : J.M.I.


LTP3
BUBBLE TEST APPROVED BY : D.D.S.

LOCATION : BINAN, LAGUNA DRAWING NO:PMI - WS - QAM - BLG -MEPFS - 2024 - 001 - LTP3 - Rev. 0
CONNECTION TO PIPING SYSTEM SAMPLE LINE PIPE CONNECTION TO PIPING SYSTEM SAMPLE LINE PIPE

WORKER INJECTED WATER INTO


PRESSURE GAUGE THE PIPELINE

WORKER SETUP
PRESSURE MANIFOLD THE EQUIPMENTS
PRESSURE PRESSURE
VENT PRESSURE MANIFOLD GAUGE
GAUGE
VENT
WATER TANK 75

50
100
125 150 175

200

225

250
75
100
125 150 175

200

225

50
25 250
275 25
0 300 275
0 300

125 150 175


100 125
150 175
200
100
75 200
225
75
50 225
250
50
25 250
275
0 25
300 275
0 300

PRESSURE PUMP

125
150 175
100
125 150 175
200
100
75 200
225
75
225
50
250
50
25 250
275
0 25
300 275
0
300

DRAIN VALVE PRESSURE RECORDER

Pressure manifold equipment shall be set up at the end of the pipeline.all the other ends of the Water shall then be injected gradually into the pipeline until it is full and until the required pressure
1 pipeline shall be ensured closed and shall be provided with adequate thrust blocks. 2 is attained.

WORKER CONDUCTING INSPECTION

CONNECTION TO PIPING SYSTEM SAMPLE LINE PIPE CONNECTION TO PIPING SYSTEM SAMPLE LINE PIPE

PRESSURE
PRESSURE MANIFOLD GAUGE
PRESSURE
PRESSURE MANIFOLD GAUGE

WORKER RECORDED THE


PRESSURE
125 150 175 125 150 175

100 100
200 200

75 75
225
225

50 50
250 250

25 25
275 275
0 0 300
300

125 150
125 175
150 175
100
100
200
200
75
75 225
225
50
50 250
250
25
25 275
275
0
0 300
300

125
125 150 175
150 175
100
100 200
200
75
75 225
225
50
50 250
250
25
25
275
275
0
300
0 300

PRESSURE RECORDER

The pipeline shall then be inspected for any leakage.if no leaks observed the pipeline system is
3 Pressure shall be maintained for a period of time in accordance with the technical specifications. 4 passed the test.
PROJECT TITLE : WORK SEQUENCE : NO. DATE REVISION (S) : DESIGNED BY : SHEET NO. :
0 5/3/24 NEW ESTABLISHMENT
DRAWN BY : A.M.E.

CERISE TOWER LEAK TESTS PROCEDURES CHECKED BY : J.M.I.


LTP4
HYDROTASTIC TEST APPROVED BY : D.D.S.

LOCATION : BINAN ,LAGUNA DRAWING NO: PMI - WS - QAM - BLG -MEPFS - 2024 - 001 - LTP4 - Rev. 0
PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

APPENDIX 9.2
Inspection Test Plan
PREMIUM MEGASTRUCTURES, INC.
1423 The Mondrian Bldg. P. Ocampo St. Ext.
San Antonio Village, Makati City 1203 Philippines
Tel. Nos. (02) 744-5264/576-8546

INSPECTION AND TEST PLAN (PER ACTIVITY)


Project Name: Cerise Tower Project Project ID:

Contract Package: General Works Date:

INSPECTION AND TEST PLAN DATA

Inspection & Test Plan No.: PMI-ITP-QAM-CRS-BLG-MEPFS-2024-008-0 Method Statement Ref. No.:

Title/Name: Pipe Leak Test Inspection Test Plan PMI-MS-QAM-CRS-BLG-MEPFS-2024-008-0

Inspection Codes
Item Specification and other
Description of Activity Test or Inspection Method Acceptance Criteria Frequency Records CM/ Remarks
No. Reference Documents Subcon Gencon Client
Consultant

1 Documentation
Project Specifications,
1.1 Method Statement International Standards, Review of Client Obtain Category A status from Engineer Prior to Work Execution Approval Letter H R R/A R
Contract Drawings

Project Specifications,
1.2 Material Appraisal International Standards, Review of Client Obtain Category A status from Engineer Prior to Work Execution Approval Letter H R R/A R
Contract Drawings

Project Specifications,
1.3 Shop Drawing International Standards, Review of Client Obtain Category A status from Engineer Prior to Work Execution Approval Letter H R R/A R
Contract Drawings
2 Tools and Equipment

Prior to use of the equipment / as per


2.1 Equipment Control and Calibration Project Specifications Inspection Obtain Certificate as recommended Calibration Certificate H R S S
calibration schedule

3 Activities

Method Statement, No bubbles should be formed at the applied area Test Results, Inspection Work
3.1 Bubble Test Visual Inspection, Measurement During Work Execution X H/W H/A R
Technical Specifications or joint Requests

Method Statement, No leakage should be observed at the pipeline Test Results, Inspection Work
3.2 Hydrostatic Test Visual Inspection, Measurement During Work Execution X H/W H/A R
Technical Specifications being tested during the whole test Requests

Legend:
X : Responsible for Implementing Work W : Witness Point R : Review Records

H : Hold Point S : Surveillance A : Accept/ Approve

Prepared By: Reviewed & Recommended By: Approved By:

QAQC Engineer Project Manager Client Representative

PMI-SP-QAC-XXXX
Rev. 0 05/10/2022 Page 1 of 1
PREMIUM MEGASTRUCTURES INC.
PMI Tower Cabanillas Corner, 273 Pablo Ocampo Sr.
Ext. Brgy. La Paz, Makati City 1203
Tel. Nos. (02) 7750-7195 / 8777-1764
METHOD STATEMENT FOR PIPE LEAKAGE DETECTION TEST

APPENDIX 9.3
Inspection Checklist
PREMIUM MEGASTRUCTURES, INC.
1423 The Mondrian Bldg. P. Ocampo St. Ext.
San Antonio Village, Makati City 1203 Philippines
Tel. Nos. (02) 744-5264/576-8546

INSPECTION CHECKLIST
Project Name: Cerise Tower Project Project ID:
Contract Package: General Works Date:

A. CHECKLIST DATA
Inspection Checklist No: Trade:
PMI-CHK-QAM-CRS-BLG-MEPFS-2024-008-0 MEPFS

Description:
Inspection Checklist for Pipe Leak Test

Items of Concern Yes No Remarks


Preparatory Works
1 Equipment Calibration
2 Equipment Condition
3 Site Preparation
4
5
6
7
8
9
10
11
12
13
14
15
Leak Test
1 Formation of Bubbles (Bubble Test)
2 Presence of Leakage (Hydrostatic Test)
3 Duration of Test
4
5
6
7
8
9
10
11
12
13
14
15

B. SIGNATORIES
Inspected By: Checked & Verified By: Approved By:

Field Operations/Subcontractor Representative Project QAQC Engineer Client/Consultant/Construction Management

PMI-SP-QAC-XXXX
Rev. 0 12/01/2022 Page 1 of 1