Balance WORKS forcast @ 9.June.2020
Balance WORKS forcast @ 9.June.2020
Balance WORKS forcast @ 9.June.2020
A . Ducting
1 Installation of Duct At roof 80%DONE BALANCE PCS ORDERED WAITING FOR DELIVERY
4 Installation Equipment mouth connection & Return Plenum 0%DONE MOUTH PCS ORDERED WAITING FOR DELIVERY
5 Installation of Flexible duct 0%DONE MOUTH PCS ORDERED WAITING FOR DELIVERY
2 Installation of fresh air supply and return Diffuser 98% DONE ABOVE TICKET COUNTER AREA NO ACCESS TO INSTALL 2 DIFFUSER
3 Installation of Exhaust Grill 0% EXHAUST GRILL IN TOILET ARE NOT YET ORDERED BY K.G
LUSAIL BUS STATION WORK STATUS DATE: 01/09/2021
SL NO DESCRIPTION OF WORK work Remarks
A . Ducting
4 Installation Equipment mouth connection & Return Plenum 95%DONE 3 PIC BALANCE ON GOING
3 Installation of Exhaust Grill 0% EXHAUST GRILL IN TOILET ARE NOT YET ORDERED BY K.G
WAKRA BUS STATION WORK STATUS DATE: 01/09/2021
SL NO DESCRIPTION OF WORK work Remarks
A . Ducting
2 Installation of fresh air supply and return Diffuser 98% DONE ABOVE TICKET COUNTER AREA NO ACCESS TO INSTALL 2 DIFFUSER
3 Installation of Exhaust Grill 0% EXHAUST GRILL IN TOILET ARE NOT YET ORDERED BY K.G
SUDAN BUS STATION WORK STATUS DATE: 01/09/2021
SL NO DESCRIPTION OF WORK work Remarks
A . Ducting
3 Installation of Exhaust Grill 0%DONE EXHAUST GRILL IN TOILET ARE NOT YET ORDERED BY K.G