Professional Documents
Culture Documents
Book 1
Book 1
neccontract.com
©NEC 2023
Delivering
real value
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 2
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 3
Objectives
• Attendees should be confident in fulfilling the role of the
Project Manager under the ECC (clause 10.1….act as
stated in the contract……)
• How to engage the team and help build a 'spirit of
mutual trust and co‐operation’ (clause 10.2)
• Understand what needs to be implemented at the
commencement, during and at the end of a successful
project
• How to deal with typical problems that may occur
• How to be an effective ECC Project Manager
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 4
Payment
Managing the
ECC documents Other matters
programme
Defined Cost and the
Fee
Initial duties Risk management Project closure
Defined Cost ‐ SCC
ECC contract
Establishing key Compensation Defined Cost – management in
procedures events part 1 Disallowed Cost action
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 5
Assessment
On completion of the classroom training, you will need to
complete an online assessment in two parts, multiple‐
choice and long answer questions.
It can be accessed through the NEC website
(www.neccontract.com), via the My NEC area. You must
complete the assessment within 30‐days of receiving
notification of the assessment after the end of this course.
You will receive all necessary information via email once
we have confirmation of your attendance on this course.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 6
Assessment
Please note
• You must attend all 4 classroom training days
consecutively to be granted access to take the final
assessment.
• Reasonable adjustments may only be considered in
exceptional circumstances (see your delegate guide).
Applications with evidence must be submitted by email
for approval to the NEC
(accreditations@neccontract.com)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 7
Session 1
PROJECT START UP
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 8
Session 1 programme
10
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 11
11
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 12
12
13
14
• Exercise 1.1
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 15
15
Supervisor
Cost Quality
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 16
16
Communication Risk
protocol management
Programme
management
17
18
19
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 20
20
21.2 The Contractor submits the particulars of its design as the Scope requires to the
Project Manager for acceptance. A reason for not accepting the Contractor’s design
is that it does not comply with either the Scope or the applicable law.
The Contractor does not proceed with the relevant work until the Project Manager
has accepted its design.
(6) The Project Manager or the Supervisor does not reply to a communication
from the Contractor within the period required by the contract.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 21
21
31.3 Within two weeks of the Contractor submitting a programme for acceptance, the Project
Manager notifies the Contractor of the acceptance of the programme or the reasons for
not accepting it. A reason for not accepting a programme is that
22
61.4 The Project Manager replies to the Contractor’s notification of a compensation event within
one week after the Contractor’s notification or
a longer period to which the Contractor has agreed.
If the Project Manager fails to reply to the Contractor’s notification of a compensation event
within the time allowed, the Contractor may notify the Project Manager of that failure. If the
failure continues for a further two weeks after the Contractor’s notification it is treated as
acceptance by the Project Manager that the event is a compensation event …
Failure to respond to a quoted compensation event: Impact if not adhered to: clause 60.1:
62.6 If the Project Manager does not reply to a quotation within the (6) The Project Manager or the
time allowed, the Contractor may notify the Project Manager of Supervisor does not reply to a
that failure….. If the failure continues for a further two weeks communication from the
after the Contractor’s notification it is treated as acceptance by Contractor within the period
the Project Manager of the quotation. required by the contract.
23
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
23
Project
success
Effective
people
24
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 25
25
Form of agreement
ECC documents
Contract Data
part one
part two
Client’s Scope
Scope provided by the Contractor for
its design
© NEC Contracts
Site Information
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 26
26
Key documents
• The effective management of the contract by the Project
Manager requires a thorough understanding of the key
documents which form the contract. Two of the key
documents are the
• CONTRACT DATA
• SCOPE
• The objective of this next group exercise is help you to
familiarise yourselves with the structure and content of
the Contract Data
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 27
27
• Exercise 1.2
28
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
28
• If Option Z is used
• the additional conditions of contract are “…………………”
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 29
29
C – Target contract with activity schedule Lump sum with agreed pain/ gain share – 'share
ranges’
D – Target contract with bill of quantities Bill of quantities/ admeasurement with agreed pain/
gain share – 'share ranges’
E – Cost reimbursable contract Cost reimbursable (however, some costs may be
disallowed)
F – Management contract Management Contractor appointed – Client takes the
risk of subcontract cost
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 30
30
31
Secondary Options
Ref Option Objective > Risk to the > Risk to the Commercial Legal Time
Client Contractor related
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 32
32
Secondary Options
Ref Option Objective > Risk to the > Risk to the Commercial Legal Time
Client Contractor related
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 33
33
Secondary Options
Ref Option Objective > Risk to the > Risk to the Commercial Legal Time
Client Contractor related
34
Secondary Options
Ref Option Objective > Risk to the > Risk to the Commercial Legal Time
Client Contractor related
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 35
35
Secondary Options
Secondary Options
Ref Option Objective > Risk to the > Risk to the Commercial Legal Time
Client Contractor related
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 36
36
‘Z clauses’
• Additional conditions of contract (Z clauses)
• are incorporated through the Contract Data
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 37
37
38
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 39
39
40
• Period post Completion in which the Contractor has to correct notified Defects
defect • The Contract Data provides for different periods to be stated for different types of notified
correction
period
Defects
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 41
41
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 42
42
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 43
43
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 44
44
• Exercise 1.3
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 45
45
Scope
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 46
46
User guides
• For all contracts
• volume 1 Establishing a procurement and
contract strategy
• volume 3 Selecting a supplier
• For the ECC
• volume 2 Preparing an engineering and
construction contract
• volume 4 Managing an engineering and
construction contract
• Flow charts for the ECC ‐ electronic only
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 47
47
User guides
Preparing an engineering and construction contract
•the documents in the contract
•drafting Contract Data, Scope, Site Information and pricing documents
•worked example of Contract Data
Flowcharts
•show the procedural logic
•electronic only
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 48
48
49
Contractor’s design
Clause 21.1 states
“The Contractor designs the parts of the works which the Scope states the
Contractor is to design”
If the Client carries out most of the design, a list of items designed by the Contractor
may be stated
“The Contractor designs the following …..”
If, conversely, the Contractor carries out most of the design, a list of items designed by
the Client may be stated
“The Contractor designs all of the works with the exception of the following ….”
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 50
50
51
Inconsistent Scope
• What happens if there are inconsistencies between the Scope
provided by the Contractor (for its design) and the
Scope provided by the Client?
