ABB UNIVERSIT Y & O NLINE ACA DEMY FO R E XCITATIO N AND SYNCHRO NIZATIO N
Course goals
UNITROL® 1010 and UNITROL® 1020 provides a comprehensive range of Automatic Voltage Regulators
and is intended for small generators and industrial synchronous machines. The maximum output
current for continuous operation is 20 ADC. The most advanced microprocessor technology together
with IGBT semiconductor technology allows it to be used in all conceivable areas of application.
The course goal is to learn how to operate, maintain, perform commissioning, and trouble-shoot the
automatic voltage regulator (AVR).
Registration
For registration or enquiries please visit: ABB University & Online Academy for Excitation - Enquiries
Notes
© Copyright 2024 ABB. All rights reserved. Specifications subject to change without notice. 1/4
J1 3 1D - U NI T RO L ® 10 10/ 10 2 0 S E R V IC E A ND CO M M IS SI O N ING
Topics
Topics
– Basics of the synchronous machine
– Duties of excitation system
– Major components of the UNITROL® 1010 and UNITROL® 1020
Operating aspects
– How to use the local control panel
– Start/Stop sequence
– Commands and Indications
– Exercises using the demo equipment
– How to use the PC-tool
– How to install the PC-tool
– How to display signals
– How to change parameters
– How to use the oscilloscope function
– How to configure I/O’s
– How to use the event logger function
– How to tune the closed loop controllers
– How to operate the voltage regulator using the PC-tool
– Exercises using the demo equipment and PC-Tool
© Copyright 2024 ABB. All rights reserved. Specifications subject to change without notice. 2/4
J1 3 1D - U NI T RO L ® 10 10/ 10 2 0 S E R V IC E A ND CO M M IS SI O N ING
D AY 1 | 9:30 AM – 3:30 PM
– Course overview – Modes of operation
– Basics of excitation system – Overview to the various software packages
– Introduction to UNITROL® 1010/20 – Hardware: connection to the remote simulator
– Field of application • SMTS explanation
– Supply modes
D AY 2 | 9:00 AM – 3:30 PM
– Recap day 1 – Exercises using the training unit
– How to connect the UNITROL® 1010/20 – How to use the CMT1000 tool
– Introduction to the training unit (table Model) – Exercises using the CMT-Tool and training unit
used for hands-on part
D AY 3 | 9:00 AM – 3:30 PM
– Recap day 2 – Commissioning aspects
– Software Functions and parameter settings • Safety rules
– Engineering aspects • Step by step procedure
• Technical data • Machine at stand still
• Engineering hints • Machine idle running
• Exercise project engineering • Machine on load
D AY 4 | 9:00 AM – 3:30 PM
– Exercises related to commissioning – Maintenance and trouble shooting
• Tuning PID of the controller using • Recommended maintenance work
oscilloscope function and integrated tunning • Download of new software release
assistant • Trouble shooting procedure
• Testing of the limiter reactive load rejection • Alarm indication
• Testing of reactive power and power factor • Event logger
control
• Testing of the synchronizer function
© Copyright 2024 ABB. All rights reserved. Specifications subject to change without notice. 3/4
—
Contact us