(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level.

3) Page 40 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
On-Off Valve (Gate)
S00.03.PCI01.1210 On-Off Valve (Gate) - Manufacturing 224 15-Apr-25 24-Nov-25 On-Off Valve (Gate) - Manufacturing
S00.03.PCI01.1220 On-Off Valve (Gate) - Delivery 56 25-Nov-25 19-Jan-26 On-Off Valve (Gate) - Delivery
Motor Operated Valve (Globe)
S00.03.PCI01.1310 Motor Operated Valve (Globe) - Manufacturing 224 29-Apr-25 08-Dec-25 Motor Operated Valve (Globe) - Manufacturing
S00.03.PCI01.1320 Motor Operated Valve (Globe) - Delivery 56 09-Dec-25 02-Feb-26 Motor Operated Valve (Globe) - Delivery
Control Valve & PCV (Globe)
S00.03.PCI01.1410 Control Valve & PCV (Globe) - Manufacturing 224 15-Apr-25 24-Nov-25 Control Valve & PCV (Globe) - Manufacturing
S00.03.PCI01.1420 Control Valve & PCV (Globe) - Delivery 56 25-Nov-25 19-Jan-26 Control Valve & PCV (Globe) - Delivery
Control Valve (Butterfly)
S00.03.PCI01.1510 Control Valve (Butterfly) - Manufacturing 224 29-Apr-25 08-Dec-25 Control Valve (Butterfly) - Manufacturing
S00.03.PCI01.1520 Control Valve (Butterfly) - Delivery 56 09-Dec-25 02-Feb-26 Control Valve (Butterfly) - Delivery
Pressure Relief Valve (with Thermal Relief Valve)
S00.03.PCI01.1610 Pressure Relief Valve (with Thermal Relief Valve) - Manufacturing 224 29-Apr-25 08-Dec-25 Pressure Relief Valve (with Thermal Relief Valve) - Manufacturing
S00.03.PCI01.1620 Pressure Relief Valve (with Thermal Relief Valve) - Delivery 56 09-Dec-25 02-Feb-26 Pressure Relief Valve (with Thermal Relief Valve) - Delivery
Ultrasonic Flowmeter
S00.03.PCI01.1910 Ultrasonic Flowmeter - Manufacturing 224 03-Jun-25 12-Jan-26 Ultrasonic Flowmeter - Manufacturing
S00.03.PCI01.1920 Ultrasonic Flowmeter - Delivery 56 13-Jan-26 09-Mar-26 Ultrasonic Flowmeter - Delivery
Pre-Assembled Building (PAB)
S00.03.PCI01.2010 Pre-Assembled Building (PAB) - Manufacturing 245 03-Jun-25 02-Feb-26 Pre-Assembled Building (PAB) - Manufacturing
S00.03.PCI01.2020 Pre-Assembled Building (PAB) - Delivery 56 03-Feb-26 30-Mar-26 Pre-Assembled Building (PAB) - Delivery
Transmitters
S00.03.PCI02.0110 Transmitters - Manufacturing 224 15-Apr-25 24-Nov-25 Transmitters - Manufacturing
S00.03.PCI02.0120 Transmitters - Delivery 56 25-Nov-25 19-Jan-26 Transmitters - Delivery
Level Gauge & Sight Glass
S00.03.PCI02.0210 Level Gauge & Sight Glass - Manufacturing 224 03-Jun-25 12-Jan-26 Level Gauge & Sight Glass - Manufacturing
S00.03.PCI02.0220 Level Gauge & Sight Glass - Delivery 56 13-Jan-26 09-Mar-26 Level Gauge & Sight Glass - Delivery
Level Transmitter
S00.03.PCI02.0310 Level Transmitter - Manufacturing 224 17-Jun-25 26-Jan-26 Level Transmitter - Manufacturing
S00.03.PCI02.0320 Level Transmitter - Delivery 56 27-Jan-26 23-Mar-26 Level Transmitter - Delivery
Flow Element
S00.03.PCI02.0410 Flow Element - Manufacturing 224 03-Jun-25 12-Jan-26 Flow Element - Manufacturing
S00.03.PCI02.0420 Flow Element - Delivery 56 13-Jan-26 09-Mar-26 Flow Element - Delivery
Local Gauge
S00.03.PCI02.0510 Local Gauge - Manufacturing 224 17-Jun-25 26-Jan-26 Local Gauge - Manufacturing
S00.03.PCI02.0520 Local Gauge - Delivery 56 27-Jan-26 23-Mar-26 Local Gauge - Delivery
Gas Detector, Horn & Beacon
S00.03.PCI02.0610 Gas Detector, Horn & Beacon - Manufacturing 224 17-Jun-25 26-Jan-26 Gas Detector, Horn & Beacon - Manufacturing
S00.03.PCI02.0620 Gas Detector, Horn & Beacon - Delivery 56 27-Jan-26 23-Mar-26 Gas Detector, Horn & Beacon - Delivery
Rotameter
S00.03.PCI02.0710 Rotameter - Manufacturing 224 17-Jun-25 26-Jan-26 Rotameter - Manufacturing
S00.03.PCI02.0720 Rotameter - Delivery 56 27-Jan-26 23-Mar-26 Rotameter - Delivery
HVAC
HVAC Equipment
S00.03.PHV01.0110 HVAC Equipment - Manufacturing 182 19-Nov-24 19-May-25 HVAC Equipment - Manufacturing
S00.03.PHV01.0120 HVAC Equipment - Delivery 14 20-May-25 02-Jun-25 HVAC Equipment - Delivery
HVAC Control System
S00.03.PHV01.0210 HVAC Control System - Manufacturing 203 31-Dec-24 21-Jul-25 HVAC Control System - Manufacturing
S00.03.PHV01.0220 HVAC Control System - Delivery 14 22-Jul-25 04-Aug-25 HVAC Control System - Delivery
Fire Fighting & Safety
Fire Fighting Equipment
S00.03.PSE01.0110 Fire Fighting Equipment - Manufacturing 126 28-Jan-25 02-Jun-25 Fire Fighting Equipment - Manufacturing
S00.03.PSE01.0120 Fire Fighting Equipment - Delivery 56 03-Jun-25 28-Jul-25 Fire Fighting Equipment - Delivery
Construction
Common
Site Preparation
Site Survey & Site Preparation
Temporary Facilities
S00.04.CSP01.1110 Temporary Facilities 210 01-Aug-23 01-Apr-24 Temporary Facilities
Survey
S00.04.CSP02.1110 Soil Investigation 54 27-Apr-24 27-Jun-24 Soil Investigation
GOSP Train 1 & Crude Stabilization / Storage
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 41 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
CCB & Maintenance Building
Architecture
Reinforced Concrete Building
S90.21.CAR01.1110 (Central Control Building) Substructure 78 01-Oct-24 30-Dec-24 (Central Control Building) Substructure
S90.21.CAR01.1120 (Central Control Building) Superstructure (Wall / Roof) 180 31-Dec-24 28-Jul-25 (Central Control Building) Superstructure (Wall / Roof)
S90.21.CAR01.1130 (Central Control Building) Interior Work 78 29-Jul-25 27-Oct-25 (Central Control Building) Interior Work
S90.21.CAR01.1140 (Central Control Building) Finishing Work 186 28-Oct-25 01-Jun-26 (Central Control Building) Finishing Work
S90.21.CAR01.2110 (Prayer Building-01 / PR-01) Substructure 42 28-Oct-25 15-Dec-25 (Prayer Building-01 / PR-01) Substructure
S90.21.CAR01.2120 (Prayer Building-01 / PR-01) Superstructure (Wall / Roof) 102 16-Dec-25 13-Apr-26 (Prayer Building-01 / PR-01) Superstructure (Wall / Roof)
S90.21.CAR01.2130 (Prayer Building-01 / PR-01) Interior Work 42 14-Apr-26 01-Jun-26 (Prayer Building-01 / PR-01) Interior Work
S90.21.CAR01.2140 (Prayer Building-01 / PR-01) Finishing Work 132 02-Jun-26 02-Nov-26 (Prayer Building-01 / PR-01) Finishing Work
HVAC
HVAC System
S90.21.CHV01.1110 (Central Control Building) HVAC Equipment - Installation 42 30-Sep-25 17-Nov-25 (Central Control Building) HVAC Equipment - Installation
S90.21.CHV01.1120 (Central Control Building) HVAC Duct - Installation 78 30-Sep-25 29-Dec-25 (Central Control Building) HVAC Duct - Installation
S90.21.CHV01.1130 (Central Control Building) HVAC Piping - Installation 54 18-Nov-25 19-Jan-26 (Central Control Building) HVAC Piping - Installation
S90.21.CHV01.1140 (Central Control Building) HVAC Control System - Installation 66 18-Nov-25 02-Feb-26 (Central Control Building) HVAC Control System - Installation
S90.21.CHV01.1150 (Central Control Building) HVAC System - SAT 24 03-Feb-26 02-Mar-26 (Central Control Building) HVAC System - SAT
S90.21.CHV01.2110 (Prayer Building-01 / PR-01) HVAC Equipment - Installation 36 02-Jun-26 13-Jul-26 (Prayer Building-01 / PR-01) HVAC Equipment - Installation
S90.21.CHV01.2120 (Prayer Building-01 / PR-01) HVAC Duct - Installation 54 02-Jun-26 03-Aug-26 (Prayer Building-01 / PR-01) HVAC Duct - Installation
S90.21.CHV01.2130 (Prayer Building-01 / PR-01) HVAC Piping - Installation 42 14-Jul-26 31-Aug-26 (Prayer Building-01 / PR-01) HVAC Piping - Installation
S90.21.CHV01.2150 (Prayer Building-01 / PR-01) HVAC System - SAT 24 01-Sep-26 28-Sep-26 (Prayer Building-01 / PR-01) HVAC System - SAT
Plumbing System
S90.21.CHV02.1110 (Central Control Building) U/G Plumbing Piping - Installation 18 05-Nov-24 25-Nov-24 (Central Control Building) U/G Plumbing Piping - Installation
S90.21.CHV02.1120 (Central Control Building) A/G Plumbing Piping - Installation 66 18-Nov-25 02-Feb-26 (Central Control Building) A/G Plumbing Piping - Installation
S90.21.CHV02.1130 (Central Control Building) Plumbing Equipment - Installation 30 30-Dec-25 02-Feb-26 (Central Control Building) Plumbing Equipment - Installation
S90.21.CHV02.1140 (Central Control Building) Plumbing System - SAT 24 03-Feb-26 02-Mar-26 (Central Control Building) Plumbing System - SAT
S90.21.CHV02.2110 (Prayer Building-01 / PR-01) U/G Plumbing Piping - Installation 12 25-Nov-25 08-Dec-25 (Prayer Building-01 / PR-01) U/G Plumbing Piping - Installation
S90.21.CHV02.2120 (Prayer Building-01 / PR-01) A/G Plumbing Piping - Installation 42 14-Jul-26 31-Aug-26 (Prayer Building-01 / PR-01) A/G Plumbing Piping - Installation
S90.21.CHV02.2130 (Prayer Building-01 / PR-01) Plumbing Equipment - Installation 24 04-Aug-26 31-Aug-26 (Prayer Building-01 / PR-01) Plumbing Equipment - Installation
S90.21.CHV02.2140 (Prayer Building-01 / PR-01) Plumbing System - SAT 24 01-Sep-26 28-Sep-26 (Prayer Building-01 / PR-01) Plumbing System - SAT
Rotating Equipment
Pump
S90.21.CMR02.1147 [S93-G-0718 A/B/S] Sewage Lift Station 1 Pump 4 23-Sep-25 27-Sep-25 [S93-G-0718 A/B/S] Sewage Lift Station 1 Pump
S90.21.CMR02.1148 [S93-G-0719 A/B/S] Sewage Lift Station 2 Pump 4 23-Sep-25 27-Sep-25 [S93-G-0719 A/B/S] Sewage Lift Station 2 Pump
Packaged Equipment
S90.21.CMR06.1184 [S90-U-XXX9] 15T Overhead Crane for Mechanical Workshop 4 27-Aug-25 31-Aug-25 [S90-U-XXX9] 15T Overhead Crane for Mechanical Workshop
S90.21.CMR06.1185 [S90-U-XX10] 5T Overhead Crane for Instrument Workshop 4 27-Aug-25 31-Aug-25 [S90-U-XX10] 5T Overhead Crane for Instrument Workshop
S90.21.CMR06.1186 [S90-U-XX11] 5T Overhead Crane for Electrical/PM Workshop 4 27-Aug-25 31-Aug-25 [S90-U-XX11] 5T Overhead Crane for Electrical/PM Workshop
S90.21.CMR07.1170 [S93-U-0706] Sanitary Odour Control Unit 1 4 04-Nov-25 08-Nov-25 [S93-U-0706] Sanitary Odour Control Unit 1
S90.21.CMR07.1171 [S93-U-0707] Sanitary Odour Control Unit 2 4 04-Nov-25 08-Nov-25 [S93-U-0707] Sanitary Odour Control Unit 2
Electrical
Cabling Work (Tray / Pulling & Termination)
S90.21.CEL01.1110 (Central Control Building) Electrical Cable Tray & Conduit 108 29-Jul-25 01-Dec-25 (Central Control Building) Electrical Cable Tray & Conduit
S90.21.CEL01.1120 (Central Control Building) Electrical Cable Pulling & Termination 144 02-Sep-25 16-Feb-26 (Central Control Building) Electrical Cable Pulling & Termination
Switchgear & MCC (Motor Control Center)
S90.21.CEL03.1210 (Central Control Building) Electrical Panel - Installation 144 28-Oct-25 13-Apr-26 (Central Control Building) Electrical Panel - Installation
UPS & DC System
S90.21.CEL04.1110 (Central Control Building) UPS & DC System - Installation 54 28-Oct-25 29-Dec-25 (Central Control Building) UPS & DC System - Installation
S90.21.CEL04.1120 (Central Control Building) UPS & DC System - Test 24 30-Dec-25 26-Jan-26 (Central Control Building) UPS & DC System - Test
Lighting System
S90.21.CEL01.2110 (Prayer Building-01 / PR-01) Electrical Cable Tray & Conduit 108 14-Apr-26 17-Aug-26 (Prayer Building-01 / PR-01) Electrical Cable Tray & Conduit
S90.21.CEL01.2120 (Prayer Building-01 / PR-01) Electrical Cable Pulling & Termination 108 26-May-26 28-Sep-26 (Prayer Building-01 / PR-01) Electrical Cable Pulling & Termination
S90.21.CEL05.1110 (Central Control Building) Lighting System - Installation 105 28-Oct-25 26-Feb-26 (Central Control Building) Lighting System - Installation
S90.21.CEL05.1120 (Central Control Building) Grounding - Installation 288 31-Dec-24 01-Dec-25 (Central Control Building) Grounding - Installation
S90.21.CEL05.2110 (Prayer Building-01 / PR-01) Lighting System - Installation 132 02-Jun-26 02-Nov-26 (Prayer Building-01 / PR-01) Lighting System - Installation
S90.21.CEL05.2120 (Prayer Building-01 / PR-01) Grounding - Installation 186 16-Dec-25 20-Jul-26 (Prayer Building-01 / PR-01) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S90.21.CCI01.1110 (Central Control Building) I&C Cable Tray & Conduit 132 29-Jul-25 29-Dec-25 (Central Control Building) I&C Cable Tray & Conduit
S90.21.CCI01.1120 (Central Control Building) I&C Cable Pulling & Termination 156 02-Sep-25 02-Mar-26 (Central Control Building) I&C Cable Pulling & Termination
PCS (MAC) & Instrument Panel
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 42 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S90.21.CCI03.1110 (Central Control Building) PCS - Installation 108 28-Oct-25 02-Mar-26 (Central Control Building) PCS - Installation
S90.21.CCI03.1120 (Central Control Building) PCS - Test 54 03-Mar-26 04-May-26 (Central Control Building) PCS - Test
Main Intake Substation
Architecture
Reinforced Concrete Building
S90.22.CAR01.1110 (230kV GIS Receiving Substation) Substructure 180 30-Apr-24 25-Nov-24 (230kV GIS Receiving Substation) Substructure
S90.22.CAR01.1120 (230kV GIS Receiving Substation) Superstructure (Wall / Roof) 324 15-Oct-24 27-Oct-25 (230kV GIS Receiving Substation) Superstructure (Wall / Roof)
S90.22.CAR01.1130 (230kV GIS Receiving Substation) Interior Work 54 28-Oct-25 29-Dec-25 (230kV GIS Receiving Substation) Interior Work
S90.22.CAR01.1140 (230kV GIS Receiving Substation) Finishing Work 288 30-Dec-25 30-Nov-26 (230kV GIS Receiving Substation) Finishing Work
S90.22.CAR01.2110 (Main Substation 01 / MS-01) Substructure 60 22-Oct-24 30-Dec-24 (Main Substation 01 / MS-01) Substructure
S90.22.CAR01.2120 (Main Substation 01 / MS-01) Superstructure (Wall / Roof) 156 31-Dec-24 30-Jun-25 (Main Substation 01 / MS-01) Superstructure (Wall / Roof)
S90.22.CAR01.2130 (Main Substation 01 / MS-01) Interior Work 54 01-Jul-25 01-Sep-25 (Main Substation 01 / MS-01) Interior Work
S90.22.CAR01.2140 (Main Substation 01 / MS-01) Finishing Work 210 02-Sep-25 04-May-26 (Main Substation 01 / MS-01) Finishing Work
S90.22.CAR01.3110 (Main Substation 02 / MS-02) Substructure 60 22-Oct-24 30-Dec-24 (Main Substation 02 / MS-02) Substructure
S90.22.CAR01.3120 (Main Substation 02 / MS-02) Superstructure (Wall / Roof) 156 31-Dec-24 30-Jun-25 (Main Substation 02 / MS-02) Superstructure (Wall / Roof)
S90.22.CAR01.3130 (Main Substation 02 / MS-02) Interior Work 54 01-Jul-25 01-Sep-25 (Main Substation 02 / MS-02) Interior Work
S90.22.CAR01.3140 (Main Substation 02 / MS-02) Finishing Work 210 02-Sep-25 04-May-26 (Main Substation 02 / MS-02) Finishing Work
S90.22.CAR01.4110 (EDG Building / EDG-30) Substructure 42 28-Oct-25 15-Dec-25 (EDG Building / EDG-30) Substructure
S90.22.CAR01.4120 (EDG Building / EDG-30) Superstructure (Wall / Roof) 90 16-Dec-25 30-Mar-26 (EDG Building / EDG-30) Superstructure (Wall / Roof)
S90.22.CAR01.4130 (EDG Building / EDG-30) Interior Work 24 31-Mar-26 27-Apr-26 (EDG Building / EDG-30) Interior Work
S90.22.CAR01.4140 (EDG Building / EDG-30) Finishing Work 132 28-Apr-26 28-Sep-26 (EDG Building / EDG-30) Finishing Work
S90.22.CAR01.5110 (EDG Building / EDG-20) Substructure 42 03-Jun-25 21-Jul-25 (EDG Building / EDG-20) Substructure
S90.22.CAR01.5120 (EDG Building / EDG-20) Superstructure (Wall / Roof) 90 22-Jul-25 03-Nov-25 (EDG Building / EDG-20) Superstructure (Wall / Roof)
S90.22.CAR01.5130 (EDG Building / EDG-20) Interior Work 24 04-Nov-25 01-Dec-25 (EDG Building / EDG-20) Interior Work
S90.22.CAR01.5140 (EDG Building / EDG-20) Finishing Work 132 02-Dec-25 04-May-26 (EDG Building / EDG-20) Finishing Work
S90.22.CAR01.6110 (EDG Building / EDG-21) Substructure 42 03-Jun-25 21-Jul-25 (EDG Building / EDG-21) Substructure
S90.22.CAR01.6120 (EDG Building / EDG-21) Superstructure (Wall / Roof) 90 22-Jul-25 03-Nov-25 (EDG Building / EDG-21) Superstructure (Wall / Roof)
S90.22.CAR01.6130 (EDG Building / EDG-21) Interior Work 24 04-Nov-25 01-Dec-25 (EDG Building / EDG-21) Interior Work
S90.22.CAR01.6140 (EDG Building / EDG-21) Finishing Work 132 02-Dec-25 04-May-26 (EDG Building / EDG-21) Finishing Work
Reinforced Concrete Structure
S90.22.CAR02.1110 (230kV GIS Receiving Substation) Transformer Foundation 54 28-Oct-25 29-Dec-25 (230kV GIS Receiving Substation) Transformer Foundation
S90.22.CAR02.1120 (230kV GIS Receiving Substation) Firewall Structure 42 30-Dec-25 16-Feb-26 (230kV GIS Receiving Substation) Firewall Structure
S90.22.CAR02.1130 (230kV GIS Receiving Substation) Firewall Finishing Work 42 28-Apr-26 15-Jun-26 (230kV GIS Receiving Substation) Firewall Finishing Work
S90.22.CAR02.2110 (Main Substation 01 / MS-01) Transformer Foundation 54 01-Jul-25 01-Sep-25 (Main Substation 01 / MS-01) Transformer Foundation
S90.22.CAR02.2120 (Main Substation 01 / MS-01) Firewall Structure 42 02-Sep-25 20-Oct-25 (Main Substation 01 / MS-01) Firewall Structure
S90.22.CAR02.2130 (Main Substation 01 / MS-01) Firewall Finishing Work 42 30-Dec-25 16-Feb-26 (Main Substation 01 / MS-01) Firewall Finishing Work