Clause 60.1(1) – it
Clause 17.1, is not a
Clause 14.3, ability to change
notify (13.7) compensation
event
52
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 53
53
• Exercise 1.4
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 54
54
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 55
55
Initial duties
• The Project Manager will need to start up the contract
and implement key procedures
• These will vary dependent on the project and the options
selected by the Client
• The ECC requires these to be recorded (refer to clause
13.1)
• Discretion is required as to which require attention first
• The ‘procedures’ are covered in the next module (for
example, communication, early warnings). This module
covers the likes of design acceptance and insurances
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 56
56
Start up procedures
Clause Issue Action / to note
‐ Contract signature Ensure there is evidence of contract agreement
13.2 Communication address Need to notify the address for communication
14.2 Delegations Notify any relevant Project Manager (and Supervisor)
delegations
15 Early Warning Register Compile the initial Early Warning Register. Set up the first
and early warnings early warning meeting to implement the early warnings
process (covered in next module)
21.2 Design acceptance The Contractor submits particulars of its design as
required by the Scope provided by the Client. The
Contractor does not proceed before acceptance. Clause
14.1 clarifies the status of any such ‘acceptance’
23.1 Design of Equipment Equipment (11.2(9)) covers items provided by the
Contractor and used by it to Provide the Works and
which the Scope does not require the Contractor to
include in the works; for example temporary footbridges,
hoardings and temporary sheet piling
57
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
57
Start up procedures
Clause Issue Action / to note
24.1 People Perhaps unlikely at the outset but any new ‘key person’
needs to be accepted by the Project Manager
26.2 Subcontracting The ECC requires each Subcontractor to be accepted by
the Project Manager before being appointed. Note that
failure to gain acceptance is potentially a reason for
termination (clause 91.2, R13!)
31.3 Programme acceptance (Covered in next module) the acceptance of the
programme is key to managing the contract
33.1 Access to and use of the Need to confirm access arrangements and use of the
Site Site
40.2 Quality management The Contractor must provide the Project Manager with a
system quality policy statement and a quality plan, within time
stated in the Contract Data
41.1 and Tests and inspections Although arguably not the direct role of the Project
42.1 Manager, it is important that adequate resource is in
place and timescales/ procedures are understood
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 58
58
Start up procedures
Clause Issue Action / to note
50.1 and Payment Payment procedures and contact details will need to be
50.2 established within the first month. Ensure requirements
for applications for payment are understood
Section 6 Compensation events This is covered in the next module. A clear and practical
method of managing compensation events will need to
be implemented.
84.1 Contractor insurances These need to be accepted before the starting date and
whenever renewed
86.1 Client insurances These need to be accepted before the starting date and
whenever renewed
Options C‐F, Cost forecasts This clause requires ‘consultation’ with the Project
clause 20.4 Manager. These arrangements will need to be
discussed and put in the diary
C, D, E and F Open‐book inspections Arrangements around open‐book inspections will need
to be discussed and organised
59
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
59
Start up procedures
Clause Issue Action/ to note
X4 Ultimate holding company If not already supplied, this needs to be provided within 4
guarantee weeks of the Contract Date. This needs to be checked.
X10 Information modelling The Information Model needs to be identified and the
process for creating it made clear to all those involved.
If not already supplied, the Contractor must supply a first
Information Execution Plan as stated in the Contract Data.
X12 Multiparty collaboration This potentially will need to be developed and completed
X13 Performance bond If not already supplied, this needs to be provided within 4
weeks of the Contract Date. This needs to be checked.
X14 Advanced payment Advanced payments will need to be organised. A bond
may be needed from the Contractor
X29 Climate Change Plan If not already supplied, the Contractor must supply a first
Climate Change Plan as stated in the Contract Data.
Y(UK)1 Project Bank Account This will need to be set up if incorporated
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 60
60
Launch workshops
• A ‘pre‐start meeting’ or project launch is advisable in
order for the procedures to be implemented
• A pre‐start meet may be appropriate on smaller projects
• A launch event should be considered on larger/ more
complex projects. This is a blend of ECC training and
group working in order that the appropriate procedures
and systems are implemented
• We suggest that the Project Manager should instigate
this
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 61
61
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 62
62
63
64
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 65
65
66
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 67
67
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 68
68
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 69
69
Communication protocol
• NEC published guidance on communication
in User Guide Volume 4
• example forms are contained within the Guide
• As a minimum, the ECC forms are
recommended as the means of
communicating
• they state the relevant clause
• communications are structured
• This is following what the contract requires
(‘acting as stated’) rather than being
adversarial
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 70
70
This needs to be
understood and Poor
ground
followed by the team conditions
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 71
71
72
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 73
73
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 74
74
75
76
• Exercise 1.5
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 77
77
Summary of session 1
• The principles of good project management are embedded
within the ECC
• A competent Project Manager addresses the implementation
of procedures and ensure a team understanding/ ethos
• The ECC provides good management data and controls to
ensure projects are successfully administered
• The Contract Data and Scope need to be well written and
managed carefully
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 78
78
Summary of session 1
• A number of technical duties/actions were detailed in
chronological order (for example, ultimate holding
company guarantee, insurances, acceptance of the design
and subcontractors)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 79
79
Delivering
real value
Payment
Managing the
ECC documents Other matters
programme
Defined Cost and the
Fee
Initial duties Risk management Project closure
Defined Cost – SCC
ECC contract
Establishing key Compensation Defined Cost – management in
procedures events part 1 Disallowed Cost action
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 2
Session 2
PROGRAMME AND RISK MANAGEMENT
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 3
Session 2 Programme
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 5
Core clauses
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 6
Some examples
Obligation Programme Compensation
Event
21.2: submit design 31.2, bullet 13 60.1(6)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 7
Core clauses
??
The absence of an Accepted
Programme will make it difficult
to assess compensation events!
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 8
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 9
operation 1
Critical operations:
operation 2
operation 3
operation 4
operation 5
2 weeks float
Non-critical operations:
planned
Completion
Completion 10
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
10
operation 1
operation 2
operation 3
CE001
‘Operation 4’ has to start after CE001
operation 4
operation 5
2 weeks float
planned
Completion
Completion
11
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
11
operation 4
1 week float
operation 5
planned
Completion planned Completion is unaffected, the
Client takes advantage of the float
Completion 12
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
12
operation 1
Critical operations:
operation 2
operation 3
operation 4
operation 5
Non‐critical operations: 2 weeks float
planned
Completion
Completion 13
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
13
operation 1
operation 2
operation 3
operation 4
operation 5
2 weeks float
planned
Completion
Completion 14
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
14
operation 1
operation 2
operation 3
operation 4
No float
operation 5 remains
planned
Completion
The Contractor takes advantage of the float
Completion 15
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
15
operation 1
Critical operations:
operation 2
operation 3
operation 4
operation 5
Non‐critical operations: 2 weeks float
planned
Completion
Completion 16
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
16
operation 1
operation 2
operation 3
operation 4
operation 5
2 weeks float
planned
Completion
Completion 17
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
17
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
1 week float
planned
Completion
Completion 18
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
18
operation 4
1 week float
operation 5
Completion
takes advantage of the float
19
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
19
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
1 week float
planned
Completion
Completion 20
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
20
operation 1
operation 2
operation 3
CE001
Contractor
delay
operation 4
operation 5
planned
Completion
Completion 21
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
21
operation 1
operation 2
operation 3
CE001
Contractor
delay
operation 4
operation 5
planned
Completion
Delay, no
compensation
Completion
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
event 22
22
operation 1
operation 2
operation 3
operation 4
operation 5
2 weeks float
planned
Completion
Completion 23
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
23
operation 1
operation 2
operation 3
Contractor
delay
operation 4
No float
operation 5 remains
planned
Completion
Completion 24
The Contractor takes advantage of the float
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
24
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 25
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
25
operation 1
operation 2
operation 3
CE001
Contractor
delay
operation 4
operation 5
planned
Completion
Completion 26
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
26
operation 1
operation 2
operation 3
CE001
operation 5
planned
Completion
Completion 27
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
27
operation 4
operation 5
planned
Completion
Completion 28
The compensation event will cover the one week effect
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
28
operation 5
29
operation 1
operation 2
operation 3
CE001
CE001 must complete before
‘Operation 4’ can start
Contractor
delay
operation 4
operation 5
planned
Completion
Completion 30
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
30
operation 4
operation 5
planned
Completion 1 further week delay
Completion 31
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
The compensation event will cover the one week effect
31
operation 1
How do we know?
