Professional Documents
Culture Documents
Presentation - WTC2023 - Ashish Rawat
Presentation - WTC2023 - Ashish Rawat
• Mumbai Metro Line 3 (MML3) Project is a 33.5km long corridor from Colaba to SEEPZ
• Twin tunnel underground corridor with 27 stations
• Connects 6 Business Districts, 30 recreational facilities & the domestic and International Airports.
• Has several Interchanges with the Western Railway sub-urban network and Mumbai Metro Line-1
Kalbadevi Station Layout
Connecting Adits
Platform Tunnel
Cut & cover box Cut & cover box Widening
• Up Line and Down Line Tunnels were bored through at the first instance and were widened later
after ring removal by conventional drill and blast method
• The Central Cavern was excavated by conventional means of Drilling & Blasting
Importance of Kalbadevi
Kalbadevi Metro station provides direct access to traditional markets and is a hub for
wholesale buyers and thus has the potential of a substantial footfall along MML3.
The Metro Station is expected to bring a new dimension to this area in the form of a
Public Transit leading to major changes in the urban environment of Kalbadevi precinct.
This also calls for a guided urban renewal mechanism which can protect the heritage
value while accommodating the new infrastructure.
Heritage and important places of worship include the renowned Mumbadevi Temple & the
Parsi Fire Temples besides various other places of importance.
Challenges prior to start of construction of Kalbadevi Station
1. Resistance from local populace for demolition of structures and
rehabilitation of the Project Affected Persons
Series of Public hearings were held to build a conducive environment for the
works to start
In-Situ rehabilitation schemes were finalized
In-Situ Rehabilitation
2. Dilapidated structures in close proximity to the excavation
An extensive Building Condition Survey of structures within the Zone of Influence
was conducted prior to the start of the works along with a structural audit of some
critical structures
Some of the structures were even repaired basis the Structural Audit Reports as
a mark of social responsibility
No damage to any structure was imparted due to the construction works carried
out in the vicinity
Bird’s Eye View of Shafts K1 & K2
Shaft K1 Shaft K2
3. Excavation works amidst narrow streets with traffic congestion
a. Noise pollution & Vibration emanating from various metro construction activities
Noise and Vibration Monitoring was carried on which ranged within permissible limits
Drilling & Blasting was not taken up for the Open Excavations due to public sentiments
resulting in delay in shaft excavations
Activities of pile driving & hard rock excavation were limited to daytime which
contributed to the delay
• Extensive seepage into the excavation hampered the progress of the works during the
shaft excavation. A 2m thick band of fractured and weathered rock mass was
encountered at depths of 7m below the Ground Level. Ground Water Table was
recorded between 6.5m to 7m. The water bearing soil strata above expunged water
from this weak zone into the excavation. The Ingress ranged roughly between 200 to
300 litres per minute and at high pressures thus causing delays.
Precautions in the form of Poly Urethane Grout and/or a mixture of cement and
sodium silicate were immediately taken up thus containing the ingress into the
excavation.
After the initial few phases of the heavy ingress, additional grouting measures
were taken up as a precautionary measure through the excavated walls to
consolidate this weaker zone.
Excessive Water Ingress
Start of Excavation Installation of Traffic Decking Deep Excavation Excavation of Central Cavern
and Platform widening
21
MODIFIED CONSTRUCTION SEQUENCE
A change in the construction sequence was necessitated to keep up to
the Project Timelines, which seemed challenging due to the delays in
excavation of the shafts K1 & K2. Excavation for the central cavern, Stage 1 : Marking, Installation of Temporary support at TBM & Excavation of
platform widening and the connecting adits was take up from within the Transition zone at Down line tunnel as per drawing
bored tunnel.
CST STATION GRANT ROAD STATION
Stage 2: Excavation of Adit upto platform level till start of Collar Beam at Upline
station Tunnel
UP LINE TUNNEL
22
Segment Removal from within the Bored Tunnel
5. Blast induced vibration limitation imposed due to the litigation
• As a result of the litigation filed, the limits of blast induced vibrations for the Heritage
Structure were reduced to 2.54mm/sec as against the original set limits of 5mm/sec.
Controlled Blasting measures were put to place keeping in view the restrictions
imposed
Line Drilling at the periphery of the tunnel face consisting of 51mm diameter at a
spacing of 200mm and depths of more than 2m were used to limit the blast
induced vibrations to transmit beyond the excavation boundary
5 numbers of Reamer holes of 102mm diameter were drilled at the centre of the
profile as a provision of free face for the subsequent blasts
Production holes of 32mm diameter of 1.2m length were drilled in a ring pattern
at varied spacing for effective blasting
Vibration Monitoring of the Heritage Structure and other dilapidated structures
above the tunnels was carried out diligently
The vibrations were thus controlled to levels below 1.5mm/sec at the Heritage
Structure
Drilling and Blasting
Line Drilling
Reamer Holes
and Ring
Pattern of
Production
Controlled Blast Pattern for Adits Holes
Ring wise Blasting in Adits and Central Cavern
Platform Widening
6. Space Constraints for Conventional Excavation from within the Bored Tunnel
An effective Space Management Plan to deal with the limited space was
formulated
Rail tracks were shifted in order that both the TBM boring and underground
excavation of the central cavern were carried out without any obstructions
Walkway
Adit opening
from within bored
tunnel
#WTC2023