Client : M/s Jassim & Hamed Bin Jassim Charitable Foundation

Attn. : Mr. Shabeer Basheer – Procurement Officer


Ref. : ST-CVL-PAKLIBRY-186-21
Date : 30-Aug-2021

PROJECT: Civil works in Library – Pakistan School

Wishes from Seylan Tech.

With reference to your enquiry, we are pleased to furnish our special offer for your kind
perusal consideration as per standard manufacturing specification, as follows:
Documents considered for pricing: Provided BOQ

SCOPE OF WORK:

No Description

1 Civil works as per provided BOQ

# For Detailed Scope and the Pricing Breakdown Please Refer attached BOQ

BOQ : Attached

Price : Our price for the whole job (Refer Note) as per attached BOQ’s will be –

QR. ONE HUNDRED AND NINETEEN THOUSAND ONE HUNDRED ONLY.


(QR 119,100.00 /-)

Terms:

- Any works and quantity with addition to the BOQ will be considered as variation.

- Project duration will be counted from the day of receiving LPO.

- Electrical power arrangement by Main contractor.

-Changing of Material or the design by the client after the job execution will be
considered as variation.
- Payment condition: 60% in advance,
30% with Delivery of the Materials to the Site.
Balance with completion of the project

Job Duration: Will be discussed.


(Any Delay in project execution cause of site clearance, Lockdown by authorities will be
adjusted accordingly)

Validity: 30 days from the date of quotation.

We hope that our above offer is in line with your requirements and for any further
clarifications please contact the undersigned.

Thanks & Regards

Jithin Paul

Head of Department
Tender & Estimation
+974 77886477
projectsdoha@seylantech.com
projectseylantech@gmail.com
BOQ
No Description QTY unit Unit Rate Amount
Supply & Installing New Stainless Steel Main
Doors (3000X3000mm) with Frame and Glass
1 2 nos 18,500.00 37,000.00
Work – Both side Entrance and remmoving the
old Doors.

Supply & Installing Floor Tiling – Removing the


2 existing tile and Screeding, Fixing the new tile (Tile 320 SQM 165.00 52,800.00
supplied by Seylan Tech) and removing the debris

Wall, Pillers & Slab Painting & Wall Paper


3 340 SQM 35.00 11,900.00
Application

4 Closing Exixsting AC Openings by block works 6 nos 200.00 1,200.00

Wall Opening & Fixiig new windows with Aluminum


5 4 nos 1,850.00 7,400.00
frame and glass work (1500x1000)

6 Supply & Installing New LED Tube Lights 40 nos 220.00 8,800.00

TOTAL VALUE 119,100.00