S90.22.CAR02.3110 (Main Substation 02 / MS-02) Transformer Foundation 54 01-Jul-25 01-Sep-25 (Main Substation 02 / MS-02) Transformer Foundation
S90.22.CAR02.3120 (Main Substation 02 / MS-02) Firewall Structure 42 02-Sep-25 20-Oct-25 (Main Substation 02 / MS-02) Firewall Structure
S90.22.CAR02.3130 (Main Substation 02 / MS-02) Firewall Finishing Work 42 30-Dec-25 16-Feb-26 (Main Substation 02 / MS-02) Firewall Finishing Work
HVAC
HVAC System
S90.22.CHV01.1110 (230kV GIS Receiving Substation) HVAC Equipment - Installation 84 28-Oct-25 02-Feb-26 (230kV GIS Receiving Substation) HVAC Equipment - Installation
S90.22.CHV01.1120 (230kV GIS Receiving Substation) HVAC Duct - Installation 186 28-Oct-25 01-Jun-26 (230kV GIS Receiving Substation) HVAC Duct - Installation
S90.22.CHV01.1130 (230kV GIS Receiving Substation) HVAC Piping - Installation 102 03-Feb-26 01-Jun-26 (230kV GIS Receiving Substation) HVAC Piping - Installation
S90.22.CHV01.1140 (230kV GIS Receiving Substation) HVAC Control System - Installation 132 30-Dec-25 01-Jun-26 (230kV GIS Receiving Substation) HVAC Control System - Installation
S90.22.CHV01.1150 (230kV GIS Receiving Substation) HVAC System - SAT 30 04-May-27 07-Jun-27 (230kV GIS Receiving Substation) HVAC System - SAT
S90.22.CHV01.2110 (Main Substation 01 / MS-01) HVAC Equipment - Installation 42 01-Jul-25 18-Aug-25 (Main Substation 01 / MS-01) HVAC Equipment - Installation
S90.22.CHV01.2120 (Main Substation 01 / MS-01) HVAC Duct - Installation 108 01-Jul-25 03-Nov-25 (Main Substation 01 / MS-01) HVAC Duct - Installation
S90.22.CHV01.2130 (Main Substation 01 / MS-01) HVAC Piping - Installation 54 19-Aug-25 20-Oct-25 (Main Substation 01 / MS-01) HVAC Piping - Installation
S90.22.CHV01.2140 (Main Substation 01 / MS-01) HVAC Control System - Installation 78 02-Sep-25 01-Dec-25 (Main Substation 01 / MS-01) HVAC Control System - Installation
S90.22.CHV01.2150 (Main Substation 01 / MS-01) HVAC System - SAT 24 02-Dec-25 29-Dec-25 (Main Substation 01 / MS-01) HVAC System - SAT
S90.22.CHV01.3110 (Main Substation 02 / MS-02) HVAC Equipment - Installation 42 01-Jul-25 18-Aug-25 (Main Substation 02 / MS-02) HVAC Equipment - Installation
S90.22.CHV01.3120 (Main Substation 02 / MS-02) HVAC Duct - Installation 108 01-Jul-25 03-Nov-25 (Main Substation 02 / MS-02) HVAC Duct - Installation
S90.22.CHV01.3130 (Main Substation 02 / MS-02) HVAC Piping - Installation 54 19-Aug-25 20-Oct-25 (Main Substation 02 / MS-02) HVAC Piping - Installation
S90.22.CHV01.3140 (Main Substation 02 / MS-02) HVAC Control System - Installation 78 02-Sep-25 01-Dec-25 (Main Substation 02 / MS-02) HVAC Control System - Installation
S90.22.CHV01.3150 (Main Substation 02 / MS-02) HVAC System - SAT 24 02-Dec-25 29-Dec-25 (Main Substation 02 / MS-02) HVAC System - SAT
S90.22.CHV01.4110 (EDG Building / EDG-30) HVAC Equipment - Installation 12 28-Apr-26 11-May-26 (EDG Building / EDG-30) HVAC Equipment - Installation
S90.22.CHV01.4120 (EDG Building / EDG-30) HVAC Duct - Installation 24 28-Apr-26 25-May-26 (EDG Building / EDG-30) HVAC Duct - Installation
S90.22.CHV01.4130 (EDG Building / EDG-30) HVAC Piping - Installation 24 12-May-26 08-Jun-26 (EDG Building / EDG-30) HVAC Piping - Installation
S90.22.CHV01.4140 (EDG Building / EDG-30) HVAC Control System - Installation 24 28-Apr-26 25-May-26 (EDG Building / EDG-30) HVAC Control System - Installation
S90.22.CHV01.4150 (EDG Building / EDG-30) HVAC System - SAT 12 09-Jun-26 22-Jun-26 (EDG Building / EDG-30) HVAC System - SAT
S90.22.CHV01.5110 (EDG Building / EDG-20) HVAC Equipment - Installation 12 02-Dec-25 15-Dec-25 (EDG Building / EDG-20) HVAC Equipment - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 43 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S90.22.CHV01.5120 (EDG Building / EDG-20) HVAC Duct - Installation 24 02-Dec-25 29-Dec-25 (EDG Building / EDG-20) HVAC Duct - Installation
S90.22.CHV01.5130 (EDG Building / EDG-20) HVAC Piping - Installation 24 16-Dec-25 12-Jan-26 (EDG Building / EDG-20) HVAC Piping - Installation
S90.22.CHV01.5140 (EDG Building / EDG-20) HVAC Control System - Installation 24 02-Dec-25 29-Dec-25 (EDG Building / EDG-20) HVAC Control System - Installation
S90.22.CHV01.5150 (EDG Building / EDG-20) HVAC System - SAT 12 13-Jan-26 26-Jan-26 (EDG Building / EDG-20) HVAC System - SAT
S90.22.CHV01.6110 (EDG Building / EDG-21) HVAC Equipment - Installation 12 02-Dec-25 15-Dec-25 (EDG Building / EDG-21) HVAC Equipment - Installation
S90.22.CHV01.6120 (EDG Building / EDG-21) HVAC Duct - Installation 24 02-Dec-25 29-Dec-25 (EDG Building / EDG-21) HVAC Duct - Installation
S90.22.CHV01.6130 (EDG Building / EDG-21) HVAC Piping - Installation 24 16-Dec-25 12-Jan-26 (EDG Building / EDG-21) HVAC Piping - Installation
S90.22.CHV01.6140 (EDG Building / EDG-21) HVAC Control System - Installation 24 02-Dec-25 29-Dec-25 (EDG Building / EDG-21) HVAC Control System - Installation
S90.22.CHV01.6150 (EDG Building / EDG-21) HVAC System - SAT 12 13-Jan-26 26-Jan-26 (EDG Building / EDG-21) HVAC System - SAT
Plumbing System
S90.22.CHV02.1110 (230kV GIS Receiving Substation) U/G Plumbing Piping - Installation 18 04-Jun-24 24-Jun-24 (230kV GIS Receiving Substation) U/G Plumbing Piping - Installation
S90.22.CHV02.1120 (230kV GIS Receiving Substation) A/G Plumbing Piping - Installation 66 03-Feb-26 20-Apr-26 (230kV GIS Receiving Substation) A/G Plumbing Piping - Installation
S90.22.CHV02.1130 (230kV GIS Receiving Substation) Plumbing Equipment - Installation 30 03-Feb-26 09-Mar-26 (230kV GIS Receiving Substation) Plumbing Equipment - Installation
S90.22.CHV02.1140 (230kV GIS Receiving Substation) Plumbing System - SAT 24 21-Apr-26 18-May-26 (230kV GIS Receiving Substation) Plumbing System - SAT
S90.22.CHV02.2110 (Main Substation 01 / MS-01) U/G Plumbing Piping - Installation 18 26-Nov-24 16-Dec-24 (Main Substation 01 / MS-01) U/G Plumbing Piping - Installation
S90.22.CHV02.2120 (Main Substation 01 / MS-01) A/G Plumbing Piping - Installation 66 19-Aug-25 03-Nov-25 (Main Substation 01 / MS-01) A/G Plumbing Piping - Installation
S90.22.CHV02.2130 (Main Substation 01 / MS-01) Plumbing Equipment - Installation 30 19-Aug-25 22-Sep-25 (Main Substation 01 / MS-01) Plumbing Equipment - Installation
S90.22.CHV02.2140 (Main Substation 01 / MS-01) Plumbing System - SAT 24 04-Nov-25 01-Dec-25 (Main Substation 01 / MS-01) Plumbing System - SAT
S90.22.CHV02.3110 (Main Substation 02 / MS-02) U/G Plumbing Piping - Installation 18 26-Nov-24 16-Dec-24 (Main Substation 02 / MS-02) U/G Plumbing Piping - Installation
S90.22.CHV02.3120 (Main Substation 02 / MS-02) A/G Plumbing Piping - Installation 66 19-Aug-25 03-Nov-25 (Main Substation 02 / MS-02) A/G Plumbing Piping - Installation
S90.22.CHV02.3130 (Main Substation 02 / MS-02) Plumbing Equipment - Installation 30 19-Aug-25 22-Sep-25 (Main Substation 02 / MS-02) Plumbing Equipment - Installation
S90.22.CHV02.3140 (Main Substation 02 / MS-02) Plumbing System - SAT 24 04-Nov-25 01-Dec-25 (Main Substation 02 / MS-02) Plumbing System - SAT
S90.22.CHV02.4110 (EDG Building / EDG-30) U/G Plumbing Piping - Installation 6 25-Nov-25 01-Dec-25 (EDG Building / EDG-30) U/G Plumbing Piping - Installation
S90.22.CHV02.4120 (EDG Building / EDG-30) A/G Plumbing Piping - Installation 24 12-May-26 08-Jun-26 (EDG Building / EDG-30) A/G Plumbing Piping - Installation
S90.22.CHV02.4130 (EDG Building / EDG-30) Plumbing Equipment - Installation 12 12-May-26 25-May-26 (EDG Building / EDG-30) Plumbing Equipment - Installation
S90.22.CHV02.4140 (EDG Building / EDG-30) Plumbing System - SAT 12 09-Jun-26 22-Jun-26 (EDG Building / EDG-30) Plumbing System - SAT
S90.22.CHV02.5110 (EDG Building / EDG-20) U/G Plumbing Piping - Installation 6 01-Jul-25 07-Jul-25 (EDG Building / EDG-20) U/G Plumbing Piping - Installation
S90.22.CHV02.5120 (EDG Building / EDG-20) A/G Plumbing Piping - Installation 24 16-Dec-25 12-Jan-26 (EDG Building / EDG-20) A/G Plumbing Piping - Installation
S90.22.CHV02.5130 (EDG Building / EDG-20) Plumbing Equipment - Installation 12 16-Dec-25 29-Dec-25 (EDG Building / EDG-20) Plumbing Equipment - Installation
S90.22.CHV02.5140 (EDG Building / EDG-20) Plumbing System - SAT 12 13-Jan-26 26-Jan-26 (EDG Building / EDG-20) Plumbing System - SAT
S90.22.CHV02.6110 (EDG Building / EDG-21) U/G Plumbing Piping - Installation 6 01-Jul-25 07-Jul-25 (EDG Building / EDG-21) U/G Plumbing Piping - Installation
S90.22.CHV02.6120 (EDG Building / EDG-21) A/G Plumbing Piping - Installation 24 16-Dec-25 12-Jan-26 (EDG Building / EDG-21) A/G Plumbing Piping - Installation
S90.22.CHV02.6130 (EDG Building / EDG-21) Plumbing Equipment - Installation 12 16-Dec-25 29-Dec-25 (EDG Building / EDG-21) Plumbing Equipment - Installation
S90.22.CHV02.6140 (EDG Building / EDG-21) Plumbing System - SAT 12 13-Jan-26 26-Jan-26 (EDG Building / EDG-21) Plumbing System - SAT
Rotating Equipment
S90.22.CMR02.1143 [S93-G-0707 A/B/C] Lift Station 4 Low Flow Pump 36 03-Mar-26 13-Apr-26 [S93-G-0707 A/B/C] Lift Station 4 Low Flow Pump
S90.22.CMR02.1144 [S93-G-0708 A/B] Lift Station 4 High Flow Pump 36 03-Mar-26 13-Apr-26 [S93-G-0708 A/B] Lift Station 4 High Flow Pump
S90.22.CMR06.1178 [S90-U-XXX3] 10T Overhead Crane for 230kV GIS Receiving Substation 78 30-Sep-25 29-Dec-25 [S90-U-XXX3] 10T Overhead Crane for 230kV GIS Receiving Substation
Crain & Hoist
S90.22.CMR07.4110 [S90-U-XXX5] 7.5T Overhead Crane for EDG-30 12 28-Apr-26 11-May-26 [S90-U-XXX5] 7.5T Overhead Crane for EDG-30
S90.22.CMR07.5110 [S90-U-XXX4] 7.5T Overhead Crane for EDG-20 12 02-Dec-25 15-Dec-25 [S90-U-XXX4] 7.5T Overhead Crane for EDG-20
S90.22.CMR07.6110 [S90-U-XXX1] Overhead Crane - Installation 12 02-Dec-25 15-Dec-25 [S90-U-XXX1] Overhead Crane - Installation
Packaged Equipment
S90.22.CMR07.4120 [S90-U-1016] Emergency Diesel Generator - Installation 24 12-May-26 08-Jun-26 [S90-U-1016] Emergency Diesel Generator - Installation
S90.22.CMR07.5120 [S90-U-1016] Emergency Diesel Generator - Installation 24 16-Dec-25 12-Jan-26 [S90-U-1016] Emergency Diesel Generator - Installation
S90.22.CMR07.6120 [S90-U-1016] Emergency Diesel Generator - Installation 24 16-Dec-25 12-Jan-26 [S90-U-1016] Emergency Diesel Generator - Installation
Electrical
Cabling Work (Tray / Pulling & Termination)
S90.22.CEL01.1110 (230kV GIS Receiving Substation) Electrical Cable Tray & Conduit 156 28-Oct-25 27-Apr-26 (230kV GIS Receiving Substation) Electrical Cable Tray & Conduit
S90.22.CEL01.1120 (230kV GIS Receiving Substation) Electrical Cable Pulling & Termination 234 02-Dec-25 31-Aug-26 (230kV GIS Receiving Substation) Electrical Cable Pulling & Termination
S90.22.CEL01.2110 (Main Substation 01 / MS-01) Electrical Cable Tray & Conduit 120 01-Jul-25 17-Nov-25 (Main Substation 01 / MS-01) Electrical Cable Tray & Conduit
S90.22.CEL01.2120 (Main Substation 01 / MS-01) Electrical Cable Pulling & Termination 138 12-Aug-25 19-Jan-26 (Main Substation 01 / MS-01) Electrical Cable Pulling & Termination
S90.22.CEL01.3110 (Main Substation 02 / MS-02) Electrical Cable Tray & Conduit 120 01-Jul-25 17-Nov-25 (Main Substation 02 / MS-02) Electrical Cable Tray & Conduit
S90.22.CEL01.3120 (Main Substation 02 / MS-02) Electrical Cable Pulling & Termination 138 12-Aug-25 19-Jan-26 (Main Substation 02 / MS-02) Electrical Cable Pulling & Termination
S90.22.CEL01.4110 (EDG Building / EDG-30) Electrical Cable Tray & Conduit 36 31-Mar-26 11-May-26 (EDG Building / EDG-30) Electrical Cable Tray & Conduit
S90.22.CEL01.4120 (EDG Building / EDG-30) Electrical Cable Pulling & Termination 30 28-Apr-26 01-Jun-26 (EDG Building / EDG-30) Electrical Cable Pulling & Termination
S90.22.CEL01.5110 (EDG Building / EDG-20) Electrical Cable Tray & Conduit 36 04-Nov-25 15-Dec-25 (EDG Building / EDG-20) Electrical Cable Tray & Conduit
S90.22.CEL01.5120 (EDG Building / EDG-20) Electrical Cable Pulling & Termination 30 02-Dec-25 05-Jan-26 (EDG Building / EDG-20) Electrical Cable Pulling & Termination
S90.22.CEL01.6110 (EDG Building / EDG-21) Electrical Cable Tray & Conduit 36 04-Nov-25 15-Dec-25 (EDG Building / EDG-21) Electrical Cable Tray & Conduit
S90.22.CEL01.6120 (EDG Building / EDG-21) Electrical Cable Pulling & Termination 30 02-Dec-25 05-Jan-26 (EDG Building / EDG-21) Electrical Cable Pulling & Termination
Transformer
S90.22.CEL02.1120 (230kV GIS Receiving Substation) Distribution Transformer - Installation 60 17-Feb-26 27-Apr-26 (230kV GIS Receiving Substation) Distribution Transformer - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 44 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S90.22.CEL02.1130 (230kV GIS Receiving Substation) Neutral Grounding Resistor (NGR) - Installation 36 17-Feb-26 30-Mar-26 (230kV GIS Receiving Substation) Neutral Grounding Resistor (NGR) - Installation
S90.22.CEL02.1210 (230kV GIS Receiving Substation) Cablebus - Installation 42 31-Mar-26 18-May-26 (230kV GIS Receiving Substation) Cablebus - Installation
S90.22.CEL02.2120 (Main Substation 01 / MS-01) Distribution Transformer - Installation 60 21-Oct-25 29-Dec-25 (Main Substation 01 / MS-01) Distribution Transformer - Installation
S90.22.CEL02.2130 (Main Substation 01 / MS-01) Neutral Grounding Resistor (NGR) - Installation 36 21-Oct-25 01-Dec-25 (Main Substation 01 / MS-01) Neutral Grounding Resistor (NGR) - Installation
S90.22.CEL02.2210 (Main Substation 01 / MS-01) Cablebus - Installation 42 02-Dec-25 19-Jan-26 (Main Substation 01 / MS-01) Cablebus - Installation
S90.22.CEL02.3120 (Main Substation 02 / MS-02) Distribution Transformer - Installation 60 21-Oct-25 29-Dec-25 (Main Substation 02 / MS-02) Distribution Transformer - Installation
S90.22.CEL02.3130 (Main Substation 02 / MS-02) Neutral Grounding Resistor (NGR) - Installation 36 21-Oct-25 01-Dec-25 (Main Substation 02 / MS-02) Neutral Grounding Resistor (NGR) - Installation
S90.22.CEL02.3210 (Main Substation 02 / MS-02) Cablebus - Installation 42 02-Dec-25 19-Jan-26 (Main Substation 02 / MS-02) Cablebus - Installation
Switchgear & MCC (Motor Control Center)
S90.22.CEL03.1110 (230kV GIS Receiving Substation) 230kV GIS - Installation 234 30-Dec-25 28-Sep-26 (230kV GIS Receiving Substation) 230kV GIS - Installation
S90.22.CEL03.1120 (230kV GIS Receiving Substation) LV Switchgear & MCC - Installation 132 30-Dec-25 01-Jun-26 (230kV GIS Receiving Substation) LV Switchgear & MCC - Installation
S90.22.CEL03.1210 (230kV GIS Receiving Substation) PSA - Installation 102 30-Dec-25 27-Apr-26 (230kV GIS Receiving Substation) PSA - Installation
S90.22.CEL03.1220 (230kV GIS Receiving Substation) Electrical Panel - Installation 156 30-Dec-25 29-Jun-26 (230kV GIS Receiving Substation) Electrical Panel - Installation
S90.22.CEL03.1230 (230kV GIS Receiving Substation) Telecommunication System - Installation 102 02-Sep-25 29-Dec-25 (230kV GIS Receiving Substation) Telecommunication System - Installation
S90.22.CEL03.1310 (230kV GIS Receiving Substation) 230kV GIS - Test 240 28-Jul-26 03-May-27 (230kV GIS Receiving Substation) 230kV GIS - Test
S90.22.CEL03.1320 (230kV GIS Receiving Substation) LV Switchgear & MCC - Test 78 01-Sep-26 30-Nov-26 (230kV GIS Receiving Substation) LV Switchgear & MCC - Test
S90.22.CEL03.1330 (230kV GIS Receiving Substation) PSA - Test 54 02-Jun-26 03-Aug-26 (230kV GIS Receiving Substation) PSA - Test
S90.22.CEL03.2110 (Main Substation 01 / MS-01) MV Switchgear & MCC - Installation 78 02-Sep-25 01-Dec-25 (Main Substation 01 / MS-01) MV Switchgear & MCC - Installation
S90.22.CEL03.2120 (Main Substation 01 / MS-01) LV Switchgear & MCC - Installation 132 02-Sep-25 02-Feb-26 (Main Substation 01 / MS-01) LV Switchgear & MCC - Installation
S90.22.CEL03.2210 (Main Substation 01 / MS-01) PSA - Installation 102 02-Sep-25 29-Dec-25 (Main Substation 01 / MS-01) PSA - Installation
S90.22.CEL03.2220 (Main Substation 01 / MS-01) Electrical Panel - Installation 156 02-Sep-25 02-Mar-26 (Main Substation 01 / MS-01) Electrical Panel - Installation
S90.22.CEL03.2230 (Main Substation 01 / MS-01) Telecommunication System - Installation 102 02-Sep-25 29-Dec-25 (Main Substation 01 / MS-01) Telecommunication System - Installation
S90.22.CEL03.2310 (Main Substation 01 / MS-01) MV Switchgear & MCC - Test 36 30-Dec-25 09-Feb-26 (Main Substation 01 / MS-01) MV Switchgear & MCC - Test
