SECTION 12 48 53 - AREA RUGS
SECTION 12 48 53 - AREA RUGS
14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA
PART 1 - GENERAL
1.1 SUMMARY
B. Scope Includes:
C. The Owner requires the Contractor to implement practices and procedures to meet the
project's environmental performance goals, which include compliance with the
requirements determined by the Sustainability Consultant’s design documentation
(LEED & WELL), and applicable local authority Green Building Regulation. Specific
project goals that may impact this area of work include, but are not limited to: reduced
impact of construction activities, construction waste recycling, reduction of water and
energy usage, adequate protection for storing materials, use of recycled-content
materials, use of locally manufactured materials, use of low-emitting materials, use of
materials having EPD's, and avoid use of restricted materials. The Contractor shall
ensure that the requirements related to these goals, as defined in individual
specification sections are implemented to the fullest extent. Substitutions, or other
changes to the work proposed by the Contractor or their Subcontractors, shall not be
allowed if such changes compromise the aforementioned environmental goals and
Green Building Regulation compliance.
1. Contractor shall, at all times undertake to ensure that all targeted goals are
achieved. As and when any risks arise that could compromise the achievement of
one or more of the targeted goals, the Contractor shall bring these to the attention
of the Employer's Representative immediately.
1.2 STANDARDS
A. Except as modified by governing codes and by the Contract Documents, comply with
the applicable provisions and recommendations of the following:
AREA RUGS 12 48 53 - 1
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA
1. Seam locations.
2. Pattern type, repeat, location, direction, and starting point.
3. Pile direction.
4. Insets and borders.
D. Samples: For each for each rug and exposed accessory and for each color and pattern
required.
C. Product Schedule: Use same room and product designations indicated on Drawings
and in schedules.
A. Maintenance data.
B. Operation and Maintenance (O&M) Manuals: Include component list with the
manufacturer’s reference numbers, descriptions of materials and procedures
forrepairing and cleaning of finishes, and cleaning frequency.
AREA RUGS 12 48 53 - 2
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA
B. Environmental Limitations: Do not install rug until wet work in spaces is complete and
dry, and ambient temperature and humidity conditions are maintained at the levels
indicated for Project when occupied for its intended use.
1.9 WARRANTY
PART 2 - PRODUCTS
AREA RUGS 12 48 53 - 3
Copyright 2022 Gensler
Gensler 18 November 2022 Riyad Bank HQ, KAFD 1.14
064.1240.000 Interior Design Specification Riyadh, Ar Riyad
Stage 4 - Detailed Design Rev 01 KSA
PART 3 - EXECUTION
3.1 INSTALLATION
END OF SECTION
AREA RUGS 12 48 53 - 4
Copyright 2022 Gensler