operation 2
Which clause states this?
operation 3
operation 4
This belongs to
the Contractor
operation 5
planned
Completion
Terminal float
Completion
32
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
32
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
planned
Completion
Completion 33
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
Terminal float
33
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
planned
Completion
Completion 34
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
Terminal float
34
operation 4
operation 5
planned
Completion
The compensation event will cover
Completion the one week effect 35
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
Terminal float
35
• Exercise 2.1
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 36
36
The Contractor is delayed by the Subcontractor’s poor performance (their risk) during
weeks 4, 5 and 6 (add 2 weeks in total). This impacts on the start of operation 5 (in‐situ
lab).
Question 1 What are the revised planned Completion and Completion Dates?
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 37
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
37
Answer 1
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
Contractor
delay
operation 4
operation 5
planned
Completion
Completion 38
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
38
The Project Manager instructs PMI 001 and notifies CE001: a sauna and relaxation
room. The work will take place in weeks 5, 6 and 7.
Question 2 What are the revised planned Completion and Completion Dates?
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 39
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
39
Clause 63.5, planned Completion is delayed by two weeks and therefore so too is the
Completion Date
Answer 2
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
planned
Completion
Completion 40
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
40
The Project Manager instructs PMI 001 and notifies CE001: 2 weeks of work starting in
week 5. Operation 5 is dependent on this.
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 41
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
41
Answer 3
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
Contractor
delay
CE001
operation 4
operation 5
planned
Completion
Completion 42
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
42
The Project Manager then issues a PMI 001 and notifies CE001 which is a compensation
event to extend operation 5 by 1 week.
Question 4 What are the revised planned Completion and Completion Dates?
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 43
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
43
Planned Completion was delayed by 1 week as a result of the CE. The Completion Date
therefore moves out by 1 week (week 8).
Answer 4
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
Contractor
delay
operation 4
operation 5
CE001
planned
Completion
Completion 44
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
44
The Project Manager instructs PMI 001 and notifies CE001. This is for 3 weeks
additional work to Operation 5.
Question 5
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 45
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
45
Planned Completion was delayed by 1 week as a result of the CE, the Completion Date
therefore moves out by 1 week (week 9).
Answer 5
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
Contractor
delay
operation 4
operation 5
CE001
planned
Completion
Completion 46
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
46
operation 1
operation 2
operation 3
planned
Completion
Completion 47
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
Terminal float
47
Checklist:
• Risk allowances relate to risks that are the Contractor's within the contract (refer to any additional
compensation events stated in the Contract Data part one, Z clauses and additional Client's liabilities)
• Separate references to 'float' and to 'time risk allowances' are included in clause 31.2. It is important
that they are each clearly identifiable on the programme
• The duration of the risk allowance is reasonable, that they have a significant chance of occurring
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 48
48
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 49
49
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 50
50
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 51
51
If using the latter and, if the first programme does not comply,
clause 50.5 would take effect!!
There is also no discretion.
Avoid at all costs – hardly a good start to the project
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 52
52
Suggestion
• Meet to agree each programme before submission
• agree changes in the meeting
• the programme shows input from all
• this can be submitted by the Contractor following / at the
meeting
• an acceptance is then required
• this is a much more collaborative way of working
• we also develop our understanding and what the project
pressures are – this will aid the identification of early warnings
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 53
53
54
55
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 56
56
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 57
57
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 58
58
Assessment
• A delay to the Completion Date is assessed as the length
of time that, due to a compensation event, planned
Completion is later than planned Completion as shown
on the Accepted Programme current at the dividing date
(63.5)
• The dividing date is date of the Project Manager’s or
Supervisor’s instruction, notification etc. or the date of
the notification of the compensation event (63.1)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 59
59
Assessment
• Does the programme change in any way to assess the
compensation event? See clause 63.5:
“The assessment takes into account
• any delay caused by the compensation event already in the
Accepted Programme and
• events which have happened between the date of the
Accepted Programme and the dividing date.”
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 60
60
Assessment
• The key requirements for assessing delays to the
Completion Date due to a compensation event are to
• determine the effect that the compensation event has
upon planned Completion and
• use the Accepted Programme current at the dividing
date to do so
• The objective is to assess the effect due only to the
compensation event and not due to other events
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 61
61
Assessment
• 4 basic steps
1. 2. 3. 4.
‐ Decide the ‐ Use the ‐ Update (for ‐ Impact the
dividing date Accepted progress, compensation
(63.1) Programme other events, event (63.5)
current at the etc.) (62.2 and
dividing date 63.5)
(63.5)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 62
62
Managing updates.
Example 1 use latest Accepted Programme
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
operation 4
Completion 63
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
63
Managing updates.
Example 1 impact of compensation event
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
‘Operation 5’ must
PMI
001/CE001 complete before new
operation CE001 can start
operation 4
operation 5
planned Completion is
planned
Completion
unaffected, the Completion
Date therefore remains
Completion
unchanged
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 64
64
Managing updates.
Example 2 use latest Accepted Programme
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
operation 4
Completion 65
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
65
operation 1
operation 2
operation 3
operation 5
1 week float
planned
Completion
Completion 66
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
66
Managing updates.
Example 2 add the compensation event
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion
67
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
67
Managing updates.
Example 2 add the compensation event
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
planned Completion is affected
planned
Completion
by 1 week
Completion 68
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
68
Managing updates.
Example 2 add the compensation event
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
since planned Completion is
planned
Completion
affected by 1 week, the
Completion Date therefore
Completion
moves out by 1 week
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
69
69
Managing updates.
