Lusail Plaza Towers Project - BP 12 - Site Quality Walkdown Checklist

Ref. No. : 9205-BP12B-LBQPM-CKL-QL-NS-000-00040 Date: 18-Mar-2024

Location/Area : BP12B Tower & Podiums

Attendees : QA/QC Team from LBQPM, DAR & MMJV

Walkdown No. : MMJV Quality Walkdown No.81

Category (Please Tick)


Reference Documents Evidence Cited (e.g. photo to be provided) Areas of Areas of Non-
S. No. Findings Best Practice
Standard Improvement Concern Compliance
(Compliant)
(AFI) (Observation) (NCR)

Plot 2, Level 06, Roof Level - Hand wheel of the installed


butterfly valve is not accessible. MMJV shall provide
chainwheels for the butterfly valves located on the roof
level, which are positioned more than 2.4 meters above the
floor. Project Specification-200523.13,
1
Section 3.2, E X
As per project specification-200523.13, Section 3.2, E -
Valves shall be provided with chainwheels on operators for
butterfly valves DN 200 and larger and more than 2400 mm
above floor. Extend chains to 1520 mm above finished floor.

Plot 2, Level 06, Roof Level - AHU mouth connection flexible


canvas connection installed is for indoor application. MMJV
2
shall provide weatherproof/fire rated flexible connector for X
the AHU connection in roof top.

LUS-BP12-LBQPM-FMT-PM-00171 Rev.000 21/06/2021 Site Quality Walkdown Checklist


Category (Please Tick)
Reference Documents Evidence Cited (e.g. photo to be provided) Areas of Areas of Non-
S. No. Findings Best Practice
Standard Improvement Concern Compliance
(Compliant)
(AFI) (Observation) (NCR)

Plot 2, Basement 01 - Potable Tank door clashing with the


3
cable tray. X

Plot 2, Level LG - No maintenance access for the installed


FCU in MOI Room & Facility Control Room. MMJV shall
4
ensure that units must be accessible for maintenance and X
servicing purposes.

LUS-BP12-LBQPM-FMT-PM-00171 Rev.000 21/06/2021 Site Quality Walkdown Checklist


Category (Please Tick)
Reference Documents Evidence Cited (e.g. photo to be provided) Areas of Areas of Non-
S. No. Findings Best Practice
Standard Improvement Concern Compliance
(Compliant)
(AFI) (Observation) (NCR)

Plot 2, Level LG - Access door to be provided for MSFD to


access the Heat Sensing Element during inspection and
testing in ICT Room and Electrical Room. Accessing MSFD
from the grilles side is not possible since the Heat Sensor
actuated device is at other side of the damper blades. 9205-BP12B-MMJV-MAT-ME-NS-
5
000-00019 X
As per NFPA-80, unobstructed access shall be provided
through the ceiling or wall to gain access for inspection and
service of the dampers working parts.

Plot 2, Basement 01 - Pressure gauge on the potable water


6
pump in Basement 01 is broken. X

LUS-BP12-LBQPM-FMT-PM-00171 Rev.000 21/06/2021 Site Quality Walkdown Checklist


Category (Please Tick)
Reference Documents Evidence Cited (e.g. photo to be provided) Areas of Areas of Non-
S. No. Findings Best Practice
Standard Improvement Concern Compliance
(Compliant)
(AFI) (Observation) (NCR)

Plot 2, Level LG - Poor workmanship in the installation of


7
cladding on chilled water pipes. X

Plot 2, Level 06, Roof Level - Threaded fasteners when


8 installed and tightened, should protrude a distance of at X
least one thread beyond the top of the nut.

LUS-BP12-LBQPM-FMT-PM-00171 Rev.000 21/06/2021 Site Quality Walkdown Checklist


Category (Please Tick)
Reference Documents Evidence Cited (e.g. photo to be provided) Areas of Areas of Non-
S. No. Findings Best Practice
Standard Improvement Concern Compliance
(Compliant)
(AFI) (Observation) (NCR)

Plot 2, Level LG - Flexible duct support to be provided


9 inorder to avoid sagging and to eliminate air flow X
restrictions.

Plot 2, Level 06, Roof Level - Welding of GI supports for the


chilled water pipe is ongoing without removing the zinc
10 coating from the welded area. Site weld joints were left X
uncoated. Welded joints must be painted with zinc to
protect the welds from corrosion

LUS-BP12-LBQPM-FMT-PM-00171 Rev.000 21/06/2021 Site Quality Walkdown Checklist


Category (Please Tick)
Reference Documents Evidence Cited (e.g. photo to be provided) Areas of Areas of Non-
S. No. Findings Best Practice
Standard Improvement Concern Compliance
(Compliant)
(AFI) (Observation) (NCR)
Plot 2 Podium 2 Level 2 - Rockwool installation at UHPC window
panels are not properly installed. Rockwool materials are of poor
quality.

11 X

12 Plot 2 Podium 2 Level 2 Decking slab -


1. Provide approved Method Statement for installation of
steel decking slab.
2. Water leakage / stain at concrete slab construction joints
were observed.
3. White rust was observed on galvanized steel angles.

LUS-BP12-LBQPM-FMT-PM-00171 Rev.000 21/06/2021 Site Quality Walkdown Checklist