S90.22.CEL03.2320 (Main Substation 01 / MS-01) LV Switchgear & MCC - Test 72 03-Feb-26 27-Apr-26 (Main Substation 01 / MS-01) LV Switchgear & MCC - Test
S90.22.CEL03.2330 (Main Substation 01 / MS-01) PSA - Test 54 30-Dec-25 02-Mar-26 (Main Substation 01 / MS-01) PSA - Test
S90.22.CEL03.3110 (Main Substation 02 / MS-02) MV Switchgear & MCC - Installation 78 02-Sep-25 01-Dec-25 (Main Substation 02 / MS-02) MV Switchgear & MCC - Installation
S90.22.CEL03.3120 (Main Substation 02 / MS-02) LV Switchgear & MCC - Installation 132 02-Sep-25 02-Feb-26 (Main Substation 02 / MS-02) LV Switchgear & MCC - Installation
S90.22.CEL03.3210 (Main Substation 02 / MS-02) PSA - Installation 102 02-Sep-25 29-Dec-25 (Main Substation 02 / MS-02) PSA - Installation
S90.22.CEL03.3220 (Main Substation 02 / MS-02) Electrical Panel - Installation 156 02-Sep-25 02-Mar-26 (Main Substation 02 / MS-02) Electrical Panel - Installation
S90.22.CEL03.3230 (Main Substation 02 / MS-02) Telecommunication System - Installation 102 02-Sep-25 29-Dec-25 (Main Substation 02 / MS-02) Telecommunication System - Installation
S90.22.CEL03.3310 (Main Substation 02 / MS-02) MV Switchgear & MCC - Test 36 30-Dec-25 09-Feb-26 (Main Substation 02 / MS-02) MV Switchgear & MCC - Test
S90.22.CEL03.3320 (Main Substation 02 / MS-02) LV Switchgear & MCC - Test 72 03-Feb-26 27-Apr-26 (Main Substation 02 / MS-02) LV Switchgear & MCC - Test
S90.22.CEL03.3330 (Main Substation 02 / MS-02) PSA - Test 54 30-Dec-25 02-Mar-26 (Main Substation 02 / MS-02) PSA - Test
S90.22.CEL03.4310 (EDG Building / EDG-30) EDG - Test 24 23-Jun-26 20-Jul-26 (EDG Building / EDG-30) EDG - Test
S90.22.CEL03.5310 (EDG Building / EDG-20) EDG - Test 24 27-Jan-26 23-Feb-26 (EDG Building / EDG-20) EDG - Test
S90.22.CEL03.6310 (EDG Building / EDG-21) EDG - Test 24 27-Jan-26 23-Feb-26 (EDG Building / EDG-21) EDG - Test
UPS & DC System
S90.22.CEL04.1110 (230kV GIS Receiving Substation) UPS & DC System - Installation 66 30-Dec-25 16-Mar-26 (230kV GIS Receiving Substation) UPS & DC System - Installation
S90.22.CEL04.1120 (230kV GIS Receiving Substation) UPS & DC System - Test 30 28-Apr-26 01-Jun-26 (230kV GIS Receiving Substation) UPS & DC System - Test
S90.22.CEL04.2110 (Main Substation 01 / MS-01) UPS & DC System - Installation 66 02-Sep-25 17-Nov-25 (Main Substation 01 / MS-01) UPS & DC System - Installation
S90.22.CEL04.2120 (Main Substation 01 / MS-01) UPS & DC System - Test 36 18-Nov-25 29-Dec-25 (Main Substation 01 / MS-01) UPS & DC System - Test
S90.22.CEL04.3110 (Main Substation 02 / MS-02) UPS & DC System - Installation 66 02-Sep-25 17-Nov-25 (Main Substation 02 / MS-02) UPS & DC System - Installation
S90.22.CEL04.3120 (Main Substation 02 / MS-02) UPS & DC System - Test 36 18-Nov-25 29-Dec-25 (Main Substation 02 / MS-02) UPS & DC System - Test
Lighting System
S90.22.CEL05.1110 (230kV GIS Receiving Substation) Lighting System - Installation 132 30-Dec-25 01-Jun-26 (230kV GIS Receiving Substation) Lighting System - Installation
S90.22.CEL05.1120 (230kV GIS Receiving Substation) Grounding - Installation 264 26-Nov-24 29-Sep-25 (230kV GIS Receiving Substation) Grounding - Installation
S90.22.CEL05.2110 (Main Substation 01 / MS-01) Lighting System - Installation 132 02-Sep-25 02-Feb-26 (Main Substation 01 / MS-01) Lighting System - Installation
S90.22.CEL05.2120 (Main Substation 01 / MS-01) Grounding - Installation 264 31-Dec-24 03-Nov-25 (Main Substation 01 / MS-01) Grounding - Installation
S90.22.CEL05.3110 (Main Substation 02 / MS-02) Lighting System - Installation 132 02-Sep-25 02-Feb-26 (Main Substation 02 / MS-02) Lighting System - Installation
S90.22.CEL05.3120 (Main Substation 02 / MS-02) Grounding - Installation 264 31-Dec-24 03-Nov-25 (Main Substation 02 / MS-02) Grounding - Installation
S90.22.CEL05.4110 (EDG Building / EDG-30) Lighting System - Installation 42 28-Apr-26 15-Jun-26 (EDG Building / EDG-30) Lighting System - Installation
S90.22.CEL05.4120 (EDG Building / EDG-30) Grounding - Installation 144 16-Dec-25 01-Jun-26 (EDG Building / EDG-30) Grounding - Installation
S90.22.CEL05.5110 (EDG Building / EDG-20) Lighting System - Installation 42 02-Dec-25 19-Jan-26 (EDG Building / EDG-20) Lighting System - Installation
S90.22.CEL05.5120 (EDG Building / EDG-20) Grounding - Installation 144 22-Jul-25 05-Jan-26 (EDG Building / EDG-20) Grounding - Installation
S90.22.CEL05.6110 (EDG Building / EDG-21) Lighting System - Installation 42 02-Dec-25 19-Jan-26 (EDG Building / EDG-21) Lighting System - Installation
S90.22.CEL05.6120 (EDG Building / EDG-21) Grounding - Installation 144 22-Jul-25 05-Jan-26 (EDG Building / EDG-21) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S90.22.CCI01.1110 (230kV GIS Receiving Substation) I&C Cable Tray & Conduit 96 30-Dec-25 20-Apr-26 (230kV GIS Receiving Substation) I&C Cable Tray & Conduit
S90.22.CCI01.1120 (230kV GIS Receiving Substation) I&C Cable Pulling & Termination 114 10-Feb-26 22-Jun-26 (230kV GIS Receiving Substation) I&C Cable Pulling & Termination
S90.22.CCI01.2110 (Main Substation 01 / MS-01) I&C Cable Tray & Conduit 96 02-Sep-25 22-Dec-25 (Main Substation 01 / MS-01) I&C Cable Tray & Conduit
S90.22.CCI01.2120 (Main Substation 01 / MS-01) I&C Cable Pulling & Termination 114 14-Oct-25 23-Feb-26 (Main Substation 01 / MS-01) I&C Cable Pulling & Termination
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 45 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S90.22.CCI01.3110 (Main Substation 02 / MS-02) I&C Cable Tray & Conduit 96 02-Sep-25 22-Dec-25 (Main Substation 02 / MS-02) I&C Cable Tray & Conduit
S90.22.CCI01.3120 (Main Substation 02 / MS-02) I&C Cable Pulling & Termination 114 14-Oct-25 23-Feb-26 (Main Substation 02 / MS-02) I&C Cable Pulling & Termination
Main East-West Piperack
Civil
Foundation (Equipment & Piperack)
S90.23.CCV02.1120 (Main East-West Piperack) Piperack Foundation 126 31-Dec-24 26-May-25 (Main East-West Piperack) Piperack Foundation
Misc. Foundation & Paving
S90.23.CCV03.1110 (Main East-West Piperack) Misc. Foundation & Concrete Paving 156 31-Mar-26 28-Sep-26 (Main East-West Piperack) Misc. Foundation & Concrete Paving
S90.23.CCV03.1120 (Main East-West Piperack) Asphalt Paving & Road 42 29-Sep-26 16-Nov-26 (Main East-West Piperack) Asphalt Paving & Road
Steel Structure
Piperack
S90.23.CSS01.1110 (Main East-West Piperack) Piperack Installation 156 27-May-25 24-Nov-25 (Main East-West Piperack) Piperack Installation
S90.23.CSS01.1120 (Main East-West Piperack) Misc. Steel Installation 108 25-Nov-25 30-Mar-26 (Main East-West Piperack) Misc. Steel Installation
Piping
Underground (U/G) Piping
S90.23.CPI01.1110 (Main East-West Piperack) U/G Piping Field Installation (with Pressure Test) 210 26-Nov-24 28-Jul-25 (Main East-West Piperack) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S90.23.CPI02.1110 (Main East-West Piperack) A/G Piping Shop Fabrication 192 15-Apr-25 24-Nov-25 (Main East-West Piperack) A/G Piping Shop Fabrication
S90.23.CPI02.1120 (Main East-West Piperack) A/G Piping Field Installation 258 30-Sep-25 27-Jul-26 (Main East-West Piperack) A/G Piping Field Installation
S90.23.CPI02.1121 (Main East-West Piperack) A/G Piping Support Installation 234 02-Dec-25 31-Aug-26 (Main East-West Piperack) A/G Piping Support Installation
S90.23.CPI02.1130 (Main East-West Piperack) A/G Piping Pressure Test 132 31-Mar-26 31-Aug-26 (Main East-West Piperack) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S90.23.CPA01.1110 (Main East-West Piperack) Piping Painting 78 28-Jul-26 26-Oct-26 (Main East-West Piperack) Piping Painting
Insulation
S90.23.CPA02.1110 (Main East-West Piperack) Piping Insulation 78 28-Jul-26 26-Oct-26 (Main East-West Piperack) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
S90.23.CEL01.1110 (Main East-West Piperack) Electrical Cable Tray & Conduit 132 25-Nov-25 27-Apr-26 (Main East-West Piperack) Electrical Cable Tray & Conduit
S90.23.CEL01.1120 (Main East-West Piperack) Electrical Cable Pulling & Termination 156 27-Jan-26 27-Jul-26 (Main East-West Piperack) Electrical Cable Pulling & Termination
Lighting System
S90.23.CEL05.1110 (Main East-West Piperack) Lighting System - Installation 102 31-Mar-26 27-Jul-26 (Main East-West Piperack) Lighting System - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S90.23.CCI01.1110 (Main East-West Piperack) I&C Cable Tray & Conduit 156 25-Nov-25 25-May-26 (Main East-West Piperack) I&C Cable Tray & Conduit
S90.23.CCI01.1120 (Main East-West Piperack) I&C Cable Pulling & Termination 186 27-Jan-26 31-Aug-26 (Main East-West Piperack) I&C Cable Pulling & Termination
Field Instrument
S90.23.CCI02.1110 (Main East-West Piperack) Field Instrument Installation (with Calibration) 132 28-Apr-26 28-Sep-26 (Main East-West Piperack) Field Instrument Installation (with Calibration)
Loop Test
S90.23.CCI04.1110 (Main East-West Piperack) Loop Test 132 26-May-26 26-Oct-26 (Main East-West Piperack) Loop Test
Pre-commissioning
S90.23.CPC03.1110 (Main East-West Piperack) Leak Test 30 22-May-27 24-Jun-27 (Main East-West Piperack) Leak Test
S90.23.CPC03.1120 (Main East-West Piperack) Mechanical Running Test 48 22-May-27 15-Jul-27 (Main East-West Piperack) Mechanical Running Test
Flushing & Blowing
S90.23.CPC01.1110 (Main East-West Piperack) Mechanical Cleaning 78 01-Sep-26 30-Nov-26 (Main East-West Piperack) Mechanical Cleaning
Function Test
S90.23.CPC02.1110 (Main East-West Piperack) Function Test 54 29-Sep-26 30-Nov-26 (Main East-West Piperack) Function Test
T&I Area & Future Increment Utilities
Civil
Foundation (Tank)
S90.24.CCV01.1110 (T&I Area & Future Increment Utilities) Tank Foundation 156 27-Aug-24 24-Feb-25 (T&I Area & Future Increment Utilities) Tank Foundation
Foundation (Equipment & Piperack)
S90.24.CCV02.1110 (T&I Area & Future Increment Utilities) Equipment Foundation 156 29-Apr-25 27-Oct-25 (T&I Area & Future Increment Utilities) Equipment Foundation
S90.24.CCV02.1120 (T&I Area & Future Increment Utilities) Piperack Foundation 132 28-Jan-25 30-Jun-25 (T&I Area & Future Increment Utilities) Piperack Foundation
Misc. Foundation & Paving
S90.24.CCV03.1110 (T&I Area & Future Increment Utilities) Misc. Foundation & Concrete Paving 162 24-Feb-26 31-Aug-26 (T&I Area & Future Increment Utilities) Misc. Foundation & Concrete Paving
S90.24.CCV03.1120 (T&I Area & Future Increment Utilities) Asphalt Paving & Road 36 01-Sep-26 12-Oct-26 (T&I Area & Future Increment Utilities) Asphalt Paving & Road
Architecture
Reinforced Concrete Building
S90.24.CAR01.4110 (Crew Building - T&I) Substructure 42 25-Mar-25 12-May-25 (Crew Building - T&I) Substructure
S90.24.CAR01.4120 (Crew Building - T&I) Superstructure (Wall / Roof) 96 13-May-25 01-Sep-25 (Crew Building - T&I) Superstructure (Wall / Roof)
S90.24.CAR01.4130 (Crew Building - T&I) Interior Work 36 02-Sep-25 13-Oct-25 (Crew Building - T&I) Interior Work
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 46 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S90.24.CAR01.4140 (Crew Building - T&I) Finishing Work 144 14-Oct-25 30-Mar-26 (Crew Building - T&I) Finishing Work
HVAC
HVAC System
S90.24.CHV01.4110 (Crew Building - T&I) HVAC Equipment - Installation 36 14-Oct-25 24-Nov-25 (Crew Building - T&I) HVAC Equipment - Installation
S90.24.CHV01.4120 (Crew Building - T&I) HVAC Duct - Installation 54 14-Oct-25 15-Dec-25 (Crew Building - T&I) HVAC Duct - Installation
S90.24.CHV01.4130 (Crew Building - T&I) HVAC Piping - Installation 42 25-Nov-25 12-Jan-26 (Crew Building - T&I) HVAC Piping - Installation
S90.24.CHV01.4150 (Crew Building - T&I) HVAC System - SAT 30 13-Jan-26 16-Feb-26 (Crew Building - T&I) HVAC System - SAT
Plumbing System
S90.24.CHV02.4110 (Crew Building - T&I) U/G Plumbing Piping - Installation 12 29-Apr-25 12-May-25 (Crew Building - T&I) U/G Plumbing Piping - Installation
S90.24.CHV02.4120 (Crew Building - T&I) A/G Plumbing Piping - Installation 42 25-Nov-25 12-Jan-26 (Crew Building - T&I) A/G Plumbing Piping - Installation
S90.24.CHV02.4130 (Crew Building - T&I) Plumbing Equipment - Installation 24 16-Dec-25 12-Jan-26 (Crew Building - T&I) Plumbing Equipment - Installation
S90.24.CHV02.4140 (Crew Building - T&I) Plumbing System - SAT 30 13-Jan-26 16-Feb-26 (Crew Building - T&I) Plumbing System - SAT
Steel Structure
Piperack
S90.24.CSS01.1110 (T&I Area & Future Increment Utilities) Piperack Installation 126 01-Jul-25 24-Nov-25 (T&I Area & Future Increment Utilities) Piperack Installation
S90.24.CSS01.1120 (T&I Area & Future Increment Utilities) Misc. Steel Installation 78 25-Nov-25 23-Feb-26 (T&I Area & Future Increment Utilities) Misc. Steel Installation
Platform & Ladder
S90.24.CSS02.1110 (T&I Area & Future Increment Utilities) Equipment Platform Installation 96 24-Feb-26 15-Jun-26 (T&I Area & Future Increment Utilities) Equipment Platform Installation
Rotating Equipment
S90.24.CMR02.1149 [S93-G-0731 A/B/S] Sewage Lift Station 7 Pump 36 23-Sep-25 03-Nov-25 [S93-G-0731 A/B/S] Sewage Lift Station 7 Pump
S90.24.CMR06.1187 [S90-U-XX12] 15T Overhead Crane for Maintenance Shelter (T&I) 36 27-Aug-25 07-Oct-25 [S90-U-XX12] 15T Overhead Crane for Maintenance Shelter (T&I)
S90.24.CMR07.1172 [S93-U-0714] Sanitary Odour Control Unit 7 36 04-Nov-25 15-Dec-25 [S93-U-0714] Sanitary Odour Control Unit 7
Piping
Underground (U/G) Piping
S90.24.CPI01.1110 (T&I Area & Future Increment Utilities) U/G Piping Field Installation (with Pressure Test) 234 26-Nov-24 25-Aug-25 (T&I Area & Future Increment Utilities) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S90.24.CPI02.1110 (T&I Area & Future Increment Utilities) A/G Piping Shop Fabrication 180 29-Apr-25 24-Nov-25 (T&I Area & Future Increment Utilities) A/G Piping Shop Fabrication
S90.24.CPI02.1120 (T&I Area & Future Increment Utilities) A/G Piping Field Installation 222 14-Oct-25 29-Jun-26 (T&I Area & Future Increment Utilities) A/G Piping Field Installation
S90.24.CPI02.1130 (T&I Area & Future Increment Utilities) A/G Piping Support Installation 192 16-Dec-25 27-Jul-26 (T&I Area & Future Increment Utilities) A/G Piping Support Installation
S90.24.CPI02.1140 (T&I Area & Future Increment Utilities) A/G Piping Pressure Test 114 17-Mar-26 27-Jul-26 (T&I Area & Future Increment Utilities) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S90.24.CPA01.1110 (T&I Area & Future Increment Utilities) Piping Painting 78 30-Jun-26 28-Sep-26 (T&I Area & Future Increment Utilities) Piping Painting
Insulation
S90.24.CPA02.1110 (T&I Area & Future Increment Utilities) Piping Insulation 78 30-Jun-26 28-Sep-26 (T&I Area & Future Increment Utilities) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
S90.24.CEL01.1110 (T&I Area & Future Increment Utilities) Electrical Cable Tray & Conduit 132 25-Nov-25 27-Apr-26 (T&I Area & Future Increment Utilities) Electrical Cable Tray & Conduit
S90.24.CEL01.1120 (T&I Area & Future Increment Utilities) Electrical Cable Pulling & Termination 132 27-Jan-26 29-Jun-26 (T&I Area & Future Increment Utilities) Electrical Cable Pulling & Termination
S90.24.CEL01.4110 (Crew Building - T&I) Electrical Cable Tray & Conduit 120 02-Sep-25 19-Jan-26 (Crew Building - T&I) Electrical Cable Tray & Conduit
S90.24.CEL01.4120 (Crew Building - T&I) Electrical Cable Pulling & Termination 138 14-Oct-25 23-Mar-26 (Crew Building - T&I) Electrical Cable Pulling & Termination
Lighting System
S90.24.CEL05.1110 (T&I Area & Future Increment Utilities) Lighting System Installation 108 24-Feb-26 29-Jun-26 (T&I Area & Future Increment Utilities) Lighting System Installation
S90.24.CEL05.4110 (Crew Building - T&I) Lighting System - Installation 132 14-Oct-25 16-Mar-26 (Crew Building - T&I) Lighting System - Installation
S90.24.CEL05.4120 (Crew Building - T&I) Grounding - Installation 258 13-May-25 09-Mar-26 (Crew Building - T&I) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S90.24.CCI01.1110 (T&I Area & Future Increment Utilities) I&C Cable Tray & Conduit 156 25-Nov-25 25-May-26 (T&I Area & Future Increment Utilities) I&C Cable Tray & Conduit
S90.24.CCI01.1120 (T&I Area & Future Increment Utilities) I&C Cable Pulling & Termination 162 20-Jan-26 27-Jul-26 (T&I Area & Future Increment Utilities) I&C Cable Pulling & Termination
Field Instrument