Example 3 use latest Accepted Programme
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
operation 4
operation 5
2 weeks float
planned
Completion
Completion 70
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
70
operation 1
operation 2
operation 3
operation 4
operation 5
3 weeks float
planned
Completion
Completion 71
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
71
operation 1
operation 2
operation 4
operation 5
3 weeks float
planned
Completion
Completion 72
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
72
Managing updates.
Example 3 Impact of the compensation event
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
CE001
operation 4
operation 5
planned
Completion
planned Completion is not affected, the
Completion Completion Date therefore remains the same 73
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
73
• Exercise 2.2
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 74
74
The Project Manager issues PMI 001 and notifies CE001. This is for 3 weeks
additional work to Operation 5. However, at the dividing date the Contractor is
ahead on Operation 5 (instead of taking 2 weeks it looks like they will take 1 week).
Exercise 2.2 What are the revised planned Completion and Completion Dates?
operation 1
operation 2
operation 3
operation 4
operation 5
planned
Completion
Completion 75
Date L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
75
Answer
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
operation 1
operation 2
operation 3
operation 4
operation 5
CE001
planned
Completion
Completion 76
Date
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023
76
Sectional Completion
• Clause X5.1
• each reference to Completion, unless stated as the whole of the
works (e.g. defects date), is relevant to any section
• so the principles we have been through also apply for each
section (for example, terminal float, effect on planned sectional
Completion)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 77
77
Key Dates
• Clause 63.5
• exactly the same principles apply for Key Dates too
• “A delay to a Key Date is assessed as the length of time that, due
to the compensation event, the planned date when the
Condition stated for a Key Date will be met is later than the date
shown on the Accepted Programme current at the dividing
date.”
• in essence, what was the net effect on the date the Contractor
planned to meet the Condition stated? This could be before or
after the Key Date itself
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 78
78
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 79
79
Risk management
• Where risk management begins (or should begin)
• Client's liabilities and additional compensation events
• Role of the Early Warning Register
• Early warning process and links in the contract
• Practical suggestions to ensure this is managed
collaboratively
Many project management methodologies (Prince2, Six Sigma etc) include
a risk management process
The ECC defines this process within the contract and makes
‘good practice’ the norm
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 80
80
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 81
81
Risk allocation
• Risk allocation can be changed by the Client by
• including additional Client’s liabilities in Contract Data part one
• including additional compensation events in Contract Data part
one
• through Option Z clauses
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 82
82
If they occur then they would If they occur then they would
become a compensation event become a compensation event
(clause 60.1(21)) (clause 60.1(14))
The Client will be liable for any costs
which the Contractor has paid or will
pay to Others as a result of the event
(clause 82.2)
The Contractor does not have to
insure against a Client's liability
(clauses 80.1 and 83.3)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 83
83
• Exercise 2.3
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 84
84
Items identified in Contract Data parts one and two (headed ‘matters to be
included in the Early Warning Register’) do not change the risk allocation
– their purpose is to support post‐contract risk management
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 85
85
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 86
86
Time
EWs
Cost Quality
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 87
87
88
• Exercise 2.4
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 89
89
Recognise that
both Parties
The Project
will encounter
Manager
Not about problems and
facilitates and
casting blame working to
trouble shoots
overcome
the process
them
collaboratively
You could go through the group working exercise with your team!
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 90
90
91
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 92
92
Agree how the early warnings will be managed. As a minimum use the
communication forms in the User Guide
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 93
93
• Exercise 2.5
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 94
94
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 95
95
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 96
96
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 97
97
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 98
98
2. A further 3 stated in
1. Clause 60.1 (21
clauses 60.4, 60.5 and
reasons)
60.6 (Options B and D)
99
2. Failure to do
1. A change of mind/ something (many
decision relate back to the
programme)
3. Something has
happened that is
beyond a specified
reasonable risk level
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 100
100
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 101
L46350 NEC4 ECC Project Manager Accreditation v6 Dec 2021 © NEC 2021
101
60.1(21) Additional compensation events stated in Contract Data part one Contract Data
X15.2 Contractor corrects a Defect for which it was not liable under the contract 44
Y2.5 Contractor exercises its right under the Act to suspend performance ‐
Z Additional conditions of contract ‐
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 102
102
Clause 60.1(1)
The Project Manager gives an instruction changing the Scope except
• a change made in order to accept a Defect or
• a change to the Scope provided by the Contractor for its design which is made
at the Contractor’s request or in order to comply with Scope provided by the
Client
103
Clause 60.1(1)
Exceptions ……
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 104
104
Clause 60.1(1)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 105
105
• Exercise 2.6
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 106
106
Clause 60.1(2)
The Client does not allow access to and use of each part of the Site by the
later of its access date and the date for access shown on the Accepted
Programme
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 107
107
Clause 60.1(3)
The Client does not provide something which it is to provide by the date shown
on the Accepted Programme
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 108
108
Clause 60.1(4)
The Project Manager gives an instruction to stop or not to start any work or to
change a Key Date
109
Clause 60.1(5)
The Client or Others
• do not work within the times shown on the Accepted Programme
• do not work within the conditions stated in the Scope or
• carry out work on the Site that is not stated in the Scope
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 110
110
Clause 60.1(6)
The Project Manager or Supervisor does not reply to a communication from the
Contractor within the period required by the contract
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 111
111
Clause 60.1(7)
The Project Manager gives an instruction for dealing with an object of value or
of historical or other interest found within the Site
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 112
112
Clause 60.1(8)
The Project Manager or Supervisor changes a decision which either has
previously communicated to the Contractor
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 113
113
Clause 60.1(9)
The Project Manager withholds an acceptance (other than acceptance of a
quotation for acceleration or for not correcting a Defect) for a reason not stated
in the contract
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 114
114
Clause 60.1(10)
The Supervisor instructs the Contractor to search for a Defect and no Defect is
found unless the search is needed only because the Contractor gave insufficient
notice of doing work obstructing a required test or inspection
115
Clause 60.1(11)
A test or inspection done by the Supervisor causes unnecessary delay
116
Clause 60.1(12)
The Contractor encounters physical conditions which
• are within the Site,
• are not weather conditions and
• an experienced contractor would have judged at the Contract Date to have such a small
chance of occurring that it would be unreasonable to have allowed for them
Only the difference between the physical conditions encountered and those for which it
would have been reasonable to have allowed is taken into account in assessing the
compensation event
Explanation: Mitigation: Examples:
• Something physical is • Ensure thorough site • Asbestos is found but
encountered which is investigations and that there was no mention
beyond the threshold the Site Information is of this in the Site
stated for an robust Information and it was
experienced contractor not anticipated
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 117
117
Needs to be read in conjunction with Link to the list of early warning matters in
clause 60.2: Contract Data part two:
• ‘Other information which an • It would be illogical for the Contractor
experienced contractor could to identify a matter in Contract Data
reasonably be expected to have or to part two and then to subsequently
obtain’ is quite broad notify a compensation event under
60.1(12)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 118
118
Clause 60.1(13)
A weather measurement is recorded
• within a calendar month,
• before the Completion Date for the whole of the works and
• at the place stated in the Contract Data
the value of which, by comparison with the weather data, is shown to occur on
average less frequently than once in ten years.
