Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.

14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA

SECTION 12 22 00 - DRAPERIES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes draperies and drapery tracks.

B. Related Sections include the following:

1. Section 05 50 00 METAL FABRICATIONS for support systems.


2. Division 26 Sections for electrical service and connections for motor operators,
controls, limit switches, and other powered devices and for system disconnect
switches for motorized shade operation.

C. Scope Includes:

1. Compliance with the General Conditions of Contract.


2. Compliance with all current and applicable statutory codes and requirements.
3. Completion of the design, fabrication, supply and installation of all items
specified herein, shown on the Contract Drawings, and as required to provide a
complete installation.
4. Completion of the design and coordination of all interfaces with adjoining
systems and trades prior to the commencement of fabrication.

D. The Owner requires the Contractor to implement practices and procedures to meet the
project's environmental performance goals, which include compliance with the
requirements determined by the Sustainability Consultant’s design documentation
(LEED & WELL), and applicable local authority Green Building Regulation. Specific
project goals that may impact this area of work include, but are not limited to: reduced
impact of construction activities, construction waste recycling, reduction of water and
energy usage, adequate protection for storing materials, use of recycled-content
materials, use of locally manufactured materials, use of low-emitting materials, use of
materials having EPD's, and avoid use of restricted materials. The Contractor shall
ensure that the requirements related to these goals, as defined in individual
specification sections are implemented to the fullest extent. Substitutions, or other
changes to the work proposed by the Contractor or their Subcontractors, shall not be
allowed if such changes compromise the aforementioned environmental goals and
Green Building Regulation compliance.

1. Contractor shall, at all times undertake to ensure that all targeted goals are
achieved. As and when any risks arise that could compromise the achievement of
one or more of the targeted goals, the Contractor shall bring these to the attention
of the Employer's Representative immediately.

DRAPERIES 12 22 00 - 1
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA

1.2 ACTION SUBMITTALS

A. Product Data: Submit copies of manufacturer's specifications and installation


instructions for the drapery.

B. Sustainable Design Submittals: Refer to Division 01 Section 01 81 13 "Sustainable


Design Requirements."

C. Shop Drawings: Submit shop drawings showing locations of each drapery item,
dimensioned plans and elevations, large-scale details, attachment devices, and other
components. Plans shall be drawn at a scale of not less than (1:50). Elevations shall be
drawn at a scale of not less than (1:25). Details shall be drawn at a scale of not less
than (1:5).

1. Tracks: Show installation and anchorage details, and locations of controls.


2. Draperies: Show sizes, locations, and details of installation.

1.3 INFORMATIONAL SUBMITTALS

A. Embodied Carbon Submittals:

1. Completed Environmental Product Declaration Reporting Form for each


principal product type in this Section.
2. For products with completed Environmental Product Declaration Reporting
Forms claiming availability of an applicable EPD, provide the Product-Specific
or Industry-Wide Type III Environmental Product Declaration (EPD) in
compliance with ISO 14025.

1.4 CLOSEOUT SUBMITTALS

A. Operation and Maintenance (O&M) Manuals: Include component list with the
manufacturer’s reference numbers, descriptions of materials and procedures
forrepairing and cleaning of finishes, and cleaning frequency.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: For draperies and tracks, fabricator of draperies.

B. Source Limitations: For draperies, obtain each color and pattern of fabric and trim
from one dye lot.

C. Fire-Test-Response Characteristics: For fabrics treated with fire retardants, provide


products that pass NFPA 701 as determined by testing of fabrics that were treated using
treatment-application method intended for use for this Project by a testing and
inspecting agency acceptable to authorities having jurisdiction.

DRAPERIES 12 22 00 - 2
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA

1.6 PROJECT CONDITIONS

A. Field Measurements: Verify dimensions by field measurements before drapery


fabrication and indicate measurements on Shop Drawings.

B. Scheduling: Do not deliver or install draperies until after other finish work, including
painting, is complete and spaces are otherwise ready for occupancy.

PART 2 - PRODUCTS

2.1 DRAPERY TRACKS

A. Electrically Operated Track:

1. Basis-of-Design Manufacturer and Product: Serena 95 by Euro Systems.

a. Mounting: Ceiling.
b. Operation: Electrically operated drapery track system.