S90.24.CCI02.1110 (T&I Area & Future Increment Utilities) Field Instrument Installation (with Calibration) 108 28-Apr-26 31-Aug-26 (T&I Area & Future Increment Utilities) Field Instrument Installation (with Calibration)
Loop Test
S90.24.CCI04.1110 (T&I Area & Future Increment Utilities) Loop Test 108 26-May-26 28-Sep-26 (T&I Area & Future Increment Utilities) Loop Test
Pre-commissioning

S90.24.CPC03.1110 (T&I Area & Future Increment Utilities) Leak Test 30 22-May-27 24-Jun-27 (T&I Area & Future Increment Utilities) Leak Test
S90.24.CPC03.1120 (T&I Area & Future Increment Utilities) Mechanical Running Test 48 22-May-27 15-Jul-27 (T&I Area & Future Increment Utilities) Mechanical Running Test
Flushing & Blowing
S90.24.CPC01.1110 (T&I Area & Future Increment Utilities) Mechanical Cleaning 108 28-Jul-26 30-Nov-26 (T&I Area & Future Increment Utilities) Mechanical Cleaning
Function Test
S90.24.CPC02.1110 (T&I Area & Future Increment Utilities) Function Test 78 01-Sep-26 30-Nov-26 (T&I Area & Future Increment Utilities) Function Test
Gas Compression & Flare
Flare K.O. Drum & Common
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 47 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
Civil
Foundation (Equipment & Piperack)
S92.21.CCV02.1110 (Flare K.O. Drum & Common) Equipment Foundation 156 01-Apr-25 29-Sep-25 (Flare K.O. Drum & Common) Equipment Foundation
S92.21.CCV02.1120 (Flare K.O. Drum & Common) Piperack Foundation 102 31-Dec-24 28-Apr-25 (Flare K.O. Drum & Common) Piperack Foundation
Misc. Foundation & Paving
S92.21.CCV03.1110 (Flare K.O. Drum & Common) Misc. Foundation & Concrete Paving 204 03-Feb-26 28-Sep-26 (Flare K.O. Drum & Common) Misc. Foundation & Concrete Paving
S92.21.CCV03.1120 (Flare K.O. Drum & Common) Asphalt Paving & Road 42 29-Sep-26 16-Nov-26 (Flare K.O. Drum & Common) Asphalt Paving & Road
Steel Structure
Piperack
S92.21.CSS01.1110 (Flare K.O. Drum & Common) Piperack Installation 132 29-Apr-25 29-Sep-25 (Flare K.O. Drum & Common) Piperack Installation
S92.21.CSS01.1120 (Flare K.O. Drum & Common) Misc. Steel Installation 108 30-Sep-25 02-Feb-26 (Flare K.O. Drum & Common) Misc. Steel Installation
Platform & Ladder
S92.21.CSS02.1110 (Flare K.O. Drum & Common) Equipment Platform Installation 126 03-Feb-26 29-Jun-26 (Flare K.O. Drum & Common) Equipment Platform Installation
Static Equipment
Vessel
S92.21.CMS02.1110 [S92-D-0010] Common T&I Flare K.O. Drum 42 12-May-26 29-Jun-26 [S92-D-0010] Common T&I Flare K.O. Drum
S92.21.CMS02.1111 [S92-D-0011] Cold Flare K.O. Drum 42 12-May-26 29-Jun-26 [S92-D-0011] Cold Flare K.O. Drum
S92.21.CMS02.1112 [S92-D-0012] Cold T&I Flare K.O. Drum 42 12-May-26 29-Jun-26 [S92-D-0012] Cold T&I Flare K.O. Drum
S92.21.CMS02.1113 [S92-D-0013] HP Flare K.O. Drum 42 12-May-26 29-Jun-26 [S92-D-0013] HP Flare K.O. Drum
S92.21.CMS02.1114 [S92-D-0014] LP Flare K.O. Drum 42 12-May-26 29-Jun-26 [S92-D-0014] LP Flare K.O. Drum
Packaged Equipment
S92.21.CMS07.1162 [S92-U-0014] Flare Gas Recovery System 132 30-Sep-25 02-Mar-26 [S92-U-0014] Flare Gas Recovery System
Rotating Equipment
Pump
S92.21.CMR02.1117 [S92-G-0012 A/B] HP Flare K.O. Drum Pump 36 30-Sep-25 04-Nov-25 [S92-G-0012 A/B] HP Flare K.O. Drum Pump
S92.21.CMR02.1118 [S92-G-0013 A/B] LP Flare K.O. Drum Pump 36 30-Sep-25 04-Nov-25 [S92-G-0013 A/B] LP Flare K.O. Drum Pump
S92.21.CMR02.1119 [S92-G-0011 A/B] Cold Flare K.O. Drum Pump 36 30-Sep-25 04-Nov-25 [S92-G-0011 A/B] Cold Flare K.O. Drum Pump
S92.21.CMR02.1120 [S92-G-0010 A/B] Common T&I Flare K.O. Drum Pump 36 30-Sep-25 04-Nov-25 [S92-G-0010 A/B] Common T&I Flare K.O. Drum Pump
S92.21.CMR02.1121 [S92-G-0014 A/B] Cold T&I Flare K.O. Drum Pump 36 30-Sep-25 04-Nov-25 [S92-G-0014 A/B] Cold T&I Flare K.O. Drum Pump
S92.21.CMR02.1137 [S93-G-0701 A/B/C] Lift Station 1 Low Flow Pump 36 03-Mar-26 07-Apr-26 [S93-G-0701 A/B/C] Lift Station 1 Low Flow Pump
S92.21.CMR02.1138 [S93-G-0702 A/B] Lift Station 1 High Flow Pump 36 03-Mar-26 07-Apr-26 [S93-G-0702 A/B] Lift Station 1 High Flow Pump
Piping
Underground (U/G) Piping
S92.21.CPI01.1110 (Flare K.O. Drum & Common) U/G Piping Field Installation (with Pressure Test) 210 29-Oct-24 30-Jun-25 (Flare K.O. Drum & Common) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S92.21.CPI02.1110 (Flare K.O. Drum & Common) A/G Piping Shop Fabrication 210 29-Apr-25 29-Dec-25 (Flare K.O. Drum & Common) A/G Piping Shop Fabrication
S92.21.CPI02.1120 (Flare K.O. Drum & Common) A/G Piping Field Installation 312 29-Jul-25 27-Jul-26 (Flare K.O. Drum & Common) A/G Piping Field Installation
S92.21.CPI02.1121 (Flare K.O. Drum & Common) A/G Piping Support Installation 288 30-Sep-25 31-Aug-26 (Flare K.O. Drum & Common) A/G Piping Support Installation
S92.21.CPI02.1130 (Flare K.O. Drum & Common) A/G Piping Pressure Test 180 03-Feb-26 31-Aug-26 (Flare K.O. Drum & Common) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S92.21.CPA01.1110 (Flare K.O. Drum & Common) Piping Painting 96 28-Jul-26 16-Nov-26 (Flare K.O. Drum & Common) Piping Painting
Insulation
S92.21.CPA02.1110 (Flare K.O. Drum & Common) Piping Insulation 96 28-Jul-26 16-Nov-26 (Flare K.O. Drum & Common) Piping Insulation
Refractory
S92.21.CPA03.1110 (Flare K.O. Drum & Common) Refractory 120 30-Jun-26 16-Nov-26 (Flare K.O. Drum & Common) Refractory
Electrical
Cabling Work (Tray / Pulling & Termination)
S92.21.CEL01.1110 (Flare K.O. Drum & Common) Electrical Cable Tray & Conduit 180 30-Sep-25 27-Apr-26 (Flare K.O. Drum & Common) Electrical Cable Tray & Conduit
S92.21.CEL01.1120 (Flare K.O. Drum & Common) Electrical Cable Pulling & Termination 192 02-Dec-25 13-Jul-26 (Flare K.O. Drum & Common) Electrical Cable Pulling & Termination
Lighting System
S92.21.CEL05.1110 (Flare K.O. Drum & Common) Lighting System Installation 126 03-Feb-26 29-Jun-26 (Flare K.O. Drum & Common) Lighting System Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S92.21.CCI01.1110 (Flare K.O. Drum & Common) I&C Cable Tray & Conduit 210 30-Sep-25 01-Jun-26 (Flare K.O. Drum & Common) I&C Cable Tray & Conduit
S92.21.CCI01.1120 (Flare K.O. Drum & Common) I&C Cable Pulling & Termination 234 02-Dec-25 31-Aug-26 (Flare K.O. Drum & Common) I&C Cable Pulling & Termination
Field Instrument
S92.21.CCI02.1110 (Flare K.O. Drum & Common) Field Instrument Installation (with Calibration) 180 03-Mar-26 28-Sep-26 (Flare K.O. Drum & Common) Field Instrument Installation (with Calibration)
Loop Test
S92.21.CCI04.1110 (Flare K.O. Drum & Common) Loop Test 120 30-Jun-26 16-Nov-26 (Flare K.O. Drum & Common) Loop Test
Pre-commissioning

S92.21.CPC03.1110 (Flare K.O. Drum & Common) Leak Test 60 22-May-27 29-Jul-27 (Flare K.O. Drum & Common) Leak Test
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 48 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S92.21.CPC03.1120 (Flare K.O. Drum & Common) Mechanical Running Test 72 22-May-27 12-Aug-27 (Flare K.O. Drum & Common) Mechanical Running Test
Flushing & Blowing
S92.21.CPC01.1110 (Flare K.O. Drum & Common) Mechanical Cleaning 102 01-Sep-26 28-Dec-26 (Flare K.O. Drum & Common) Mechanical Cleaning
Function Test
S92.21.CPC02.1110 (Flare K.O. Drum & Common) Function Test 78 29-Sep-26 28-Dec-26 (Flare K.O. Drum & Common) Function Test
Flare Area
Civil
Foundation (Equipment & Piperack)
S92.22.CCV02.1110 (Flare Area) Equipment Foundation 180 01-Apr-25 27-Oct-25 (Flare Area) Equipment Foundation
S92.22.CCV02.1120 (Flare Area) Piperack Foundation 120 31-Dec-24 19-May-25 (Flare Area) Piperack Foundation
Misc. Foundation & Paving
S92.22.CCV03.1110 (Flare Area) Misc. Foundation & Concrete Paving 192 03-Mar-26 12-Oct-26 (Flare Area) Misc. Foundation & Concrete Paving
S92.22.CCV03.1120 (Flare Area) Asphalt Paving & Road 42 13-Oct-26 30-Nov-26 (Flare Area) Asphalt Paving & Road
Steel Structure
Piperack
S92.22.CSS01.1110 (Flare Area) Piperack Installation 144 20-May-25 03-Nov-25 (Flare Area) Piperack Installation
S92.22.CSS01.1120 (Flare Area) Misc. Steel Installation 102 04-Nov-25 02-Mar-26 (Flare Area) Misc. Steel Installation
Platform & Ladder
S92.22.CSS02.1110 (Flare Area) Equipment Platform Installation 66 03-Mar-26 18-May-26 (Flare Area) Equipment Platform Installation
Static Equipment
Packaged Equipment
S92.22.CMS08.1163 [S92-U-0012] HP Flare Package 210 28-Oct-25 29-Jun-26 [S92-U-0012] HP Flare Package
S92.22.CMS08.1164 [S92-U-0013] LP Flare Package 210 28-Oct-25 29-Jun-26 [S92-U-0013] LP Flare Package
S92.22.CMS08.1165 [S92-U-0011] Common T&I Flare Package 210 28-Oct-25 29-Jun-26 [S92-U-0011] Common T&I Flare Package
S92.22.CMS08.1166 [S92-U-0010 A] Burn Pit A 156 28-Oct-25 27-Apr-26 [S92-U-0010 A] Burn Pit A
S92.22.CMS08.1167 [S92-U-0010 B] Burn Pit B 156 28-Oct-25 27-Apr-26 [S92-U-0010 B] Burn Pit B
Piping
Underground (U/G) Piping
S92.22.CPI01.1110 (Flare Area) U/G Piping Field Installation (with Pressure Test) 210 29-Oct-24 30-Jun-25 (Flare Area) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S92.22.CPI02.1110 (Flare Area) A/G Piping Shop Fabrication 210 29-Apr-25 29-Dec-25 (Flare Area) A/G Piping Shop Fabrication
S92.22.CPI02.1120 (Flare Area) A/G Piping Field Installation 270 19-Aug-25 29-Jun-26 (Flare Area) A/G Piping Field Installation
S92.22.CPI02.1121 (Flare Area) A/G Piping Support Installation 240 21-Oct-25 27-Jul-26 (Flare Area) A/G Piping Support Installation
S92.22.CPI02.1130 (Flare Area) A/G Piping Pressure Test 138 17-Feb-26 27-Jul-26 (Flare Area) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S92.22.CPA01.1110 (Flare Area) Piping Painting 78 30-Jun-26 28-Sep-26 (Flare Area) Piping Painting
Insulation
S92.22.CPA02.1110 (Flare Area) Piping Insulation 78 30-Jun-26 28-Sep-26 (Flare Area) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
S92.22.CEL01.1110 (Flare Area) Electrical Cable Tray & Conduit 150 04-Nov-25 27-Apr-26 (Flare Area) Electrical Cable Tray & Conduit
S92.22.CEL01.1120 (Flare Area) Electrical Cable Pulling & Termination 156 30-Dec-25 29-Jun-26 (Flare Area) Electrical Cable Pulling & Termination
Lighting System
S92.22.CEL05.1110 (Flare Area) Lighting System Installation 102 03-Mar-26 29-Jun-26 (Flare Area) Lighting System Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S92.22.CCI01.1110 (Flare Area) I&C Cable Tray & Conduit 168 04-Nov-25 18-May-26 (Flare Area) I&C Cable Tray & Conduit
S92.22.CCI01.1120 (Flare Area) I&C Cable Pulling & Termination 180 30-Dec-25 27-Jul-26 (Flare Area) I&C Cable Pulling & Termination
Field Instrument
S92.22.CCI02.1110 (Flare Area) Field Instrument Installation (with Calibration) 132 31-Mar-26 31-Aug-26 (Flare Area) Field Instrument Installation (with Calibration)
Loop Test
S92.22.CCI04.1110 (Flare Area) Loop Test 102 30-Jun-26 26-Oct-26 (Flare Area) Loop Test
Pre-commissioning
S92.22.CPC03.1110 (Flare Area) Leak Test 60 22-May-27 29-Jul-27 (Flare Area) Leak Test

S92.22.CPC03.1120 (Flare Area) Mechanical Running Test 72 22-May-27 12-Aug-27 (Flare Area) Mechanical Running Test
Flushing & Blowing
S92.22.CPC01.1110 (Flare Area) Mechanical Cleaning 108 28-Jul-26 30-Nov-26 (Flare Area) Mechanical Cleaning
Function Test

S92.22.CPC02.1110 (Flare Area) Function Test 78 01-Sep-26 30-Nov-26 (Flare Area) Function Test
Utilties
Utilities Area & Common
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 49 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
Civil
Foundation (Tank)
S93.21.CCV01.1110 (Utilities Area & Common) Tank Foundation 180 27-Aug-24 24-Mar-25 (Utilities Area & Common) Tank Foundation
Foundation (Equipment & Piperack)
S93.21.CCV02.1110 (Utilities Area & Common) Equipment Foundation 156 01-Apr-25 29-Sep-25 (Utilities Area & Common) Equipment Foundation
S93.21.CCV02.1120 (Utilities Area & Common) Piperack Foundation 120 31-Dec-24 19-May-25 (Utilities Area & Common) Piperack Foundation
Misc. Foundation & Paving
S93.21.CCV03.1110 (Utilities Area & Common) Misc. Foundation & Concrete Paving 156 03-Mar-26 31-Aug-26 (Utilities Area & Common) Misc. Foundation & Concrete Paving
S93.21.CCV03.1120 (Utilities Area & Common) Asphalt Paving & Road 42 01-Sep-26 19-Oct-26 (Utilities Area & Common) Asphalt Paving & Road
Architecture
Reinforced Concrete Building
S93.21.CAR01.2110 (Substation 03 / SS-03) Substructure 60 26-Nov-24 03-Feb-25 (Substation 03 / SS-03) Substructure
S93.21.CAR01.2120 (Substation 03 / SS-03) Superstructure (Wall / Roof) 156 04-Feb-25 04-Aug-25 (Substation 03 / SS-03) Superstructure (Wall / Roof)
S93.21.CAR01.2130 (Substation 03 / SS-03) Interior Work 54 05-Aug-25 06-Oct-25 (Substation 03 / SS-03) Interior Work
S93.21.CAR01.2140 (Substation 03 / SS-03) Finishing Work 210 07-Oct-25 08-Jun-26 (Substation 03 / SS-03) Finishing Work
S93.21.CAR01.3110 (EDG Building / EDG-03) Substructure 42 11-Mar-25 28-Apr-25 (EDG Building / EDG-03) Substructure
S93.21.CAR01.3120 (EDG Building / EDG-03) Superstructure (Wall / Roof) 90 29-Apr-25 11-Aug-25 (EDG Building / EDG-03) Superstructure (Wall / Roof)
S93.21.CAR01.3130 (EDG Building / EDG-03) Interior Work 24 12-Aug-25 08-Sep-25 (EDG Building / EDG-03) Interior Work
S93.21.CAR01.3140 (EDG Building / EDG-03) Finishing Work 132 09-Sep-25 09-Feb-26 (EDG Building / EDG-03) Finishing Work
S93.21.CAR01.4110 (Process Interface Building / PIB-03) Substructure 60 04-Feb-25 14-Apr-25 (Process Interface Building / PIB-03) Substructure
S93.21.CAR01.4120 (Process Interface Building / PIB-03) Superstructure (Wall / Roof) 144 15-Apr-25 29-Sep-25 (Process Interface Building / PIB-03) Superstructure (Wall / Roof)
S93.21.CAR01.4130 (Process Interface Building / PIB-03) Interior Work 60 30-Sep-25 08-Dec-25 (Process Interface Building / PIB-03) Interior Work
S93.21.CAR01.4140 (Process Interface Building / PIB-03) Finishing Work 186 09-Dec-25 13-Jul-26 (Process Interface Building / PIB-03) Finishing Work
S93.21.CAR01.5110 (Operator Shelter / OPS-03) Substructure 60 25-Mar-25 02-Jun-25 (Operator Shelter / OPS-03) Substructure
S93.21.CAR01.5120 (Operator Shelter / OPS-03) Superstructure (Wall / Roof) 156 03-Jun-25 01-Dec-25 (Operator Shelter / OPS-03) Superstructure (Wall / Roof)
S93.21.CAR01.5130 (Operator Shelter / OPS-03) Interior Work 78 02-Dec-25 02-Mar-26 (Operator Shelter / OPS-03) Interior Work
S93.21.CAR01.5140 (Operator Shelter / OPS-03) Finishing Work 168 03-Mar-26 14-Sep-26 (Operator Shelter / OPS-03) Finishing Work
Reinforced Concrete Structure
S93.21.CAR02.2110 (Substation 03 / SS-03) Transformer Foundation 54 05-Aug-25 06-Oct-25 (Substation 03 / SS-03) Transformer Foundation
S93.21.CAR02.2120 (Substation 03 / SS-03) Firewall Structure 42 07-Oct-25 24-Nov-25 (Substation 03 / SS-03) Firewall Structure
S93.21.CAR02.2130 (Substation 03 / SS-03) Firewall Finishing Work 42 03-Feb-26 23-Mar-26 (Substation 03 / SS-03) Firewall Finishing Work
HVAC
HVAC System
S93.21.CHV01.2110 (Substation 03 / SS-03) HVAC Equipment - Installation 42 05-Aug-25 22-Sep-25 (Substation 03 / SS-03) HVAC Equipment - Installation
S93.21.CHV01.2120 (Substation 03 / SS-03) HVAC Duct - Installation 108 05-Aug-25 08-Dec-25 (Substation 03 / SS-03) HVAC Duct - Installation
S93.21.CHV01.2130 (Substation 03 / SS-03) HVAC Piping - Installation 54 23-Sep-25 24-Nov-25 (Substation 03 / SS-03) HVAC Piping - Installation
S93.21.CHV01.2140 (Substation 03 / SS-03) HVAC Control System - Installation 78 07-Oct-25 05-Jan-26 (Substation 03 / SS-03) HVAC Control System - Installation
S93.21.CHV01.2150 (Substation 03 / SS-03) HVAC System - SAT 24 06-Jan-26 02-Feb-26 (Substation 03 / SS-03) HVAC System - SAT
S93.21.CHV01.3110 (EDG Building / EDG-03) HVAC Equipment - Installation 12 09-Sep-25 22-Sep-25 (EDG Building / EDG-03) HVAC Equipment - Installation
S93.21.CHV01.3120 (EDG Building / EDG-03) HVAC Duct - Installation 24 09-Sep-25 06-Oct-25 (EDG Building / EDG-03) HVAC Duct - Installation
S93.21.CHV01.3130 (EDG Building / EDG-03) HVAC Piping - Installation 24 23-Sep-25 20-Oct-25 (EDG Building / EDG-03) HVAC Piping - Installation
S93.21.CHV01.3140 (EDG Building / EDG-03) HVAC Control System - Installation 24 09-Sep-25 06-Oct-25 (EDG Building / EDG-03) HVAC Control System - Installation
S93.21.CHV01.3150 (EDG Building / EDG-03) HVAC System - SAT 12 21-Oct-25 03-Nov-25 (EDG Building / EDG-03) HVAC System - SAT
S93.21.CHV01.4110 (Process Interface Building / PIB-03) HVAC Equipment - Installation 42 09-Dec-25 26-Jan-26 (Process Interface Building / PIB-03) HVAC Equipment - Installation