Only the difference between weather measurement and the weather which the
weather data show to occur on average less frequently than once in ten years is
taken into account in assessing a compensation event
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 119
119
120
• ‘The place where the weather should be recorded’ is advised to be as close to the
Site as possible
• The contract compiler is invited to add in additional weather measurements
• ‘wind’ is missing from the list, this is worthwhile considering for inclusion but 1
in 10 for wind?
• although not a weather measurement, wave height may also need to be
considered on coastal projects
• The 1 in 10 year return period should be included in the programme as a time risk
allowance
• The Contractor takes all weather risk after the Completion Date as there cannot be
a compensation event for this
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 121
121
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 122
122
123
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 124
124
Clause 60.1(14)
An event which is a Client's liability stated in these conditions of contract
125
Clause 60.1(15)
The Project Manager certifies take over of a part of the works before both
Completion and the Completion Date
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 126
126
• Take over if the Contractor has not achieved Completion and it is now after the
Completion Date. This could have a significant impact on the Contractor
• X7.3 – If the Client takes over a part of the works before Completion and it is after
the Completion Date, the delay damages are reduced from the date on which the
part is taken over. The Project Manager assesses the benefit to the Client of taking
over the part of the works.
• Insurances might be an issue here so the Project Manager would need to check
Client has organised this
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 127
127
Clause 60.1(16)
The Client does not provide materials, facilities and samples for tests and
inspections as stated in the Scope
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 128
128
Clause 60.1(17)
The Project Manager notifies the Contractor of a correction to an assumption
which the Project Manager stated about a compensation event
129
Clause 60.1(17)
• This is an excellent way of getting better value for money from compensation event
quotations
• Assumptions made by the Contractor have no status. Compensation events are an
extension of their risk profile in the contract (clause 63.8)
• The assumptions are stated by the Project Manager (61.6)
• Although the contract does not specifically state such, it would be sensible to
discuss this before notifying the compensation event
• The Project Manager should recognise that the assumptions transfer risk to the
Client, and should only give those assumptions needed to enable Contractor to give
a sensible quotation
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 130
130
Clause 60.1(18)
A breach of contract by the Client which is not one of the other compensation
events in the contract
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 131
131
Clause 60.1(19)
An event which
• stops the Contractor completing the whole of the works or
• stops the Contractor completing the whole of the works by the date for planned Completion
shown on the Accepted Programme
and which
• neither Party could prevent,
• an experienced contractor would have judged at the Contract Date to have such a small chance
of occurring that it would have been unreasonable to have allowed for it and
• is not one of the other compensation events stated in the contract
Explanation: Mitigation: Examples:
• The ‘prevention’ clause • Perhaps via an early • Covid‐19 prevents the
does not attempt to list warning as soon as it works being completed
the events – it describes became apparent
a scenario, clause 19.1
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 132
132
Clause 60.1(20)
The Project Manager notifies the Contractor that a quotation for a proposed
instruction is not accepted
133
Clause 60.1(21)
Additional compensation events stated in the Contract Data
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 134
134
135
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 136
136
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 137
137
• Exercise 2.7
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 138
138
• Exercise 2.8
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 139
139
Summary of session 2
• The programme is key ‐ it’s the ‘beating heart’ of the ECC
• The ECC programme is a joint programme which provides
critical management data
• If the programme is not compliant / accepted it becomes very
difficult to assess compensation events objectively
• In order to ensure acceptance of the programme it is
worthwhile considering a joint review before final submission
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 140
140
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 141
141
Delivering
real value
Payment
Managing the
ECC documents Other matters
programme
Defined Cost and the
Fee
Initial duties Risk management Project closure
Defined Cost ‐ SCC
ECC contract
Establishing key Compensation Defined Cost – management in
procedures events part 1 Disallowed Cost action
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 2
Session 3
COMMERCIAL MANAGEMENT
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 3
Session 3 programme
3.2 Payment
Commercial management
• The main commercial core clauses are contained in the
following ECC Sections
• section 5 – Payment
• section 6 – Compensation events
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 5
Commercial management
• The ECC contains further clauses which have a
commercial impact, examples include
Clause Description Clause Description
16.1 & 2 Contractor’s proposals 54 Contractor’s share (Options C & D)
20.4 Forecasts of the total Defined Cost 71 Equipment, Plant and Materials
(Options C, D, E & F) marked for payment
25.2 Not complying with the Scope 82 Recovery of costs
25.3 Not meeting a Key Date 85 & 86 Insurance
36 Acceleration
41.6 & 7 Repeating a test or inspection Note: Depending on the secondary
Options selected these may also have a
45 Accepting Defects
commercial impact i.e. X1, X6, X7 etc
46 Uncorrected Defects
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 6
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 7
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 8
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 9
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 10
10
11
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 12
12
13
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 14
14
dividing date
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 15
15
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 16
16
quotation in time
• if it decides that the Contractor has not Project Manager Contractor
assessed the compensation event correctly
and has not instructed the Contractor to 3 Weeks (to quote)
17
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 18
18
Contractor
A well documented system and adherence notifies
to timescales is paramount Automatic (that it had
acceptance no response)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 19
19
Example
• The assessment of additional stud walling was
implemented at £12k (clause 66.1)
• if the actual Defined Cost plus Fee amounted
to £10k we would not revise
• if conversely, the actual Defined Cost plus Fee
was £15k we would not revise
• There is no room for budgets or ‘say’ allowances
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 20
20
21
22
• Exercise 3.1
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 23
23
3.2 PAYMENT
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 24
24
Payment overview
• Introduction to section 5 of the ECC
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 25
25
Assessment intervals
• The first assessment date is decided by the Project Manager to suit
the procedures of the Parties (but is no later than the assessment
interval after the starting date) – clause 50.1
• Normal assessments made at assessment interval until
• the Supervisor issues the Defects Certificate or
• the Project Manager issues a termination certificate
• Final assessment (this is covered in session 4) no later than
• four weeks after Defects Certificate or
• thirteen weeks after termination certificate (53.1)
• The assessment interval is typically calendar monthly
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 26
26
Payment
• Clause 50.1 requires the Project Manager to assess the
amount due at each assessment date
• Contractor submits an application for payment before
each assessment date
• Application includes details of how amount has been
assessed, in form stated in Scope
• Project Manager considers the application when
assessing the amount due (50.2)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 27
27
Contractor's share (C or D)
etc
etc
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 28
28
Payment
• If Contractor does not submit an application, amount due is
lesser of
• amount Project Manager assesses and
• amount due at the previous assessment date (50.4)
• Any wrongly assessed payments are corrected in subsequent
payment certificates (50.6)
29
Payment certificate
• An example payment
certificate is provided in
User Guide Volume 4
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 30
30
Clause 50.5
• Clause 50.5 becomes relevant if no programme is included in the
Contract Data and
• a first programme is not submitted by the Contractor for acceptance to the
Project Manager or
• the submitted programme does not show the information which the contract
requires
• One quarter of the PWDD is retained in the assessments of the amount
due certificate on a cumulative basis until a first programme is submitted
which shows the information which the contract requires (it does not
state that is has to have been accepted)
• Once the Contractor has submitted a first programme showing the
information which the contract requires, the retained PWDD is included
in the assessment of the next amount due
Avoid at all costs by informally agreeing before first submission
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 31
31
Timeline
3 weeks or other
period stated in
Contract Data interest 51.2
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 32
32
Timeline
33
• Exercise 3.2
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 34
34
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 35
35
36
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 37
37
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 38
38
C Cost Based
Target
D
E Cost
reimbursable
F
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 39
39
CEs
Activity Schedule
11.2(21)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 40
40
CEs
Bill of Quantities
11.2(22)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 41
41
CEs
target (Options C & D)
plus Fee 11.2(10)
or Bill of Quantities
used to update the
Defined Cost
Activity Schedule
11.2(24)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 42
42
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 43
43
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 44
44
OR
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 45
45
46
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 47
47
compensation
events
Activity
Schedule
Fee
Defined Cost
11.2(10)
(SSCC):
11.2(23)
(29) The Price for Work Done to Date is the total of the Prices for
• each group of completed activities and
• each completed activity which is not in a group.