1) Draw: Two way, center opening.

c. Carrier Spacing: Manufacturer's standard spacing.


d. Master Carriers: Butt.

2. Subject to compliance with requirements, provide the basis-of-design product, or


a comparable product, acceptable to the Architect, by one of the following:

a. Silent Gliss USA Inc.


b. Kirsch.

3. Construction: Extruded aluminum, slotted for mounting at interval of not more


than 610 mm on center.

a. Lengths and Configurations: As indicated on Drawings.


b. Support Capability: Weight of drapery indicated mounted on track length
indicated.
c. Finish: White baked enamel.

4. Mounting Brackets: Aluminum, of type suitable for fastening track to surface


indicated and designed to support weight of track assembly and drapery plus
force applied to operate track.

a. Mounting Surface: As indicated on Drawings.

DRAPERIES 12 22 00 - 3
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA

5. Installation Fasteners: Sized to support track assembly and drapery, and


fabricated from metal compatible with track, brackets, and supporting
construction. Provide two fasteners to fasten each bracket to supporting
construction.

2.2 DRAPERIES

A. Fabricators: Subject to compliance with requirements, provide drapery fabrication by


the following or equal:

1. Euro Systems LLC, Suite No. 239, Al Shafar Investment Building, Sheikh Zayed
Road, Al Quoz, P.O.Box: 212688, Dubai, United Arab Emirates, T:+971 4 380
7744, E: info@eurosystems.com.

B. Drapery:

1. Heading:

a. Ripplefold Pleats.
b. Heading Accessories: Woven snap tape.

2. Fullness: 200 percent.


3. Drapery Fabric: As indicated on finish legend on Drawings.
4. [Lining Fabric: As indicated on finish legend on Drawings.]
5. Hem Weights: Tape type (string weights).

2.3 DRAPERY FABRICATION

A. Fabricate draperies in heading styles and fullnesses indicated. Fabricate headings to


stand erect. If less than a full width of fabric is required to produce panel of specified
fullness, use equal widths of not less than one-half width of fabric located at ends of
panel.

1. Center-Opening Draperies: Add 254 mm to overall width for overlap.

B. Seams: Sew vertical seams with twin-needle sewing machine with selvage trimmed
and overlocked. Join widths so that patterns match and vertical seams lay flat and
straight without puckering. Horizontal seams are not acceptable.

C. Side Hems: Double-turned, 38-mm- wide hems consisting of three layers of fabric, and
blindstitched so that stitches are not visible on face of drapery.

D. Bottom Hems: Double-turned, 102-mm- wide hems consisting of three layers of fabric,
and weighted and blindstitched so that weights and stitches are not visible on face of
drapery.

DRAPERIES 12 22 00 - 4
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA

E. Linings: Equal to widths of drapery fabric and joined to drapery fabric at top by inside
invisible seam, and hand stitched at side hems and shadowed with 38-mm return of
face fabric.

1. Bottom Hem: Hem separately from drapery fabric.

PART 3 - EXECUTION

3.1 DRAPERY TRACK INSTALLATION

A. Install track systems according to manufacturer's written instructions, level and plumb,
and at height and location in relation to adjoining openings as indicated on Drawings.

B. Isolate metal parts of tracks and brackets from concrete, masonry, and mortar to
prevent galvanic action. Use tape or another method recommended in writing by track
manufacturer.

3.2 DRAPERY INSTALLATION

A. Where draperies abut overhead construction, hang draperies so that clearance between
headings and overhead construction is 6.4 mm.

B. Where draperies extend to floor, install so that bottom hems clear finished floor by not
more than 25 mm and not less than 13 mm.

3.3 ADJUSTING

A. After hanging draperies, test and adjust each track to produce unencumbered, smooth
operation.

B. Steam and dress down draperies as required to produce crease- and wrinkle-free
installation.

C. Remove and replace draperies that are stained or soiled.

END OF SECTION

DRAPERIES 12 22 00 - 5
Copyright 2022 Gensler