S93.21.CHV01.4120 (Process Interface Building / PIB-03) HVAC Duct - Installation 78 09-Dec-25 09-Mar-26 (Process Interface Building / PIB-03) HVAC Duct - Installation
S93.21.CHV01.4130 (Process Interface Building / PIB-03) HVAC Piping - Installation 54 27-Jan-26 30-Mar-26 (Process Interface Building / PIB-03) HVAC Piping - Installation
S93.21.CHV01.4140 (Process Interface Building / PIB-03) HVAC Control System - Installation 66 27-Jan-26 13-Apr-26 (Process Interface Building / PIB-03) HVAC Control System - Installation
S93.21.CHV01.4150 (Process Interface Building / PIB-03) HVAC System - SAT 24 14-Apr-26 11-May-26 (Process Interface Building / PIB-03) HVAC System - SAT
S93.21.CHV01.5110 (Operator Shelter / OPS-03) HVAC Equipment - Installation 36 03-Mar-26 13-Apr-26 (Operator Shelter / OPS-03) HVAC Equipment - Installation
S93.21.CHV01.5120 (Operator Shelter / OPS-03) HVAC Duct - Installation 66 03-Mar-26 18-May-26 (Operator Shelter / OPS-03) HVAC Duct - Installation
S93.21.CHV01.5130 (Operator Shelter / OPS-03) HVAC Piping - Installation 48 14-Apr-26 08-Jun-26 (Operator Shelter / OPS-03) HVAC Piping - Installation
S93.21.CHV01.5140 (Operator Shelter / OPS-03) HVAC Control System - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-03) HVAC Control System - Installation
S93.21.CHV01.5150 (Operator Shelter / OPS-03) HVAC System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-03) HVAC System - SAT
Plumbing System
S93.21.CHV02.2110 (Substation 03 / SS-03) U/G Plumbing Piping - Installation 18 31-Dec-24 20-Jan-25 (Substation 03 / SS-03) U/G Plumbing Piping - Installation
S93.21.CHV02.2120 (Substation 03 / SS-03) A/G Plumbing Piping - Installation 66 23-Sep-25 08-Dec-25 (Substation 03 / SS-03) A/G Plumbing Piping - Installation
S93.21.CHV02.2130 (Substation 03 / SS-03) Plumbing Equipment - Installation 30 23-Sep-25 27-Oct-25 (Substation 03 / SS-03) Plumbing Equipment - Installation
S93.21.CHV02.2140 (Substation 03 / SS-03) Plumbing System - SAT 24 09-Dec-25 05-Jan-26 (Substation 03 / SS-03) Plumbing System - SAT
S93.21.CHV02.3110 (EDG Building / EDG-03) U/G Plumbing Piping - Installation 6 08-Apr-25 14-Apr-25 (EDG Building / EDG-03) U/G Plumbing Piping - Installation
S93.21.CHV02.3120 (EDG Building / EDG-03) A/G Plumbing Piping - Installation 24 23-Sep-25 20-Oct-25 (EDG Building / EDG-03) A/G Plumbing Piping - Installation
S93.21.CHV02.3130 (EDG Building / EDG-03) Plumbing Equipment - Installation 12 23-Sep-25 06-Oct-25 (EDG Building / EDG-03) Plumbing Equipment - Installation
S93.21.CHV02.3140 (EDG Building / EDG-03) Plumbing System - SAT 12 21-Oct-25 03-Nov-25 (EDG Building / EDG-03) Plumbing System - SAT
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 50 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S93.21.CHV02.4110 (Process Interface Building / PIB-03) U/G Plumbing Piping - Installation 18 11-Mar-25 31-Mar-25 (Process Interface Building / PIB-03) U/G Plumbing Piping - Installation
S93.21.CHV02.4120 (Process Interface Building / PIB-03) A/G Plumbing Piping - Installation 66 27-Jan-26 13-Apr-26 (Process Interface Building / PIB-03) A/G Plumbing Piping - Installation
S93.21.CHV02.4130 (Process Interface Building / PIB-03) Plumbing Equipment - Installation 30 10-Mar-26 13-Apr-26 (Process Interface Building / PIB-03) Plumbing Equipment - Installation
S93.21.CHV02.4140 (Process Interface Building / PIB-03) Plumbing System - SAT 24 14-Apr-26 11-May-26 (Process Interface Building / PIB-03) Plumbing System - SAT
S93.21.CHV02.5110 (Operator Shelter / OPS-03) U/G Plumbing Piping - Installation 18 29-Apr-25 19-May-25 (Operator Shelter / OPS-03) U/G Plumbing Piping - Installation
S93.21.CHV02.5120 (Operator Shelter / OPS-03) A/G Plumbing Piping - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-03) A/G Plumbing Piping - Installation
S93.21.CHV02.5130 (Operator Shelter / OPS-03) Plumbing Equipment - Installation 30 19-May-26 22-Jun-26 (Operator Shelter / OPS-03) Plumbing Equipment - Installation
S93.21.CHV02.5140 (Operator Shelter / OPS-03) Plumbing System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-03) Plumbing System - SAT
Steel Structure
Piperack
S93.21.CSS01.1110 (Utilities Area & Common) Piperack Installation 138 20-May-25 27-Oct-25 (Utilities Area & Common) Piperack Installation
S93.21.CSS01.1120 (Utilities Area & Common) Misc. Steel Installation 108 28-Oct-25 02-Mar-26 (Utilities Area & Common) Misc. Steel Installation
Platform & Ladder
S93.21.CSS02.1110 (Utilities Area & Common) Equipment Platform Installation 90 03-Mar-26 15-Jun-26 (Utilities Area & Common) Equipment Platform Installation
Static Equipment
S93.21.CMS09.1130 [S93-E-0006 A/B] HP Fuel Gas Heater 54 16-Dec-25 16-Feb-26 [S93-E-0006 A/B] HP Fuel Gas Heater
Tank
S93.21.CMS01.1135 [S93-D-0019] Diesel Storage Tank 108 06-May-25 08-Sep-25 [S93-D-0019] Diesel Storage Tank
S93.21.CMS01.1136 [S93-D-0020 A/B] Potable Water Storage Tank 108 06-May-25 08-Sep-25 [S93-D-0020 A/B] Potable Water Storage Tank
S93.21.CMS01.1137 [S93-D-0021 A/B] Firewater Storage Tank 234 06-May-25 02-Feb-26 [S93-D-0021 A/B] Firewater Storage Tank
S93.21.CMS01.1138 [S93-D-0022 A/B] Wash Water Tank 336 06-May-25 01-Jun-26 [S93-D-0022 A/B] Wash Water Tank
S93.21.CMS01.1139 [S93-D-0023 A/B] Utility Water Storage Tank 108 06-May-25 08-Sep-25 [S93-D-0023 A/B] Utility Water Storage Tank
Vessel
S93.21.CMS02.1115 [S93-D-0012 A/B] Plant Air K.O. Drum 42 12-May-26 29-Jun-26 [S93-D-0012 A/B] Plant Air K.O. Drum
S93.21.CMS02.1116 [S93-D-0013 A/B/C/D] Instrument Air Receiver 42 12-May-26 29-Jun-26 [S93-D-0013 A/B/C/D] Instrument Air Receiver
S93.21.CMS02.1117 [S93-D-0014 A/B] Nitrogen Receiver 42 12-May-26 29-Jun-26 [S93-D-0014 A/B] Nitrogen Receiver
S93.21.CMS02.1118 [S93-D-0015 A/B] HP Fuel Gas K.O. Drum 42 12-May-26 29-Jun-26 [S93-D-0015 A/B] HP Fuel Gas K.O. Drum
S93.21.CMS02.1119 [S93-D-0016 A/B] LP Fuel Gas K.O. Drum 42 12-May-26 29-Jun-26 [S93-D-0016 A/B] LP Fuel Gas K.O. Drum
S93.21.CMS02.1120 [S93-D-0025] LP Steam Condensate Flash Drum T&I 42 12-May-26 29-Jun-26 [S93-D-0025] LP Steam Condensate Flash Drum T&I
S93.21.CMS02.1121 [S93-D-0026] LP Steam Condensate Flash Drum 42 12-May-26 29-Jun-26 [S93-D-0026] LP Steam Condensate Flash Drum
S93.21.CMS02.1122 [S93-D-0027 A/B] Wash Water Heater Condensate Drum 42 12-May-26 29-Jun-26 [S93-D-0027 A/B] Wash Water Heater Condensate Drum
Shell & Tube Heat Exchanger
S93.21.CMS04.1125 [S93-E-0002 A/B] Wash Water Heater 36 30-Sep-25 10-Nov-25 [S93-E-0002 A/B] Wash Water Heater
Air Cooled Heat Exchanger
S93.21.CMS05.1126 [S93-E-0001] LP Steam Condensate Drum Overhead Cooler 54 24-Feb-26 27-Apr-26 [S93-E-0001] LP Steam Condensate Drum Overhead Cooler
S93.21.CMS05.1127 [S93-E-0003] Steam Condensate Cooler 54 24-Feb-26 27-Apr-26 [S93-E-0003] Steam Condensate Cooler
S93.21.CMS05.1128 [S93-E-0004] HC Contaminated Steam Condensate Cooler 54 24-Feb-26 27-Apr-26 [S93-E-0004] HC Contaminated Steam Condensate Cooler
S93.21.CMS05.1129 [S93-E-0005] LP Steam Condensate Drum Overhead Cooler 54 24-Feb-26 27-Apr-26 [S93-E-0005] LP Steam Condensate Drum Overhead Cooler
Filter
S93.21.CMS06.1131 [S93-D-0017 A/B] Diesel Unloading Filter 36 11-Nov-25 22-Dec-25 [S93-D-0017 A/B] Diesel Unloading Filter
S93.21.CMS06.1132 [S93-D-0018 A/B] Diesel Transfer Filter 36 11-Nov-25 22-Dec-25 [S93-D-0018 A/B] Diesel Transfer Filter
S93.21.CMS06.1133 [S93-D-0030 A/B] HP Fuel Gas Filter Coalescer 36 11-Nov-25 22-Dec-25 [S93-D-0030 A/B] HP Fuel Gas Filter Coalescer
S93.21.CMS06.1134 [S93-D-0031 A/B] LP Fuel Gas Filter Coalescer 36 11-Nov-25 22-Dec-25 [S93-D-0031 A/B] LP Fuel Gas Filter Coalescer
Packaged Equipment
S93.21.CMS07.1148 [S93-U-0013 A/B/C] Air Dryer Package 108 28-Oct-25 02-Mar-26 [S93-U-0013 A/B/C] Air Dryer Package
S93.21.CMS07.1149 [S93-U-0014 A/B] Nitrogen Generation Package 78 23-Dec-25 23-Mar-26 [S93-U-0014 A/B] Nitrogen Generation Package
S93.21.CMS07.1150 [S93-U-0015] Liquid Nitrogen Vapouriser Package 108 17-Feb-26 22-Jun-26 [S93-U-0015] Liquid Nitrogen Vapouriser Package
S93.21.CMS07.1151 [S93-U-0021 A/B] Vacuum Deaeration Package 108 09-Dec-25 13-Apr-26 [S93-U-0021 A/B] Vacuum Deaeration Package
Rotating Equipment
Pump
S93.21.CMR02.1124 [S93-G-0024 A/B/C/D] Steam Condensate Transfer Pump 66 10-Mar-26 25-May-26 [S93-G-0024 A/B/C/D] Steam Condensate Transfer Pump
S93.21.CMR02.1132 [S93-G-0014 A/B] Potable Water Pump 36 30-Sep-25 10-Nov-25 [S93-G-0014 A/B] Potable Water Pump
S93.21.CMR02.1133 [S93-G-0016 A/B/C/D] Wash Water Pump 66 30-Sep-25 15-Dec-25 [S93-G-0016 A/B/C/D] Wash Water Pump
S93.21.CMR02.1134 [S93-G-0019 A/B] Utility Water Pump 36 30-Sep-25 10-Nov-25 [S93-G-0019 A/B] Utility Water Pump
S93.21.CMR02.1135 [S93-G-0022] Diesel Unloading Pump 36 30-Sep-25 10-Nov-25 [S93-G-0022] Diesel Unloading Pump
S93.21.CMR02.1136 [S93-G-0023 A/B] Diesel Transfer Pump 36 30-Sep-25 10-Nov-25 [S93-G-0023 A/B] Diesel Transfer Pump
S93.21.CMR02.1150 [S93-G-0732 A/B/S] Sewage Lift Station 8 Pump 36 30-Sep-25 10-Nov-25 [S93-G-0732 A/B/S] Sewage Lift Station 8 Pump
S93.21.CMR02.1154 [S93-G-0015 A/B] Firewater Pump / Electric Driven 36 25-Nov-25 05-Jan-26 [S93-G-0015 A/B] Firewater Pump / Electric Driven
S93.21.CMR02.1155 [S93-G-0020 A/B] Firewater Pump / Diesel Driven 36 25-Nov-25 05-Jan-26 [S93-G-0020 A/B] Firewater Pump / Diesel Driven
S93.21.CMR02.1156 [S93-G-0021 A/B] Firewater Jockey Pump 36 25-Nov-25 05-Jan-26 [S93-G-0021 A/B] Firewater Jockey Pump
Packaged Equipment
S93.21.CMR07.1157 [S93-U-0017] Potable Water Hypochlorite Dosing Package 132 21-Oct-25 23-Mar-26 [S93-U-0017] Potable Water Hypochlorite Dosing Package
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 51 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S93.21.CMR07.1158 [S93-U-0019] Oxygen Scavenger Dosing Package 132 21-Oct-25 23-Mar-26 [S93-U-0019] Oxygen Scavenger Dosing Package
S93.21.CMR07.1164 [S93-U-0012 A/B/C/D] Air Compressor Package 132 16-Dec-25 18-May-26 [S93-U-0012 A/B/C/D] Air Compressor Package
S93.21.CMR07.1165 [S93-U-0018] Potable Water Chiller Package 132 30-Sep-25 02-Mar-26 [S93-U-0018] Potable Water Chiller Package
S93.21.CMR07.1173 [S93-U-0715] Sanitary Odour Control Unit 8 78 04-Nov-25 02-Feb-26 [S93-U-0715] Sanitary Odour Control Unit 8
S93.21.CMR07.3110 [S93-U-XXX6] 7.5T Overhead Crane for EDG-03 12 09-Sep-25 22-Sep-25 [S93-U-XXX6] 7.5T Overhead Crane for EDG-03
S93.21.CMR07.3120 [S90-U-1016] Emergency Diesel Generator - Installation 24 16-Dec-25 12-Jan-26 [S90-U-1016] Emergency Diesel Generator - Installation
Piping
Underground (U/G) Piping
S93.21.CPI01.1110 (Utilities Area & Common) U/G Piping Field Installation (with Pressure Test) 312 29-Oct-24 27-Oct-25 (Utilities Area & Common) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S93.21.CPI02.1110 (Utilities Area & Common) A/G Piping Shop Fabrication 264 01-Apr-25 02-Feb-26 (Utilities Area & Common) A/G Piping Shop Fabrication
S93.21.CPI02.1120 (Utilities Area & Common) A/G Piping Field Installation 234 28-Oct-25 27-Jul-26 (Utilities Area & Common) A/G Piping Field Installation
S93.21.CPI02.1121 (Utilities Area & Common) A/G Piping Support Installation 210 30-Dec-25 31-Aug-26 (Utilities Area & Common) A/G Piping Support Installation
S93.21.CPI02.1130 (Utilities Area & Common) A/G Piping Pressure Test 131 31-Mar-26 30-Aug-26 (Utilities Area & Common) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S93.21.CPA01.1110 (Utilities Area & Common) Piping Painting 78 28-Jul-26 26-Oct-26 (Utilities Area & Common) Piping Painting
Insulation
S93.21.CPA02.1110 (Utilities Area & Common) Piping Insulation 78 28-Jul-26 26-Oct-26 (Utilities Area & Common) Piping Insulation
Electrical
S93.21.CEL06.1210 (Utilities Area & Common) Motor Solo-run Test (for MV) 48 22-May-27 15-Jul-27 (Utilities Area & Common) Motor Solo-run Test (for MV)
Cabling Work (Tray / Pulling & Termination)
S93.21.CEL01.1110 (Utilities Area & Common) Electrical Cable Tray & Conduit 156 28-Oct-25 27-Apr-26 (Utilities Area & Common) Electrical Cable Tray & Conduit
S93.21.CEL01.1120 (Utilities Area & Common) Electrical Cable Pulling & Termination 168 30-Dec-25 13-Jul-26 (Utilities Area & Common) Electrical Cable Pulling & Termination
S93.21.CEL01.2110 (Substation 03 / SS-03) Electrical Cable Tray & Conduit 120 05-Aug-25 22-Dec-25 (Substation 03 / SS-03) Electrical Cable Tray & Conduit
S93.21.CEL01.2120 (Substation 03 / SS-03) Electrical Cable Pulling & Termination 138 16-Sep-25 23-Feb-26 (Substation 03 / SS-03) Electrical Cable Pulling & Termination
S93.21.CEL01.3110 (EDG Building / EDG-03) Electrical Cable Tray & Conduit 36 12-Aug-25 22-Sep-25 (EDG Building / EDG-03) Electrical Cable Tray & Conduit
S93.21.CEL01.3120 (EDG Building / EDG-03) Electrical Cable Pulling & Termination 30 09-Sep-25 13-Oct-25 (EDG Building / EDG-03) Electrical Cable Pulling & Termination
S93.21.CEL01.4110 (Process Interface Building / PIB-03) Electrical Cable Tray & Conduit 114 30-Sep-25 09-Feb-26 (Process Interface Building / PIB-03) Electrical Cable Tray & Conduit
S93.21.CEL01.4120 (Process Interface Building / PIB-03) Electrical Cable Pulling & Termination 138 11-Nov-25 20-Apr-26 (Process Interface Building / PIB-03) Electrical Cable Pulling & Termination
S93.21.CEL01.5110 (Operator Shelter / OPS-03) Electrical Cable Tray & Conduit 120 02-Dec-25 20-Apr-26 (Operator Shelter / OPS-03) Electrical Cable Tray & Conduit
S93.21.CEL01.5120 (Operator Shelter / OPS-03) Electrical Cable Pulling & Termination 138 13-Jan-26 22-Jun-26 (Operator Shelter / OPS-03) Electrical Cable Pulling & Termination
Transformer
S93.21.CEL02.2120 (Substation 03 / SS-03) Distribution Transformer - Installation 60 25-Nov-25 02-Feb-26 (Substation 03 / SS-03) Distribution Transformer - Installation
S93.21.CEL02.2130 (Substation 03 / SS-03) Neutral Grounding Resistor (NGR) - Installation 36 25-Nov-25 05-Jan-26 (Substation 03 / SS-03) Neutral Grounding Resistor (NGR) - Installation
S93.21.CEL02.2210 (Substation 03 / SS-03) Cablebus - Installation 42 06-Jan-26 23-Feb-26 (Substation 03 / SS-03) Cablebus - Installation
Switchgear & MCC (Motor Control Center)
S93.21.CEL03.2110 (Substation 03 / SS-03) MV Switchgear & MCC - Installation 78 07-Oct-25 05-Jan-26 (Substation 03 / SS-03) MV Switchgear & MCC - Installation
S93.21.CEL03.2120 (Substation 03 / SS-03) LV Switchgear & MCC - Installation 132 07-Oct-25 09-Mar-26 (Substation 03 / SS-03) LV Switchgear & MCC - Installation
S93.21.CEL03.2210 (Substation 03 / SS-03) PSA - Installation 102 07-Oct-25 02-Feb-26 (Substation 03 / SS-03) PSA - Installation
S93.21.CEL03.2220 (Substation 03 / SS-03) Electrical Panel - Installation 156 07-Oct-25 06-Apr-26 (Substation 03 / SS-03) Electrical Panel - Installation
S93.21.CEL03.2230 (Substation 03 / SS-03) Telecommunication System - Installation 102 02-Sep-25 29-Dec-25 (Substation 03 / SS-03) Telecommunication System - Installation
S93.21.CEL03.2310 (Substation 03 / SS-03) MV Switchgear & MCC - Test 36 03-Feb-26 16-Mar-26 (Substation 03 / SS-03) MV Switchgear & MCC - Test
S93.21.CEL03.2320 (Substation 03 / SS-03) LV Switchgear & MCC - Test 72 10-Mar-26 01-Jun-26 (Substation 03 / SS-03) LV Switchgear & MCC - Test
S93.21.CEL03.2330 (Substation 03 / SS-03) PSA - Test 54 03-Feb-26 06-Apr-26 (Substation 03 / SS-03) PSA - Test
S93.21.CEL03.3310 (EDG Building / EDG-03) EDG - Test 24 13-Jan-26 09-Feb-26 (EDG Building / EDG-03) EDG - Test
S93.21.CEL03.4210 (Process Interface Building / PIB-03) Electrical Panel - Installation 144 09-Dec-25 25-May-26 (Process Interface Building / PIB-03) Electrical Panel - Installation
UPS & DC System
S93.21.CEL04.2110 (Substation 03 / SS-03) UPS & DC System - Installation 54 07-Oct-25 08-Dec-25 (Substation 03 / SS-03) UPS & DC System - Installation
S93.21.CEL04.2120 (Substation 03 / SS-03) UPS & DC System - Test 24 23-Dec-25 19-Jan-26 (Substation 03 / SS-03) UPS & DC System - Test
S93.21.CEL04.4110 (Process Interface Building / PIB-03) UPS & DC System - Installation 54 09-Dec-25 09-Feb-26 (Process Interface Building / PIB-03) UPS & DC System - Installation
S93.21.CEL04.4120 (Process Interface Building / PIB-03) UPS & DC System - Test 24 10-Feb-26 09-Mar-26 (Process Interface Building / PIB-03) UPS & DC System - Test
Lighting System
S93.21.CEL05.1110 (Utilities Area & Common) Lighting System Installation 102 03-Mar-26 29-Jun-26 (Utilities Area & Common) Lighting System Installation