A completed activity is one without notified Defects the correction of
which will delay following work.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 48
48
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 49
49
compensation
events
Bill of
Quantities
Defined Cost Fee
(SSCC): 11.2(10)
11.2(23)
50
PWDD: Option B
Bill of Quantities: PWDD: Month 2
Bill Description Nr Unit Price Bill Description Nr Unit Price
item (£) item (£)
1 M3 of 10 £1 £10 PWDD: Month 1 1 M3 of 10 £1 £10
excavation excavation
Bill Description Nr Unit Price
2 Metres of 10 £1 £10 item (£) 2 Metres of 10 £1 £10
drainage drainage
1 M3 of 10 £1 £10
3 M3 of 10 £1 £10 excavation 3 M3 of 10 £1 £10
concrete concrete
2 Metres of 5 £1 £5
4 Tonnes of 10 £1 £10 drainage 4 Tonnes of 2 £1 £2
steel steel
3 M3 of ‐ £1 ‐
Total of the Prices £40 concrete Total of the Prices £32
4 Tonnes of ‐ £1 ‐
Less previous £15
steel
PWDD £15 Amount due £17
Less previous ‐
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 51
51
PWDD: Options C to E
PWDD
compensation
Defined Cost events
Plus Fee
Fee Fee
Defined Cost Defined Cost
11.2(10) 11.2(10)
(SCC): (SCC):
11.2(24) 11.2(24)
(31) The Price for Work Done to Date is the total Defined Cost which the Project Manager
forecasts will have been paid by the Contractor before the next assessment date plus the Fee.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 52
52
PWDD: Options C to E
PWDD:
Month 1 Month 2
Total of the
Prices / total
of the Prices PWDD at month 1
Defined Cost
plus Fee:
Fee
Defined
Cost
Less
Dis.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 53
53
PWDD: Option F
PWDD
Note: compensation
events in the
Subcontracts are dealt
(31) The Price for Work Done to Date is the total Defined Cost which the Project Manager within the
Subcontracts
forecasts will have been paid by the Contractor before the next assessment date plus the Fee.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 54
54
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 55
55
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 56
56
57
58
59
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 60
60
61
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 62
62
63
64
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 65
65
Subtotal 339,049.70
TOTAL 372,954.67
Note: It is advisable that the PWDD (i.e. how payment is made) resembles the total of the Prices. This will help
validate that the rates and percentages are accurate. This can be modelled as part of the tender process.
It is also advisable to consider all costs that will be incurred and whether they fall into Defined Cost, if not, they need
to be included in the Fee.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 66
66
Fee
11.2(10)
Note:
Clause 52.1: anything
Defined Cost ‐
not included in Defined Schedule of Cost
Cost is treated as Components 11.2(24)
included in the Fee
Less:
Disallowed Cost
11.2(26)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 67
67
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 68
68
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 69
69
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 70
70
• Exercise 3.3
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 71
71
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 72
72
73
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 74
74
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 75
75
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 76
76
• Exercise 3.4
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 77
77
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 78
78
• Consideration points
• good recording keeping and proof of payment
• Contractor’s accounting procedures
• Subcontractor management/compensation events
• Scope – other records
• agree appropriate timing for inspection
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 79
79
• Exercise 3.5
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 80
80
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 81
81
Understanding of Defined
Cost and Fee
Detailed understanding of
Knowledge of the accounting procedures:
construction industry accruals, payroll uplifts, etc
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 82
82
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 83
83
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 84
84
85
Summary
• Defined Cost and Fee are instrumental building blocks to the
ECC main Options
• They each have varying roles within the main Options
• It is critical that the rates and percentages are accurate and
relevant to the appropriate main Option
• The ECC requires the Prices to be updated and Defined Cost
to be forecast (for Options C, D, E and F)
• Finally, open‐book procedures need to be implemented for
Options C, D, E and F
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 86
86
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 87
87
Without an Accepted
Programme and effective
early warning process it
will make it difficult to
assess compensation
events objectively
Collaborative teams
Agree at the outset
typically agree in a
of the project how
meeting environment
the process will work
and then formally
(systems)
notify and accept
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 88
88
• Exercise 3.6
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 89
89
Summary of session 3
• The compensation event process needs careful management.
In order to maintain a collaborative relationship the Project
Manager will need to play an active role here and may need
to educate on what the process is and how it should be best
managed
• The Defined Cost and Fee are used to
• assess compensation events under all main Options and
• determine what the Contractor gets paid under Options C to F
• Open book inspection of accounts and records procedures
will need to be set up for Options C to F
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 90
90
Delivering
real value
Payment
Managing the
ECC documents Other matters
programme
Defined Cost and the
Fee
Initial duties Risk management Project closure
Defined Cost ‐ SCC
ECC contract
Establishing key Compensation Defined Cost – management in
procedures events part 1 Disallowed Cost action
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 2
Session 4
CONTRACT MANAGEMENT AND PROJECT CLOSURE
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 3
Session 4 programme
4.1 Reporting
4.1 REPORTING
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 5
• Option B, (33) The Prices are the lump sums and the amounts obtained by multiplying
11.2(33) the rates by the quantities for the items in the Bill of Quantities.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 6
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 7
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 10
10
Summary
• Each main Option is different in terms of how finances are
reported
• A key role of the Project Manager is to establish and manage
this reporting function
• Further clarity could be included within the Scope provided by
the Client. If not already included this could be changed
(clause 14.3)
Establish the reporting procedures at the
commencement of the project
Meet regularly as a team
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 11
11
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 12
12
Other matters
Clause Issue Action/ to note
16.3 Adding to the The Contractor may submit a proposal to add to the Working
Working Areas Areas. A reason for the Project Manager to not accept the
proposal is that the proposed area is not necessary to Provide
the Works or used for work not in the contract
The Working Areas concept is used in the Schedule of Cost
Components and Short Schedule of Cost Components. It affects
payment in main Options C to E and items included in
compensation events in Options A to E.