S93.21.CEL05.2110 (Substation 03 / SS-03) Lighting System - Installation 132 07-Oct-25 09-Mar-26 (Substation 03 / SS-03) Lighting System - Installation
S93.21.CEL05.2120 (Substation 03 / SS-03) Grounding - Installation 264 04-Feb-25 08-Dec-25 (Substation 03 / SS-03) Grounding - Installation
S93.21.CEL05.3110 (EDG Building / EDG-03) Lighting System - Installation 42 09-Sep-25 27-Oct-25 (EDG Building / EDG-03) Lighting System - Installation
S93.21.CEL05.3120 (EDG Building / EDG-03) Grounding - Installation 144 29-Apr-25 13-Oct-25 (EDG Building / EDG-03) Grounding - Installation
S93.21.CEL05.4110 (Process Interface Building / PIB-03) Lighting System - Installation 132 09-Dec-25 11-May-26 (Process Interface Building / PIB-03) Lighting System - Installation
S93.21.CEL05.4120 (Process Interface Building / PIB-03) Grounding - Installation 246 15-Apr-25 26-Jan-26 (Process Interface Building / PIB-03) Grounding - Installation
S93.21.CEL05.5110 (Operator Shelter / OPS-03) Lighting System - Installation 132 03-Mar-26 03-Aug-26 (Operator Shelter / OPS-03) Lighting System - Installation
S93.21.CEL05.5120 (Operator Shelter / OPS-03) Grounding - Installation 258 03-Jun-25 30-Mar-26 (Operator Shelter / OPS-03) Grounding - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 52 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S93.21.CCI01.1110 (Utilities Area & Common) I&C Cable Tray & Conduit 186 28-Oct-25 01-Jun-26 (Utilities Area & Common) I&C Cable Tray & Conduit
S93.21.CCI01.1120 (Utilities Area & Common) I&C Cable Pulling & Termination 210 30-Dec-25 31-Aug-26 (Utilities Area & Common) I&C Cable Pulling & Termination
S93.21.CCI01.2110 (Substation 03 / SS-03) I&C Cable Tray & Conduit 96 07-Oct-25 26-Jan-26 (Substation 03 / SS-03) I&C Cable Tray & Conduit
S93.21.CCI01.2120 (Substation 03 / SS-03) I&C Cable Pulling & Termination 114 18-Nov-25 30-Mar-26 (Substation 03 / SS-03) I&C Cable Pulling & Termination
S93.21.CCI01.4110 (Process Interface Building / PIB-03) I&C Cable Tray & Conduit 138 30-Sep-25 09-Mar-26 (Process Interface Building / PIB-03) I&C Cable Tray & Conduit
S93.21.CCI01.4120 (Process Interface Building / PIB-03) I&C Cable Pulling & Termination 156 11-Nov-25 11-May-26 (Process Interface Building / PIB-03) I&C Cable Pulling & Termination
Field Instrument
S93.21.CCI02.1110 (Utilities Area & Common) Field Instrument Installation (with Calibration) 156 31-Mar-26 28-Sep-26 (Utilities Area & Common) Field Instrument Installation (with Calibration)
PCS (MAC) & Instrument Panel
S93.21.CCI03.4110 (Process Interface Building / PIB-03) PCS - Installation 102 09-Dec-25 06-Apr-26 (Process Interface Building / PIB-03) PCS - Installation
S93.21.CCI03.4120 (Process Interface Building / PIB-03) PCS - Installation 132 07-Apr-26 07-Sep-26 (Process Interface Building / PIB-03) PCS - Installation
Loop Test
S93.21.CCI04.1110 (Utilities Area & Common) Loop Test 132 02-Jun-26 02-Nov-26 (Utilities Area & Common) Loop Test
Pre-commissioning
S93.21.CPC03.1110 (Utilities Area & Common) Leak Test 84 22-May-27 26-Aug-27 (Utilities Area & Common) Leak Test
S93.21.CPC03.1120 (Utilities Area & Common) Mechanical Running Test 84 22-May-27 26-Aug-27 (Utilities Area & Common) Mechanical Running Test
Flushing & Blowing
S93.21.CPC01.1110 (Utilities Area & Common) Mechanical Cleaning 102 01-Sep-26 28-Dec-26 (Utilities Area & Common) Mechanical Cleaning
Function Test
S93.21.CPC02.1110 (Utilities Area & Common) Function Test 78 29-Sep-26 28-Dec-26 (Utilities Area & Common) Function Test
Sanitary Waste Water System
Civil
Foundation (Tank)
S93.22.CCV01.1110 (Sanitary Waste Water System) Tank Foundation 180 27-Aug-24 24-Mar-25 (Sanitary Waste Water System) Tank Foundation
Foundation (Equipment & Piperack)
S93.22.CCV02.1110 (Sanitary Waste Water System) Equipment Foundation 132 29-Apr-25 29-Sep-25 (Sanitary Waste Water System) Equipment Foundation
S93.22.CCV02.1120 (Sanitary Waste Water System) Pipe Sleeper Foundation 108 28-Jan-25 02-Jun-25 (Sanitary Waste Water System) Pipe Sleeper Foundation
Misc. Foundation & Paving
S93.22.CCV03.1110 (Sanitary Waste Water System) Misc. Foundation & Concrete Paving 180 03-Mar-26 28-Sep-26 (Sanitary Waste Water System) Misc. Foundation & Concrete Paving
S93.22.CCV03.1120 (Sanitary Waste Water System) Asphalt Paving & Road 42 29-Sep-26 16-Nov-26 (Sanitary Waste Water System) Asphalt Paving & Road
Architecture
Reinforced Concrete Building
S93.22.CAR01.2110 (Substation 13 / SS-13) Substructure 60 24-Dec-24 03-Mar-25 (Substation 13 / SS-13) Substructure
S93.22.CAR01.2120 (Substation 13 / SS-13) Superstructure (Wall / Roof) 156 04-Mar-25 01-Sep-25 (Substation 13 / SS-13) Superstructure (Wall / Roof)
S93.22.CAR01.2130 (Substation 13 / SS-13) Interior Work 54 02-Sep-25 03-Nov-25 (Substation 13 / SS-13) Interior Work
S93.22.CAR01.2140 (Substation 13 / SS-13) Finishing Work 210 04-Nov-25 06-Jul-26 (Substation 13 / SS-13) Finishing Work
S93.22.CAR01.5110 (Operator Shelter / OPS-13) Substructure 60 25-Mar-25 02-Jun-25 (Operator Shelter / OPS-13) Substructure
S93.22.CAR01.5120 (Operator Shelter / OPS-13) Superstructure (Wall / Roof) 156 03-Jun-25 01-Dec-25 (Operator Shelter / OPS-13) Superstructure (Wall / Roof)
S93.22.CAR01.5130 (Operator Shelter / OPS-13) Interior Work 78 02-Dec-25 02-Mar-26 (Operator Shelter / OPS-13) Interior Work
S93.22.CAR01.5140 (Operator Shelter / OPS-13) Finishing Work 168 03-Mar-26 14-Sep-26 (Operator Shelter / OPS-13) Finishing Work
Reinforced Concrete Structure
S93.22.CAR02.2110 (Substation 13 / SS-13) Transformer Foundation 54 02-Sep-25 03-Nov-25 (Substation 13 / SS-13) Transformer Foundation
S93.22.CAR02.2120 (Substation 13 / SS-13) Firewall Structure 42 04-Nov-25 22-Dec-25 (Substation 13 / SS-13) Firewall Structure
S93.22.CAR02.2130 (Substation 13 / SS-13) Firewall Finishing Work 42 03-Mar-26 20-Apr-26 (Substation 13 / SS-13) Firewall Finishing Work
HVAC
HVAC System
S93.22.CHV01.2110 (Substation 13 / SS-13) HVAC Equipment - Installation 42 02-Sep-25 20-Oct-25 (Substation 13 / SS-13) HVAC Equipment - Installation
S93.22.CHV01.2120 (Substation 13 / SS-13) HVAC Duct - Installation 108 02-Sep-25 05-Jan-26 (Substation 13 / SS-13) HVAC Duct - Installation
S93.22.CHV01.2130 (Substation 13 / SS-13) HVAC Piping - Installation 54 21-Oct-25 22-Dec-25 (Substation 13 / SS-13) HVAC Piping - Installation
S93.22.CHV01.2140 (Substation 13 / SS-13) HVAC Control System - Installation 78 04-Nov-25 02-Feb-26 (Substation 13 / SS-13) HVAC Control System - Installation
S93.22.CHV01.2150 (Substation 13 / SS-13) HVAC System - SAT 24 03-Feb-26 02-Mar-26 (Substation 13 / SS-13) HVAC System - SAT
S93.22.CHV01.5110 (Operator Shelter / OPS-13) HVAC Equipment - Installation 36 03-Mar-26 13-Apr-26 (Operator Shelter / OPS-13) HVAC Equipment - Installation
S93.22.CHV01.5120 (Operator Shelter / OPS-13) HVAC Duct - Installation 66 03-Mar-26 18-May-26 (Operator Shelter / OPS-13) HVAC Duct - Installation
S93.22.CHV01.5130 (Operator Shelter / OPS-13) HVAC Piping - Installation 48 14-Apr-26 08-Jun-26 (Operator Shelter / OPS-13) HVAC Piping - Installation
S93.22.CHV01.5140 (Operator Shelter / OPS-13) HVAC Control System - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-13) HVAC Control System - Installation
S93.22.CHV01.5150 (Operator Shelter / OPS-13) HVAC System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-13) HVAC System - SAT
Plumbing System
S93.22.CHV02.2110 (Substation 13 / SS-13) U/G Plumbing Piping - Installation 18 28-Jan-25 17-Feb-25 (Substation 13 / SS-13) U/G Plumbing Piping - Installation
S93.22.CHV02.2120 (Substation 13 / SS-13) A/G Plumbing Piping - Installation 66 21-Oct-25 05-Jan-26 (Substation 13 / SS-13) A/G Plumbing Piping - Installation
S93.22.CHV02.2130 (Substation 13 / SS-13) Plumbing Equipment - Installation 30 21-Oct-25 24-Nov-25 (Substation 13 / SS-13) Plumbing Equipment - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 53 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S93.22.CHV02.2140 (Substation 13 / SS-13) Plumbing System - SAT 24 06-Jan-26 02-Feb-26 (Substation 13 / SS-13) Plumbing System - SAT
S93.22.CHV02.5110 (Operator Shelter / OPS-13) U/G Plumbing Piping - Installation 18 29-Apr-25 19-May-25 (Operator Shelter / OPS-13) U/G Plumbing Piping - Installation
S93.22.CHV02.5120 (Operator Shelter / OPS-13) A/G Plumbing Piping - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-13) A/G Plumbing Piping - Installation
S93.22.CHV02.5130 (Operator Shelter / OPS-13) Plumbing Equipment - Installation 30 19-May-26 22-Jun-26 (Operator Shelter / OPS-13) Plumbing Equipment - Installation
S93.22.CHV02.5140 (Operator Shelter / OPS-13) Plumbing System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-13) Plumbing System - SAT
Steel Structure
Platform & Ladder
S93.22.CSS02.1110 (Sanitary Waste Water System) Equipment Platform Installation 78 03-Mar-26 01-Jun-26 (Sanitary Waste Water System) Equipment Platform Installation
Static Equipment
Tank
S93.22.CMS01.1140 [S93-D-0706 A/B] Treated Water Tank 108 06-May-25 08-Sep-25 [S93-D-0706 A/B] Treated Water Tank
Rotating Equipment
S93.22.CMR06.1183 [S93-U-XXX8] 5T Overhead Crane for Substation-13 36 27-Aug-25 07-Oct-25 [S93-U-XXX8] 5T Overhead Crane for Substation-13
Pump
S93.22.CMR02.1111 [S93-G-0723 A/B] Treated Water Pump 36 30-Sep-25 10-Nov-25 [S93-G-0723 A/B] Treated Water Pump
S93.22.CMR02.1112 [S93-G-0727 A/B] Treated Water Effluent Pump 36 30-Sep-25 10-Nov-25 [S93-G-0727 A/B] Treated Water Effluent Pump
S93.22.CMR02.1146 [S93-G-0716 A/B] Sewage Feed Pump 36 30-Sep-25 10-Nov-25 [S93-G-0716 A/B] Sewage Feed Pump
S93.22.CMR02.1153 [S93-G-0726 A/B] STP Works Drainage Sump Pump 36 30-Sep-25 10-Nov-25 [S93-G-0726 A/B] STP Works Drainage Sump Pump
S93.22.CMR02.1189 [S93-G-0717 A/B] Sludge Transfer Pump 36 28-Oct-25 08-Dec-25 [S93-G-0717 A/B] Sludge Transfer Pump
Packaged Equipment
S93.22.CMR07.1167 [S93-U-0704 A/B] Sewage Treatment Package 108 30-Sep-25 02-Feb-26 [S93-U-0704 A/B] Sewage Treatment Package
S93.22.CMR07.1169 [S93-D-0705 A/B] Emergency Sewage Storage Tank (with Scrapper) 78 30-Sep-25 29-Dec-25 [S93-D-0705 A/B] Emergency Sewage Storage Tank (with Scrapper)
S93.22.CMR07.1177 [S93-U-0705 A/B] Hydrated Lime Big Bag Disinfection Package 108 30-Sep-25 02-Feb-26 [S93-U-0705 A/B] Hydrated Lime Big Bag Disinfection Package
Piping
Underground (U/G) Piping
S93.22.CPI01.1110 (Sanitary Waste Water System) U/G Piping Field Installation (with Pressure Test) 252 26-Nov-24 15-Sep-25 (Sanitary Waste Water System) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S93.22.CPI02.1110 (Sanitary Waste Water System) A/G Piping Shop Fabrication 186 29-Apr-25 01-Dec-25 (Sanitary Waste Water System) A/G Piping Shop Fabrication
S93.22.CPI02.1120 (Sanitary Waste Water System) A/G Piping Field Installation 144 16-Sep-25 02-Mar-26 (Sanitary Waste Water System) A/G Piping Field Installation
S93.22.CPI02.1121 (Sanitary Waste Water System) A/G Piping Support Installation 114 18-Nov-25 30-Mar-26 (Sanitary Waste Water System) A/G Piping Support Installation
S93.22.CPI02.1130 (Sanitary Waste Water System) A/G Piping Pressure Test 78 30-Dec-25 30-Mar-26 (Sanitary Waste Water System) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S93.22.CPA01.1110 (Sanitary Waste Water System) Piping Painting 78 03-Mar-26 01-Jun-26 (Sanitary Waste Water System) Piping Painting
Insulation
S93.22.CPA02.1110 (Sanitary Waste Water System) Piping Insulation 78 03-Mar-26 01-Jun-26 (Sanitary Waste Water System) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
S93.22.CEL01.1110 (Sanitary Waste Water System) Electrical Cable Tray & Conduit 96 30-Sep-25 19-Jan-26 (Sanitary Waste Water System) Electrical Cable Tray & Conduit
S93.22.CEL01.1120 (Sanitary Waste Water System) Electrical Cable Pulling & Termination 114 02-Dec-25 13-Apr-26 (Sanitary Waste Water System) Electrical Cable Pulling & Termination
S93.22.CEL01.2110 (Substation 13 / SS-13) Electrical Cable Tray & Conduit 120 02-Sep-25 19-Jan-26 (Substation 13 / SS-13) Electrical Cable Tray & Conduit
S93.22.CEL01.2120 (Substation 13 / SS-13) Electrical Cable Pulling & Termination 138 14-Oct-25 23-Mar-26 (Substation 13 / SS-13) Electrical Cable Pulling & Termination
S93.22.CEL01.5110 (Operator Shelter / OPS-13) Electrical Cable Tray & Conduit 120 02-Dec-25 20-Apr-26 (Operator Shelter / OPS-13) Electrical Cable Tray & Conduit
S93.22.CEL01.5120 (Operator Shelter / OPS-13) Electrical Cable Pulling & Termination 138 13-Jan-26 22-Jun-26 (Operator Shelter / OPS-13) Electrical Cable Pulling & Termination
Transformer
S93.22.CEL02.2120 (Substation 13 / SS-13) Distribution Transformer - Installation 60 23-Dec-25 02-Mar-26 (Substation 13 / SS-13) Distribution Transformer - Installation
S93.22.CEL02.2130 (Substation 13 / SS-13) Neutral Grounding Resistor (NGR) - Installation 36 23-Dec-25 02-Feb-26 (Substation 13 / SS-13) Neutral Grounding Resistor (NGR) - Installation
S93.22.CEL02.2210 (Substation 13 / SS-13) Cablebus - Installation 42 03-Feb-26 23-Mar-26 (Substation 13 / SS-13) Cablebus - Installation
Switchgear & MCC (Motor Control Center)
S93.22.CEL03.2120 (Substation 13 / SS-13) LV Switchgear & MCC - Installation 132 04-Nov-25 06-Apr-26 (Substation 13 / SS-13) LV Switchgear & MCC - Installation
S93.22.CEL03.2210 (Substation 13 / SS-13) PSA - Installation 102 04-Nov-25 02-Mar-26 (Substation 13 / SS-13) PSA - Installation
S93.22.CEL03.2220 (Substation 13 / SS-13) Electrical Panel - Installation 156 04-Nov-25 04-May-26 (Substation 13 / SS-13) Electrical Panel - Installation
S93.22.CEL03.2230 (Substation 13 / SS-13) Telecommunication System - Installation 102 02-Sep-25 29-Dec-25 (Substation 13 / SS-13) Telecommunication System - Installation
S93.22.CEL03.2320 (Substation 13 / SS-13) LV Switchgear & MCC - Test 72 07-Apr-26 29-Jun-26 (Substation 13 / SS-13) LV Switchgear & MCC - Test
S93.22.CEL03.2330 (Substation 13 / SS-13) PSA - Test 54 03-Mar-26 04-May-26 (Substation 13 / SS-13) PSA - Test
UPS & DC System
S93.22.CEL04.2110 (Substation 13 / SS-13) UPS & DC System - Installation 54 04-Nov-25 05-Jan-26 (Substation 13 / SS-13) UPS & DC System - Installation
S93.22.CEL04.2120 (Substation 13 / SS-13) UPS & DC System - Test 24 20-Jan-26 16-Feb-26 (Substation 13 / SS-13) UPS & DC System - Test
Lighting System
S93.22.CEL05.1110 (Sanitary Waste Water System) Lighting System Installation 108 20-Jan-26 25-May-26 (Sanitary Waste Water System) Lighting System Installation
S93.22.CEL05.2110 (Substation 13 / SS-13) Lighting System - Installation 126 04-Nov-25 30-Mar-26 (Substation 13 / SS-13) Lighting System - Installation
S93.22.CEL05.2120 (Substation 13 / SS-13) Grounding - Installation 264 04-Mar-25 05-Jan-26 (Substation 13 / SS-13) Grounding - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 54 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S93.22.CEL05.5110 (Operator Shelter / OPS-13) Lighting System - Installation 90 03-Mar-26 15-Jun-26 (Operator Shelter / OPS-13) Lighting System - Installation
S93.22.CEL05.5120 (Operator Shelter / OPS-13) Grounding - Installation 258 03-Jun-25 30-Mar-26 (Operator Shelter / OPS-13) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S93.22.CCI01.1110 (Sanitary Waste Water System) I&C Cable Tray & Conduit 132 30-Sep-25 02-Mar-26 (Sanitary Waste Water System) I&C Cable Tray & Conduit
S93.22.CCI01.1120 (Sanitary Waste Water System) I&C Cable Pulling & Termination 144 02-Dec-25 18-May-26 (Sanitary Waste Water System) I&C Cable Pulling & Termination
S93.22.CCI01.2110 (Substation 13 / SS-13) I&C Cable Tray & Conduit 96 04-Nov-25 23-Feb-26 (Substation 13 / SS-13) I&C Cable Tray & Conduit
S93.22.CCI01.2120 (Substation 13 / SS-13) I&C Cable Pulling & Termination 114 16-Dec-25 27-Apr-26 (Substation 13 / SS-13) I&C Cable Pulling & Termination
Field Instrument
S93.22.CCI02.1110 (Sanitary Waste Water System) Field Instrument Installation (with Calibration) 78 03-Feb-26 04-May-26 (Sanitary Waste Water System) Field Instrument Installation (with Calibration)
Loop Test
S93.22.CCI04.1110 (Sanitary Waste Water System) Loop Test 78 05-May-26 03-Aug-26 (Sanitary Waste Water System) Loop Test
Pre-commissioning

S93.22.CPC03.1110 (Sanitary Waste Water System) Leak Test 36 01-Jun-27 12-Jul-27 (Sanitary Waste Water System) Leak Test
S93.22.CPC03.1120 (Sanitary Waste Water System) Mechanical Running Test 48 01-Jun-27 26-Jul-27 (Sanitary Waste Water System) Mechanical Running Test
Flushing & Blowing
S93.22.CPC01.1110 (Sanitary Waste Water System) Mechanical Cleaning 78 31-Mar-26 29-Jun-26 (Sanitary Waste Water System) Mechanical Cleaning
Function Test
S93.22.CPC02.1110 (Sanitary Waste Water System) Function Test 54 30-Jun-26 31-Aug-26 (Sanitary Waste Water System) Function Test
Oily Waste Water System
Civil
Foundation (Equipment & Piperack)
S93.23.CCV02.1110 (Oily Waste Water System) Equipment Foundation 78 29-Jul-25 27-Oct-25 (Oily Waste Water System) Equipment Foundation
S93.23.CCV02.1120 (Oily Waste Water System) Concrete Structure (Pond) 234 31-Dec-24 29-Sep-25 (Oily Waste Water System) Concrete Structure (Pond)
Misc. Foundation & Paving
S93.23.CCV03.1110 (Oily Waste Water System) Misc. Foundation & Concrete Paving 180 03-Mar-26 28-Sep-26 (Oily Waste Water System) Misc. Foundation & Concrete Paving
S93.23.CCV03.1120 (Oily Waste Water System) Asphalt Paving & Road 42 29-Sep-26 16-Nov-26 (Oily Waste Water System) Asphalt Paving & Road
Steel Structure
Platform & Ladder
S93.23.CSS02.1110 (Oily Waste Water System) Equipment Platform Installation 78 03-Mar-26 01-Jun-26 (Oily Waste Water System) Equipment Platform Installation
Static Equipment
S93.23.CMS07.1152 [S93-U-0702] Walnut Shell Filtration Package 108 11-Nov-25 16-Mar-26 [S93-U-0702] Walnut Shell Filtration Package
Vessel
S93.23.CMS02.1123 [S93-D-0707] Slop Oil Drum 42 12-May-26 29-Jun-26 [S93-D-0707] Slop Oil Drum
Rotating Equipment
S93.23.CMR10.1176 [S93-U-0703 A/B] Pond Oil Skimmer 42 28-Oct-25 15-Dec-25 [S93-U-0703 A/B] Pond Oil Skimmer
Pump
S93.23.CMR02.1110 [S93-G-0722 A/B] Filtration Feed Pump 36 28-Oct-25 08-Dec-25 [S93-G-0722 A/B] Filtration Feed Pump
S93.23.CMR02.1113 [S93-G-0728 A/B] Slop Oil Pump 36 28-Oct-25 08-Dec-25 [S93-G-0728 A/B] Slop Oil Pump
S93.23.CMR02.1145 [S93-G-0715 A/B] Filtration Backwash Pump 36 03-Mar-26 13-Apr-26 [S93-G-0715 A/B] Filtration Backwash Pump
Piping
Underground (U/G) Piping
S93.23.CPI01.1110 (Oily Waste Water System) U/G Piping Field Installation (with Pressure Test) 288 29-Oct-24 29-Sep-25 (Oily Waste Water System) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S93.23.CPI02.1110 (Oily Waste Water System) A/G Piping Shop Fabrication 258 01-Apr-25 26-Jan-26 (Oily Waste Water System) A/G Piping Shop Fabrication
S93.23.CPI02.1120 (Oily Waste Water System) A/G Piping Field Installation 258 30-Sep-25 27-Jul-26 (Oily Waste Water System) A/G Piping Field Installation
S93.23.CPI02.1121 (Oily Waste Water System) A/G Piping Support Installation 234 02-Dec-25 31-Aug-26 (Oily Waste Water System) A/G Piping Support Installation
S93.23.CPI02.1130 (Oily Waste Water System) A/G Piping Pressure Test 132 31-Mar-26 31-Aug-26 (Oily Waste Water System) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S93.23.CPA01.1110 (Oily Waste Water System) Piping Painting 78 28-Jul-26 26-Oct-26 (Oily Waste Water System) Piping Painting
Insulation
S93.23.CPA02.1110 (Oily Waste Water System) Piping Insulation 78 28-Jul-26 26-Oct-26 (Oily Waste Water System) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
S93.23.CEL01.1110 (Oily Waste Water System) Electrical Cable Tray & Conduit 156 28-Oct-25 27-Apr-26 (Oily Waste Water System) Electrical Cable Tray & Conduit
S93.23.CEL01.1120 (Oily Waste Water System) Electrical Cable Pulling & Termination 180 30-Dec-25 27-Jul-26 (Oily Waste Water System) Electrical Cable Pulling & Termination
Lighting System
S93.23.CEL05.1110 (Oily Waste Water System) Lighting System Installation 108 28-Apr-26 31-Aug-26 (Oily Waste Water System) Lighting System Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S93.23.CCI01.1110 (Oily Waste Water System) I&C Cable Tray & Conduit 180 28-Oct-25 25-May-26 (Oily Waste Water System) I&C Cable Tray & Conduit
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 55 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S93.23.CCI01.1120 (Oily Waste Water System) I&C Cable Pulling & Termination 210 30-Dec-25 31-Aug-26 (Oily Waste Water System) I&C Cable Pulling & Termination
Field Instrument
S93.23.CCI02.1110 (Oily Waste Water System) Field Instrument Installation (with Calibration) 156 31-Mar-26 28-Sep-26 (Oily Waste Water System) Field Instrument Installation (with Calibration)
Loop Test
S93.23.CCI04.1110 (Oily Waste Water System) Loop Test 84 26-May-26 31-Aug-26 (Oily Waste Water System) Loop Test
Pre-commissioning
S93.23.CPC03.1110 (Oily Waste Water System) Leak Test 36 01-Jun-27 12-Jul-27 (Oily Waste Water System) Leak Test
S93.23.CPC03.1120 (Oily Waste Water System) Mechanical Running Test 48 01-Jun-27 26-Jul-27 (Oily Waste Water System) Mechanical Running Test
Flushing & Blowing
S93.23.CPC01.1110 (Oily Waste Water System) Mechanical Cleaning 78 01-Sep-26 30-Nov-26 (Oily Waste Water System) Mechanical Cleaning
Function Test
S93.23.CPC02.1110 (Oily Waste Water System) Function Test 54 29-Sep-26 30-Nov-26 (Oily Waste Water System) Function Test
Produced Water Treatment Package
Produced Water Treatment Plant & Common
Civil
Foundation (Tank)
S95.21.CCV01.1110 (Produced Water Treatment Plant & Common) Tank Foundation 102 31-Dec-24 28-Apr-25 (Produced Water Treatment Plant & Common) Tank Foundation
Foundation (Equipment & Piperack)
S95.21.CCV02.1110 (Produced Water Treatment Plant & Common) Equipment Foundation 150 04-Mar-25 25-Aug-25 (Produced Water Treatment Plant & Common) Equipment Foundation
S95.21.CCV02.1120 (Produced Water Treatment Plant & Common) Piperack Foundation 144 03-Dec-24 19-May-25 (Produced Water Treatment Plant & Common) Piperack Foundation
Misc. Foundation & Paving
S95.21.CCV03.1110 (Produced Water Treatment Plant & Common) Misc. Foundation & Concrete Paving 156 10-Feb-26 10-Aug-26 (Produced Water Treatment Plant & Common) Misc. Foundation & Concrete Paving
S95.21.CCV03.1120 (Produced Water Treatment Plant & Common) Asphalt Paving & Road 42 11-Aug-26 28-Sep-26 (Produced Water Treatment Plant & Common) Asphalt Paving & Road
Architecture
Reinforced Concrete Building
S95.21.CAR01.2110 (Substation 02-15 / SS-15) Substructure 60 26-Nov-24 03-Feb-25 (Substation 02-15 / SS-15) Substructure
S95.21.CAR01.2120 (Substation 02-15 / SS-15) Superstructure (Wall / Roof) 156 04-Feb-25 04-Aug-25 (Substation 02-15 / SS-15) Superstructure (Wall / Roof)
S95.21.CAR01.2130 (Substation 02-15 / SS-15) Interior Work 54 05-Aug-25 06-Oct-25 (Substation 02-15 / SS-15) Interior Work
S95.21.CAR01.2140 (Substation 02-15 / SS-15) Finishing Work 210 07-Oct-25 08-Jun-26 (Substation 02-15 / SS-15) Finishing Work
S95.21.CAR01.4110 (Process Interface Building / PIB-15) Substructure 60 04-Feb-25 14-Apr-25 (Process Interface Building / PIB-15) Substructure
S95.21.CAR01.4120 (Process Interface Building / PIB-15) Superstructure (Wall / Roof) 144 15-Apr-25 29-Sep-25 (Process Interface Building / PIB-15) Superstructure (Wall / Roof)
S95.21.CAR01.4130 (Process Interface Building / PIB-15) Interior Work 60 30-Sep-25 08-Dec-25 (Process Interface Building / PIB-15) Interior Work
S95.21.CAR01.4140 (Process Interface Building / PIB-15) Finishing Work 186 09-Dec-25 13-Jul-26 (Process Interface Building / PIB-15) Finishing Work
S95.21.CAR01.5110 (Operator Shelter / OPS-15) Substructure 60 25-Mar-25 02-Jun-25 (Operator Shelter / OPS-15) Substructure
S95.21.CAR01.5120 (Operator Shelter / OPS-15) Superstructure (Wall / Roof) 156 03-Jun-25 01-Dec-25 (Operator Shelter / OPS-15) Superstructure (Wall / Roof)
S95.21.CAR01.5130 (Operator Shelter / OPS-15) Interior Work 78 02-Dec-25 02-Mar-26 (Operator Shelter / OPS-15) Interior Work
S95.21.CAR01.5140 (Operator Shelter / OPS-15) Finishing Work 168 03-Mar-26 14-Sep-26 (Operator Shelter / OPS-15) Finishing Work
Reinforced Concrete Structure
S95.21.CAR02.2110 (Substation 02-15 / SS-15) Transformer Foundation 54 05-Aug-25 06-Oct-25 (Substation 02-15 / SS-15) Transformer Foundation
S95.21.CAR02.2120 (Substation 02-15 / SS-15) Firewall Structure 42 07-Oct-25 24-Nov-25 (Substation 02-15 / SS-15) Firewall Structure
S95.21.CAR02.2130 (Substation 02-15 / SS-15) Firewall Finishing Work 42 03-Feb-26 23-Mar-26 (Substation 02-15 / SS-15) Firewall Finishing Work
HVAC
HVAC System
S95.21.CHV01.2110 (Substation 02-15 / SS-15) HVAC Equipment - Installation 42 05-Aug-25 22-Sep-25 (Substation 02-15 / SS-15) HVAC Equipment - Installation
S95.21.CHV01.2120 (Substation 02-15 / SS-15) HVAC Duct - Installation 108 05-Aug-25 08-Dec-25 (Substation 02-15 / SS-15) HVAC Duct - Installation
S95.21.CHV01.2130 (Substation 02-15 / SS-15) HVAC Piping - Installation 54 23-Sep-25 24-Nov-25 (Substation 02-15 / SS-15) HVAC Piping - Installation
S95.21.CHV01.2140 (Substation 02-15 / SS-15) HVAC Control System - Installation 78 07-Oct-25 05-Jan-26 (Substation 02-15 / SS-15) HVAC Control System - Installation
S95.21.CHV01.2150 (Substation 02-15 / SS-15) HVAC System - SAT 24 06-Jan-26 02-Feb-26 (Substation 02-15 / SS-15) HVAC System - SAT
S95.21.CHV01.4110 (Process Interface Building / PIB-15) HVAC Equipment - Installation 42 09-Dec-25 26-Jan-26 (Process Interface Building / PIB-15) HVAC Equipment - Installation
S95.21.CHV01.4120 (Process Interface Building / PIB-15) HVAC Duct - Installation 78 09-Dec-25 09-Mar-26 (Process Interface Building / PIB-15) HVAC Duct - Installation
S95.21.CHV01.4130 (Process Interface Building / PIB-15) HVAC Piping - Installation 54 27-Jan-26 30-Mar-26 (Process Interface Building / PIB-15) HVAC Piping - Installation
S95.21.CHV01.4140 (Process Interface Building / PIB-15) HVAC Control System - Installation 66 27-Jan-26 13-Apr-26 (Process Interface Building / PIB-15) HVAC Control System - Installation
S95.21.CHV01.4150 (Process Interface Building / PIB-15) HVAC System - SAT 24 14-Apr-26 11-May-26 (Process Interface Building / PIB-15) HVAC System - SAT
S95.21.CHV01.5110 (Operator Shelter / OPS-15) HVAC Equipment - Installation 36 03-Mar-26 13-Apr-26 (Operator Shelter / OPS-15) HVAC Equipment - Installation
S95.21.CHV01.5120 (Operator Shelter / OPS-15) HVAC Duct - Installation 66 03-Mar-26 18-May-26 (Operator Shelter / OPS-15) HVAC Duct - Installation
S95.21.CHV01.5130 (Operator Shelter / OPS-15) HVAC Piping - Installation 48 14-Apr-26 08-Jun-26 (Operator Shelter / OPS-15) HVAC Piping - Installation
S95.21.CHV01.5140 (Operator Shelter / OPS-15) HVAC Control System - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-15) HVAC Control System - Installation
S95.21.CHV01.5150 (Operator Shelter / OPS-15) HVAC System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-15) HVAC System - SAT
Plumbing System
S95.21.CHV02.2110 (Substation 02-15 / SS-15) U/G Plumbing Piping - Installation 18 31-Dec-24 20-Jan-25 (Substation 02-15 / SS-15) U/G Plumbing Piping - Installation
S95.21.CHV02.2120 (Substation 02-15 / SS-15) A/G Plumbing Piping - Installation 66 23-Sep-25 08-Dec-25 (Substation 02-15 / SS-15) A/G Plumbing Piping - Installation
S95.21.CHV02.2130 (Substation 02-15 / SS-15) Plumbing Equipment - Installation 30 23-Sep-25 27-Oct-25 (Substation 02-15 / SS-15) Plumbing Equipment - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 56 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S95.21.CHV02.2140 (Substation 02-15 / SS-15) Plumbing System - SAT 24 09-Dec-25 05-Jan-26 (Substation 02-15 / SS-15) Plumbing System - SAT
S95.21.CHV02.4110 (Process Interface Building / PIB-15) U/G Plumbing Piping - Installation 18 11-Mar-25 31-Mar-25 (Process Interface Building / PIB-15) U/G Plumbing Piping - Installation
S95.21.CHV02.4120 (Process Interface Building / PIB-15) A/G Plumbing Piping - Installation 66 27-Jan-26 13-Apr-26 (Process Interface Building / PIB-15) A/G Plumbing Piping - Installation
S95.21.CHV02.4130 (Process Interface Building / PIB-15) Plumbing Equipment - Installation 30 10-Mar-26 13-Apr-26 (Process Interface Building / PIB-15) Plumbing Equipment - Installation
S95.21.CHV02.4140 (Process Interface Building / PIB-15) Plumbing System - SAT 24 14-Apr-26 11-May-26 (Process Interface Building / PIB-15) Plumbing System - SAT
S95.21.CHV02.5110 (Operator Shelter / OPS-15) U/G Plumbing Piping - Installation 18 29-Apr-25 19-May-25 (Operator Shelter / OPS-15) U/G Plumbing Piping - Installation
S95.21.CHV02.5120 (Operator Shelter / OPS-15) A/G Plumbing Piping - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-15) A/G Plumbing Piping - Installation
S95.21.CHV02.5130 (Operator Shelter / OPS-15) Plumbing Equipment - Installation 30 19-May-26 22-Jun-26 (Operator Shelter / OPS-15) Plumbing Equipment - Installation
S95.21.CHV02.5140 (Operator Shelter / OPS-15) Plumbing System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-15) Plumbing System - SAT
Steel Structure
Piperack
S95.21.CSS01.1110 (Produced Water Treatment Plant & Common) Piperack Installation 156 20-May-25 17-Nov-25 (Produced Water Treatment Plant & Common) Piperack Installation
S95.21.CSS01.1120 (Produced Water Treatment Plant & Common) Misc. Steel Installation 72 18-Nov-25 09-Feb-26 (Produced Water Treatment Plant & Common) Misc. Steel Installation
Platform & Ladder
S95.21.CSS02.1110 (Produced Water Treatment Plant & Common) Equipment Platform Installation 90 10-Feb-26 25-May-26 (Produced Water Treatment Plant & Common) Equipment Platform Installation
Static Equipment
Tank
S95.21.CMS01.1142 [S95-D-0001 A/B/C/D] Feed Receiving Tank 330 06-May-25 25-May-26 [S95-D-0001 A/B/C/D] Feed Receiving Tank
Vessel
S95.21.CMS02.1124 [S95-D-0004 A/B] Recovered Oil Drum 36 12-May-26 22-Jun-26 [S95-D-0004 A/B] Recovered Oil Drum
Packaged Equipment
S95.21.CMS07.1153 [S95-U-0103] Nutshell Filter Package 132 11-Nov-25 13-Apr-26 [S95-U-0103] Nutshell Filter Package
S95.21.CMS07.1154 [S95-U-0203] Nutshell Filter Package 132 11-Nov-25 13-Apr-26 [S95-U-0203] Nutshell Filter Package
S95.21.CMS07.1155 [S95-U-0303] Nutshell Filter Package 132 11-Nov-25 13-Apr-26 [S95-U-0303] Nutshell Filter Package
S95.21.CMS07.1156 [S95-U-0104] Cartridge Filter Package 132 11-Nov-25 13-Apr-26 [S95-U-0104] Cartridge Filter Package
S95.21.CMS07.1157 [S95-U-0204] Cartridge Filter Package 132 11-Nov-25 13-Apr-26 [S95-U-0204] Cartridge Filter Package
S95.21.CMS07.1158 [S95-U-0304] Cartridge Filter Package 132 11-Nov-25 13-Apr-26 [S95-U-0304] Cartridge Filter Package
S95.21.CMS07.1159 [S95-U-0101] Desanding Package A 132 09-Sep-25 09-Feb-26 [S95-U-0101] Desanding Package A
S95.21.CMS07.1160 [S95-U-0201] Desanding Package B 132 09-Sep-25 09-Feb-26 [S95-U-0201] Desanding Package B
S95.21.CMS07.1161 [S95-U-0301] Desanding Package C 132 09-Sep-25 09-Feb-26 [S95-U-0301] Desanding Package C
Rotating Equipment
Pump
S95.21.CMR02.1116 [S95-G-0006 A/B] Recovered Oily Water Pump 36 16-Sep-25 27-Oct-25 [S95-G-0006 A/B] Recovered Oily Water Pump
S95.21.CMR02.1125 [S95-G-0014 A/B/C/D/E/F/G/H/I/J] Oily Water Treatment Package Feed Pump 54 10-Mar-26 11-May-26 [S95-G-0014 A/B/C/D/E/F/G/H/I/J] Oily Water Treatment Package Feed Pump
S95.21.CMR02.1126 [S95-G-0102 A/B/C/D] Nutshell Filter Feed Pump 36 10-Mar-26 20-Apr-26 [S95-G-0102 A/B/C/D] Nutshell Filter Feed Pump
S95.21.CMR02.1127 [S95-G-0202 A/B/C/D] Nutshell Filter Feed Pump 36 10-Mar-26 20-Apr-26 [S95-G-0202 A/B/C/D] Nutshell Filter Feed Pump
S95.21.CMR02.1128 [S95-G-0302 A/B/C/D] Nutshell Filter Feed Pump 36 10-Mar-26 20-Apr-26 [S95-G-0302 A/B/C/D] Nutshell Filter Feed Pump
S95.21.CMR02.1139 [S93-G-0703 A/B/C] Lift Station 2 Low Flow Pump 36 03-Mar-26 13-Apr-26 [S93-G-0703 A/B/C] Lift Station 2 Low Flow Pump
S95.21.CMR02.1140 [S93-G-0704 A/B] Lift Station 2 High Flow Pump 36 03-Mar-26 13-Apr-26 [S93-G-0704 A/B] Lift Station 2 High Flow Pump
S95.21.CMR02.1151 [S93-G-0733 A/B/S] Sewage Lift Station 9 Pump 36 23-Sep-25 03-Nov-25 [S93-G-0733 A/B/S] Sewage Lift Station 9 Pump
Packaged Equipment
S95.21.CMR07.1166 [S95-U-0105/0205/0305] Sludge Handling Package 108 30-Sep-25 02-Feb-26 [S95-U-0105/0205/0305] Sludge Handling Package
S95.21.CMR07.1168 [S95-U-0102/0202/0302] Oily Water Treatment Package 108 30-Sep-25 02-Feb-26 [S95-U-0102/0202/0302] Oily Water Treatment Package
S95.21.CMR07.1174 [S93-U-0716] Sanitary Odour Control Unit 9 36 04-Nov-25 15-Dec-25 [S93-U-0716] Sanitary Odour Control Unit 9
Piping
Underground (U/G) Piping