17.1 Ambiguities and Both parties have an obligation to notify. The Project Manager
inconsistencies states how the ambiguity or inconsistency should be resolved. If
it’s giving an instruction to change the Scope for the Contractor's
design in order to comply with the Scope provided by the Client,
is not a compensation event (60.1(1), second bullet). But
correcting ambiguities and inconsistencies in the Scope provided
by the Client would be (clause 60.1(1) and see 63.10)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 13
13
Other matters
Clause Issue Action/ to note
17.2 Illegal and Both parties have an obligation to notify. If the Scope does
impossible include an illegal or impossible requirement, the Project
requirements Manager gives an instruction to change the Scope accordingly
19.1 Prevention If an unexpected and catastrophic event occurs which is judged
to prevent the project completing, the Project Manager gives an
instruction to the Contractor stating how the event is to be dealt
with. It is assessed as a compensation event (clause 60.1(19))
21.2 Design The Contractor submit particulars of its design as required by the
acceptance Scope. The Contractor does not proceed before acceptance.
Clause 14.1 clarifies the status of ‘acceptance’
23.1 Design of Equipment (clause 11.2(9)) covers items not included in the
Equipment works, for example temporary footbridges and hoardings
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 14
14
Other matters
Clause Issue Action/ to note
24.1 People The name of any new or replacement key person needs to be
accepted by the Project Manager
24.2 Removing a The Project Manager may, having stated the reasons, instruct the
person Contractor to remove a person
28.1 Assignment Each Party notifies the other Party if they intend to transfer the
benefit of the contract or any rights under it. This is not strictly
an issue for the Project Manager, but if the Client is transferring
benefits and rights, it may also be doing the same in the Project
Manager’s contract with the Client
29.2 Disclosure The Contractor may publicise the works only with the Client’s
agreement. The Project Manager may well be the administrator
of this
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 15
15
Other matters
Clause Issue Action/ to note
Section 4 Quality Although not directly part of the Project Manager role, it is
management suggested that the Project Manager ensures that the Supervisor
understands its role, what is written within the Scope and the
procedures in section 4. Also ensure that they both use clear
methods of communication. The ECC pro‐formas are
recommended as a minimum
40.3 Quality plan The Project Manager accepts the Contractor’s quality plans and
checks compliance. If the Contractor at any time fails to comply
the Project Manager instructs the Contractor to do so
45 Accepting Defects The Project Manager may accept Defects. It is suggested that
this is done in conjunction with the Supervisor and Client. Note,
accepting a Defect may also accept a revised programme
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 16
16
Other matters
Clause Issue Action/ to note
70.1, 71.1 Plant and The Project Manager may need to include Plant and Materials
Materials marked marked by the Supervisor in its assessment
by the Supervisor
70.2, 72.1 Project The Project Manager may be asked for permission by the
Manager’s Contractor to remove Plant and Materials from the Working
permission Areas, or leave Equipment in the works
73.1 Objects of value The Project Manager may need to instruct the Contractor how to
deal with objects of value or of historical or other interest found
by the Contractor within the Site
Section 8 Liabilities and The Project Manager will need to check the Contractor's
insurances insurances at commencement of the contract (covered in session
1) and also upon each renewal date. This should continue until
the defects date, or longer for PI insurance
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 17
17
18
Other matters:
Contractor’s proposals to reduce amount paid
• The Contractor may propose changes to the Client’s
Scope to reduce the amount paid to the Contractor (16.1)
• The Project Manager consults with the Client and the
Contractor
• Within 4 weeks the Project Manager
• accepts the proposal and instructs a change to the Scope
• instructs the Contractor to submit a quotation for a proposed
instruction (as in clause 65) or
• informs the Contractor the proposal is not accepted
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 19
19
Other matters:
Contractor’s proposals to reduce amount paid
• The change to the Scope is a compensation event
• For Option A and B, the Prices are reduced by an amount
calculated by multiplying the assessed effect of the
compensation event (the price reduction) by the value
engineering percentage (clause 63.12)
• the Contractor therefore shares in the benefit
• For Options C and D, the Prices are not reduced (clause 63.13)
• since the target total of the Prices is not reduced, the Contractor
therefore shares in the pain/gain benefit
20
Other matters:
Contractor’s proposals to reduce operating cost
• If X21 applies, the Contractor may propose changes to the Client’s Scope
to reduce the cost of operating and maintaining an asset (clause X21.1)
• If the Project Manager is prepared to consider the change, the Contractor
submits a quotation (clause X21.2). There is no basis given for assessing
this quotation; it is not a compensation event
• The Project Manager replies within the period for reply
• accepts the quotation, changes the Scope, Prices, Completion Date and Key
Dates accordingly, and accepts the revised programme, or
• does not accept it, with reasons
• If not accepted, the Project Manager cannot then instruct the change
subsequently, unless it accepts original quotation
21
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 22
22
23
Notifying and Referral has to be made within the Referral to Adjudicator can be made
referring a timescales within the Dispute “at any time” whether or not dispute
dispute Reference Table. If not, the party has gone to Senior Representatives
loses the right to refer to the Senior (W2.2(1))
Representatives, Adjudicator or
tribunal (W1.1, W1.3(1))
Referral to Senior Representatives stated in the Senior Representatives stated in the
Senior Contract Data. They may be replaced Contract Data. They may be replaced
Representatives (W1.1(1)). Dispute must be referred (W2.1(1)). Dispute referred to Senior
to Senior Representatives before Representatives before Adjudicator if
Adjudicator (W1.1(1)) Parties agree (W2.1(1))
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 24
24
Dispute resolution –
W1 and W2 Senior Representatives
Issue Option W1 Option W2
Deadline for Each Party submits statement of case Each Party submits statement of case
providing within one week of notification of within one week of notification of
information dispute to Senior Representatives dispute to Senior Representatives
(W1.1(2)) (W2.1(2))
Effect of Senior Senior Representatives make neither Senior Representatives make neither
Representatives’ recommendations nor decisions. recommendations nor decisions.
involvement Project Manager and Contractor put Project Manager and Contractor put
agreed issues into effect (W1.1(3)) agreed issues into effect (W2.1(3))
Disputing the The dissatisfied Party must issue The dissatisfied Party may issue notice
resolution by the notice of adjudication within 2 weeks of adjudication at any time (W2.2(1))
Senior otherwise it loses the right to
Representatives adjudication or tribunal. Dispute
referred to Adjudicator within 1 week
of notice (W1.3(1))
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 25
25
Deadline for Four weeks but may be extended if 7 days for the referring Party to
providing the Parties and Adjudicator agree provide the referral (W2.3(2)).
information (W1.3(3)) Timetable for further information set
by the Adjudicator to enable a
decision to be given within the overall
time allowed (W2.3(4))
Adjudicator Made within 28 days (W1.3(8)). This Made within 28 days (W2.3(8)). The
decision can be extended by agreement. The decision may be extended by up to 14
Adjudicator’s fees and expenses days. The Adjudicator may allocate its
allocated as per its appointment fees and expenses between the Parties
Effect of the Binding but not final (W1.3(10)). The Binding but not final (W2.3(11)). The
Adjudicator’s dissatisfied Party must notify such dissatisfied Party must notify such
decision within 4 weeks otherwise it loses the within 4 weeks otherwise it loses the
right to tribunal (W1.4(3)) right to tribunal (W2.4(2))
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 26
26
Dispute resolution – W3
• Option requires reference to Dispute Avoidance Board (DAB)
before referral to the tribunal
• W3 does not include for adjudication. As it is written, it would not
be used for any contract which needs to be compliant with the
HGCRA
• The DAB is appointed at the beginning of the contract, and consists
of one or three members as stated in the Contract Data (clause
W3.1(1))
• The DAB members visit the Site at intervals stated in the Contract
Data to enable it to become aware of potential disputes (clause
W3.1(5))
• The DAB should be appointed under NEC Dispute Resolution
Service Contract (clause W3.1(2))
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 27
27
Dispute resolution – W3
Issue Option W3
Notifying and referring a Potential dispute is referred to DAB between 2 and 4 weeks after
dispute notification of issue to the other Party and Project Manager
(W3.2(3))
Action of DAB DAB makes non‐binding recommendation if Parties have not
resolved potential dispute (W3.2(5))
Disputing DAB’s The dissatisfied Party must notify the other Party that it has a
recommendation dispute and intends to refer it to the tribunal within 4 weeks of
provision of the DAB’s recommendation. Otherwise, it loses the
right to refer to tribunal (W3.3(2))
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 28
28
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 29
29
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 30
30
31
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 32
32
33
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 34
34
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 35
35
36
Earlier of
defect
date when
Defects notified: correction
all notified
period defect
Defects
before Completion correction
corrected
period
or defect
after Completion correction
period
before defects date
Latest issue of
• Remember, Supervisor notifies Defects Defects Certificate
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 37
37
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 38
38
39
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 40
40
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 41
41
42
43
44
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 45
45
• Exercise 4.1
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 46
46
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 47
47
• Exercise 4.2
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 48
48
• Exercise 4.3
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 49
49
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 50
50
• identify problems
• educate on the use of the
Ensuring compliance
contract and rationale
• ensure compliance
Educating/ Informing
• maintain the spirit of
mutual trust and co‐operation
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 51
51
2. Educate on the use of Meet with the Finance Director and go through the contract
the contract and – explain about the potential gain share at Completion and
rationale also the scenario where compensation events that cost more
are not revised. This should give the Finance Director a more
balanced view
3. Compliance Encourage the Finance Director to comply with the contract
4. Maintain the spirit of By maintaining a relationship with the Finance Director and
mutual trust and co‐ ensuring payment is made, this should be achieved
operation
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 52
52
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 53
53
Overall summary
• The training programme days have covered the role of
the Project Manager in chronological order
• It is evident that the ECC contains clear processes
• In particular the 3 stimuli to good management (early
warnings, programme and compensation events) are
linked to one another
• Both the programme and compensation events sections
contain defined responses and timescales
The Project Manager’s role is critical to success
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 54
54
Overall summary
• As a suggested ethos, the
Project Manager is perhaps
continually
• educating (what the ECC Nurturing spirit of mutual
trust and collaboration
requires)
• ensuring compliance
with this, and
Ensuring compliance
• nurturing the spirit
of mutual trust
Educating/ Informing
and co‐operation
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 55
55
Overall summary
• No amount of process can guarantee project success
• A successful project requires good process and collaborative
working – the people
• The spirit of mutual trust and co‐operation (clause 10.2) is
vital to success
• The Project Manager’s role is the key role to make sure this all
happens. It should be an ambassador of the contract and
help ensure the process is followed and undertaken in a spirit
of mutual trust and co‐operation
The Project Manager should be an
ambassador of the contract
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 56
56
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 57
57
Assessment
On completion of the classroom training, you will need to
complete an online assessment in two parts, multiple‐
choice and long answer questions.
It can be accessed through the NEC website
(www.neccontract.com), via the My NEC area. You must
complete the assessment within 30‐days of receiving
notification of the assessment after the end of this course.
You will receive all necessary information via email once
we have confirmation of your attendance on this course.
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 58
58
Assessment
Please note
• You must attend all 4 classroom training days consecutively to
be granted access to take the final assessment.
• Failure to submit on the due date will result in failure of the
Accreditation
• Reasonable adjustments may only be considered in
exceptional circumstances (see your delegate guide).
Applications with evidence must be submitted by email for
approval to the NEC (accreditations@neccontract.com)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 59
59
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 60
60
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 61
61
Assessment
• Ensure the answer is comprehensive and covers the
marks for each part of the question
• Answers for each question must be between 750 and
1,500 words, not reaching or exceeding the limit will
result in marks being deducted from your overall score
• Answers must be your own work
• Do the multi‐choice questions as soon as possible to
maximise the time available within the remaining part of
the month for the written questions
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 62
62
63
64
65
Assessment – terminology
Words and phrases NOT to use
• ‘raise’ an early warning
• ‘issue’ an early warning
• ‘raise’ a compensation event
• ‘issue’ a compensation event
• ‘approve’ the programme, Subcontractor, etc
• ‘reject’ an early warning
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 66
66
Assessment
Other things to avoid:
• CDM (applies to the UK) or any other legislation
• Latin (contra proferentem etc)
• Case law
• PRINCE2, Six Sigma etc (Project Management protocols)
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 67
67
L46350 NEC4 ECC Project Manager Accreditation v7.0 Jan 2023 [HK] ©NEC 2023 68
68
Delivering
real value
Contact us
UK/Europe: +44 (0)20 7665 2446 Asia: +852 9320 7694
info@neccontract.com
One Great George Street, London SW1P 3AA
neccontract.com
69
NEC
One Great George Street
Westminster
London SW1P 3AA
United Kingdom