S95.21.CPI01.1110 (Produced Water Treatment Plant & Common) U/G Piping Field Installation (with Pressure Test) 288 29-Oct-24 29-Sep-25 (Produced Water Treatment Plant & Common) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S95.21.CPI02.1110 (Produced Water Treatment Plant & Common) A/G Piping Shop Fabrication 222 15-Apr-25 29-Dec-25 (Produced Water Treatment Plant & Common) A/G Piping Shop Fabrication
S95.21.CPI02.1120 (Produced Water Treatment Plant & Common) A/G Piping Field Installation 234 30-Sep-25 29-Jun-26 (Produced Water Treatment Plant & Common) A/G Piping Field Installation
S95.21.CPI02.1121 (Produced Water Treatment Plant & Common) A/G Piping Support Installation 204 02-Dec-25 27-Jul-26 (Produced Water Treatment Plant & Common) A/G Piping Support Installation
S95.21.CPI02.1130 (Produced Water Treatment Plant & Common) A/G Piping Pressure Test 126 03-Mar-26 27-Jul-26 (Produced Water Treatment Plant & Common) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S95.21.CPA01.1110 (Produced Water Treatment Plant & Common) Piping Painting 78 30-Jun-26 28-Sep-26 (Produced Water Treatment Plant & Common) Piping Painting
Insulation
S95.21.CPA02.1110 (Produced Water Treatment Plant & Common) Piping Insulation 78 30-Jun-26 28-Sep-26 (Produced Water Treatment Plant & Common) Piping Insulation
Refractory
S95.21.CPA03.1110 (Produced Water Treatment Plant & Common) Refractory 108 26-May-26 28-Sep-26 (Produced Water Treatment Plant & Common) Refractory
Electrical
S95.21.CEL06.1210 (Produced Water Treatment Plant & Common) Motor Solo-run Test (for MV) 78 29-May-27 26-Aug-27 (Produced Water Treatment Plant & Common) Motor Solo-run Test (for MV)
Cabling Work (Tray / Pulling & Termination)
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 57 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S95.21.CEL01.1110 (Produced Water Treatment Plant & Common) Electrical Cable Tray & Conduit 114 18-Nov-25 30-Mar-26 (Produced Water Treatment Plant & Common) Electrical Cable Tray & Conduit
S95.21.CEL01.1120 (Produced Water Treatment Plant & Common) Electrical Cable Pulling & Termination 138 20-Jan-26 29-Jun-26 (Produced Water Treatment Plant & Common) Electrical Cable Pulling & Termination
S95.21.CEL01.2110 (Substation 02-15 / SS-15) Electrical Cable Tray & Conduit 120 05-Aug-25 22-Dec-25 (Substation 02-15 / SS-15) Electrical Cable Tray & Conduit
S95.21.CEL01.2120 (Substation 02-15 / SS-15) Electrical Cable Pulling & Termination 138 16-Sep-25 23-Feb-26 (Substation 02-15 / SS-15) Electrical Cable Pulling & Termination
S95.21.CEL01.4110 (Process Interface Building / PIB-15) Electrical Cable Tray & Conduit 120 30-Sep-25 16-Feb-26 (Process Interface Building / PIB-15) Electrical Cable Tray & Conduit
S95.21.CEL01.4120 (Process Interface Building / PIB-15) Electrical Cable Pulling & Termination 138 11-Nov-25 20-Apr-26 (Process Interface Building / PIB-15) Electrical Cable Pulling & Termination
S95.21.CEL01.5110 (Operator Shelter / OPS-15) Electrical Cable Tray & Conduit 120 02-Dec-25 20-Apr-26 (Operator Shelter / OPS-15) Electrical Cable Tray & Conduit
S95.21.CEL01.5120 (Operator Shelter / OPS-15) Electrical Cable Pulling & Termination 138 13-Jan-26 22-Jun-26 (Operator Shelter / OPS-15) Electrical Cable Pulling & Termination
Transformer
S95.21.CEL02.2120 (Substation 02-15 / SS-15) Distribution Transformer - Installation 60 25-Nov-25 02-Feb-26 (Substation 02-15 / SS-15) Distribution Transformer - Installation
S95.21.CEL02.2130 (Substation 02-15 / SS-15) Neutral Grounding Resistor (NGR) - Installation 36 25-Nov-25 05-Jan-26 (Substation 02-15 / SS-15) Neutral Grounding Resistor (NGR) - Installation
S95.21.CEL02.2210 (Substation 02-15 / SS-15) Cablebus - Installation 42 06-Jan-26 23-Feb-26 (Substation 02-15 / SS-15) Cablebus - Installation
Switchgear & MCC (Motor Control Center)
S95.21.CEL03.2110 (Substation 02-15 / SS-15) MV Switchgear & MCC - Installation 78 07-Oct-25 05-Jan-26 (Substation 02-15 / SS-15) MV Switchgear & MCC - Installation
S95.21.CEL03.2120 (Substation 02-15 / SS-15) LV Switchgear & MCC - Installation 132 07-Oct-25 09-Mar-26 (Substation 02-15 / SS-15) LV Switchgear & MCC - Installation
S95.21.CEL03.2210 (Substation 02-15 / SS-15) PSA - Installation 102 07-Oct-25 02-Feb-26 (Substation 02-15 / SS-15) PSA - Installation
S95.21.CEL03.2220 (Substation 02-15 / SS-15) Electrical Panel - Installation 156 07-Oct-25 06-Apr-26 (Substation 02-15 / SS-15) Electrical Panel - Installation
S95.21.CEL03.2230 (Substation 02-15 / SS-15) Telecommunication System - Installation 102 07-Oct-25 02-Feb-26 (Substation 02-15 / SS-15) Telecommunication System - Installation
S95.21.CEL03.2310 (Substation 02-15 / SS-15) MV Switchgear & MCC - Test 36 03-Feb-26 16-Mar-26 (Substation 02-15 / SS-15) MV Switchgear & MCC - Test
S95.21.CEL03.2320 (Substation 02-15 / SS-15) LV Switchgear & MCC - Test 72 10-Mar-26 01-Jun-26 (Substation 02-15 / SS-15) LV Switchgear & MCC - Test
S95.21.CEL03.2330 (Substation 02-15 / SS-15) PSA - Test 54 03-Feb-26 06-Apr-26 (Substation 02-15 / SS-15) PSA - Test
S95.21.CEL03.4210 (Process Interface Building / PIB-15) Electrical Panel - Installation 144 09-Dec-25 25-May-26 (Process Interface Building / PIB-15) Electrical Panel - Installation
UPS & DC System
S95.21.CEL04.2110 (Substation 02-15 / SS-15) UPS & DC System - Installation 54 07-Oct-25 08-Dec-25 (Substation 02-15 / SS-15) UPS & DC System - Installation
S95.21.CEL04.2120 (Substation 02-15 / SS-15) UPS & DC System - Test 24 23-Dec-25 19-Jan-26 (Substation 02-15 / SS-15) UPS & DC System - Test
S95.21.CEL04.4110 (Process Interface Building / PIB-15) UPS & DC System - Installation 54 09-Dec-25 09-Feb-26 (Process Interface Building / PIB-15) UPS & DC System - Installation
S95.21.CEL04.4120 (Process Interface Building / PIB-15) UPS & DC System - Test 24 10-Feb-26 09-Mar-26 (Process Interface Building / PIB-15) UPS & DC System - Test
Lighting System
S95.21.CEL05.1110 (Produced Water Treatment Plant & Common) Lighting System Installation 102 10-Feb-26 08-Jun-26 (Produced Water Treatment Plant & Common) Lighting System Installation
S95.21.CEL05.2110 (Substation 02-15 / SS-15) Lighting System - Installation 132 07-Oct-25 09-Mar-26 (Substation 02-15 / SS-15) Lighting System - Installation
S95.21.CEL05.2120 (Substation 02-15 / SS-15) Grounding - Installation 264 04-Feb-25 08-Dec-25 (Substation 02-15 / SS-15) Grounding - Installation
S95.21.CEL05.4110 (Process Interface Building / PIB-15) Lighting System - Installation 132 09-Dec-25 11-May-26 (Process Interface Building / PIB-15) Lighting System - Installation
S95.21.CEL05.4120 (Process Interface Building / PIB-15) Grounding - Installation 246 15-Apr-25 26-Jan-26 (Process Interface Building / PIB-15) Grounding - Installation
S95.21.CEL05.5110 (Operator Shelter / OPS-15) Lighting System - Installation 132 03-Mar-26 03-Aug-26 (Operator Shelter / OPS-15) Lighting System - Installation
S95.21.CEL05.5120 (Operator Shelter / OPS-15) Grounding - Installation 258 03-Jun-25 30-Mar-26 (Operator Shelter / OPS-15) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S95.21.CCI01.1110 (Produced Water Treatment Plant & Common) I&C Cable Tray & Conduit 138 18-Nov-25 27-Apr-26 (Produced Water Treatment Plant & Common) I&C Cable Tray & Conduit
S95.21.CCI01.1120 (Produced Water Treatment Plant & Common) I&C Cable Pulling & Termination 162 20-Jan-26 27-Jul-26 (Produced Water Treatment Plant & Common) I&C Cable Pulling & Termination
S95.21.CCI01.2110 (Substation 02-15 / SS-15) I&C Cable Tray & Conduit 96 07-Oct-25 26-Jan-26 (Substation 02-15 / SS-15) I&C Cable Tray & Conduit
S95.21.CCI01.2120 (Substation 02-15 / SS-15) I&C Cable Pulling & Termination 114 18-Nov-25 30-Mar-26 (Substation 02-15 / SS-15) I&C Cable Pulling & Termination
S95.21.CCI01.4110 (Process Interface Building / PIB-15) I&C Cable Tray & Conduit 138 30-Sep-25 09-Mar-26 (Process Interface Building / PIB-15) I&C Cable Tray & Conduit
S95.21.CCI01.4120 (Process Interface Building / PIB-15) I&C Cable Pulling & Termination 156 11-Nov-25 11-May-26 (Process Interface Building / PIB-15) I&C Cable Pulling & Termination
Field Instrument
S95.21.CCI02.1110 (Produced Water Treatment Plant & Common) Field Instrument Installation (with Calibration) 84 21-Apr-26 27-Jul-26 (Produced Water Treatment Plant & Common) Field Instrument Installation (with Calibration)
PCS (MAC) & Instrument Panel
S95.21.CCI03.4110 (Process Interface Building / PIB-15) PCS - Installation 96 09-Dec-25 30-Mar-26 (Process Interface Building / PIB-15) PCS - Installation
S95.21.CCI03.4120 (Process Interface Building / PIB-15) PCS - Test 102 31-Mar-26 27-Jul-26 (Process Interface Building / PIB-15) PCS - Test
Loop Test
S95.21.CCI04.1110 (Produced Water Treatment Plant & Common) Loop Test 108 28-Apr-26 31-Aug-26 (Produced Water Treatment Plant & Common) Loop Test
Pre-commissioning
S95.21.CPC03.1110 (Produced Water Treatment Plant & Common) Leak Test 132 29-May-27 28-Oct-27 (Produced Water Treatment Plant & Common) Leak Test
S95.21.CPC03.1120 (Produced Water Treatment Plant & Common) Mechanical Running Test 132 29-May-27 28-Oct-27 (Produced Water Treatment Plant & Common) Mechanical Runnin
Flushing & Blowing
S95.21.CPC01.1110 (Produced Water Treatment Plant & Common) Mechanical Cleaning 78 28-Jul-26 26-Oct-26 (Produced Water Treatment Plant & Common) Mechanical Cleaning
Function Test
S95.21.CPC02.1110 (Produced Water Treatment Plant & Common) Function Test 78 28-Jul-26 26-Oct-26 (Produced Water Treatment Plant & Common) Function Test
Produced Water Treatment Plant Injection
Civil
Foundation (Tank)
S95.22.CCV01.1110 (Produced Water Treatment Plant Injection) Tank Foundation 186 27-Aug-24 31-Mar-25 (Produced Water Treatment Plant Injection) Tank Foundation
Foundation (Equipment & Piperack)
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 58 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S95.22.CCV02.1110 (Produced Water Treatment Plant Injection) Equipment Foundation 180 01-Apr-25 27-Oct-25 (Produced Water Treatment Plant Injection) Equipment Foundation
S95.22.CCV02.1120 (Produced Water Treatment Plant Injection) Piperack Foundation 156 31-Dec-24 30-Jun-25 (Produced Water Treatment Plant Injection) Piperack Foundation
Misc. Foundation & Paving
S95.22.CCV03.1110 (Produced Water Treatment Plant Injection) Misc. Foundation & Concrete Paving 180 31-Mar-26 26-Oct-26 (Produced Water Treatment Plant Injection) Misc. Foundation & Concrete Paving
S95.22.CCV03.1120 (Produced Water Treatment Plant Injection) Asphalt Paving & Road 42 27-Oct-26 14-Dec-26 (Produced Water Treatment Plant Injection) Asphalt Paving & Road
Architecture
Reinforced Concrete Building
S95.22.CAR01.2110 (Substation 01-05 / SS-05) Substructure 60 24-Dec-24 03-Mar-25 (Substation 01-05 / SS-05) Substructure
S95.22.CAR01.2120 (Substation 01-05 / SS-05) Superstructure (Wall / Roof) 156 04-Mar-25 01-Sep-25 (Substation 01-05 / SS-05) Superstructure (Wall / Roof)
S95.22.CAR01.2130 (Substation 01-05 / SS-05) Interior Work 54 02-Sep-25 03-Nov-25 (Substation 01-05 / SS-05) Interior Work
S95.22.CAR01.2140 (Substation 01-05 / SS-05) Finishing Work 210 04-Nov-25 06-Jul-26 (Substation 01-05 / SS-05) Finishing Work
S95.22.CAR01.3110 (EDG Building / EDG-05) Substructure 42 08-Apr-25 26-May-25 (EDG Building / EDG-05) Substructure
S95.22.CAR01.3120 (EDG Building / EDG-05) Superstructure (Wall / Roof) 90 27-May-25 08-Sep-25 (EDG Building / EDG-05) Superstructure (Wall / Roof)
S95.22.CAR01.3130 (EDG Building / EDG-05) Interior Work 24 09-Sep-25 06-Oct-25 (EDG Building / EDG-05) Interior Work
S95.22.CAR01.3140 (EDG Building / EDG-05) Finishing Work 132 07-Oct-25 09-Mar-26 (EDG Building / EDG-05) Finishing Work
S95.22.CAR01.4110 (Process Interface Building / PIB-05) Substructure 60 04-Mar-25 12-May-25 (Process Interface Building / PIB-05) Substructure
S95.22.CAR01.4120 (Process Interface Building / PIB-05) Superstructure (Wall / Roof) 144 13-May-25 27-Oct-25 (Process Interface Building / PIB-05) Superstructure (Wall / Roof)
S95.22.CAR01.4130 (Process Interface Building / PIB-05) Interior Work 60 28-Oct-25 05-Jan-26 (Process Interface Building / PIB-05) Interior Work
S95.22.CAR01.4140 (Process Interface Building / PIB-05) Finishing Work 186 06-Jan-26 10-Aug-26 (Process Interface Building / PIB-05) Finishing Work
Reinforced Concrete Structure
S95.22.CAR02.2110 (Substation 01-05 / SS-05) Transformer Foundation 54 02-Sep-25 03-Nov-25 (Substation 01-05 / SS-05) Transformer Foundation
S95.22.CAR02.2120 (Substation 01-05 / SS-05) Firewall Structure 42 04-Nov-25 22-Dec-25 (Substation 01-05 / SS-05) Firewall Structure
S95.22.CAR02.2130 (Substation 01-05 / SS-05) Firewall Finishing Work 42 03-Mar-26 20-Apr-26 (Substation 01-05 / SS-05) Firewall Finishing Work
HVAC
HVAC System
S95.22.CHV01.2110 (Substation 01-05 / SS-05) HVAC Equipment - Installation 42 02-Sep-25 20-Oct-25 (Substation 01-05 / SS-05) HVAC Equipment - Installation
S95.22.CHV01.2120 (Substation 01-05 / SS-05) HVAC Duct - Installation 108 02-Sep-25 05-Jan-26 (Substation 01-05 / SS-05) HVAC Duct - Installation
S95.22.CHV01.2130 (Substation 01-05 / SS-05) HVAC Piping - Installation 54 21-Oct-25 22-Dec-25 (Substation 01-05 / SS-05) HVAC Piping - Installation
S95.22.CHV01.2140 (Substation 01-05 / SS-05) HVAC Control System - Installation 78 04-Nov-25 02-Feb-26 (Substation 01-05 / SS-05) HVAC Control System - Installation
S95.22.CHV01.2150 (Substation 01-05 / SS-05) HVAC System - SAT 24 03-Feb-26 02-Mar-26 (Substation 01-05 / SS-05) HVAC System - SAT
S95.22.CHV01.3110 (EDG Building / EDG-05) HVAC Equipment - Installation 12 07-Oct-25 20-Oct-25 (EDG Building / EDG-05) HVAC Equipment - Installation
S95.22.CHV01.3120 (EDG Building / EDG-05) HVAC Duct - Installation 24 07-Oct-25 03-Nov-25 (EDG Building / EDG-05) HVAC Duct - Installation
S95.22.CHV01.3130 (EDG Building / EDG-05) HVAC Piping - Installation 24 21-Oct-25 17-Nov-25 (EDG Building / EDG-05) HVAC Piping - Installation
S95.22.CHV01.3140 (EDG Building / EDG-05) HVAC Control System - Installation 24 07-Oct-25 03-Nov-25 (EDG Building / EDG-05) HVAC Control System - Installation
S95.22.CHV01.3150 (EDG Building / EDG-05) HVAC System - SAT 12 18-Nov-25 01-Dec-25 (EDG Building / EDG-05) HVAC System - SAT
S95.22.CHV01.4110 (Process Interface Building / PIB-05) HVAC Equipment - Installation 42 06-Jan-26 23-Feb-26 (Process Interface Building / PIB-05) HVAC Equipment - Installation
S95.22.CHV01.4120 (Process Interface Building / PIB-05) HVAC Duct - Installation 78 06-Jan-26 06-Apr-26 (Process Interface Building / PIB-05) HVAC Duct - Installation
S95.22.CHV01.4130 (Process Interface Building / PIB-05) HVAC Piping - Installation 54 24-Feb-26 27-Apr-26 (Process Interface Building / PIB-05) HVAC Piping - Installation
S95.22.CHV01.4140 (Process Interface Building / PIB-05) HVAC Control System - Installation 66 24-Feb-26 11-May-26 (Process Interface Building / PIB-05) HVAC Control System - Installation
S95.22.CHV01.4150 (Process Interface Building / PIB-05) HVAC System - SAT 24 12-May-26 08-Jun-26 (Process Interface Building / PIB-05) HVAC System - SAT
Plumbing System
S95.22.CHV02.2110 (Substation 01-05 / SS-05) U/G Plumbing Piping - Installation 18 28-Jan-25 17-Feb-25 (Substation 01-05 / SS-05) U/G Plumbing Piping - Installation
S95.22.CHV02.2120 (Substation 01-05 / SS-05) A/G Plumbing Piping - Installation 66 21-Oct-25 05-Jan-26 (Substation 01-05 / SS-05) A/G Plumbing Piping - Installation
S95.22.CHV02.2130 (Substation 01-05 / SS-05) Plumbing Equipment - Installation 30 21-Oct-25 24-Nov-25 (Substation 01-05 / SS-05) Plumbing Equipment - Installation
S95.22.CHV02.2140 (Substation 01-05 / SS-05) Plumbing System - SAT 24 06-Jan-26 02-Feb-26 (Substation 01-05 / SS-05) Plumbing System - SAT
S95.22.CHV02.3110 (EDG Building / EDG-05) U/G Plumbing Piping - Installation 6 06-May-25 12-May-25 (EDG Building / EDG-05) U/G Plumbing Piping - Installation
S95.22.CHV02.3120 (EDG Building / EDG-05) A/G Plumbing Piping - Installation 24 21-Oct-25 17-Nov-25 (EDG Building / EDG-05) A/G Plumbing Piping - Installation
S95.22.CHV02.3130 (EDG Building / EDG-05) Plumbing Equipment - Installation 12 21-Oct-25 03-Nov-25 (EDG Building / EDG-05) Plumbing Equipment - Installation
S95.22.CHV02.3140 (EDG Building / EDG-05) Plumbing System - SAT 12 18-Nov-25 01-Dec-25 (EDG Building / EDG-05) Plumbing System - SAT
S95.22.CHV02.4110 (Process Interface Building / PIB-05) U/G Plumbing Piping - Installation 18 08-Apr-25 28-Apr-25 (Process Interface Building / PIB-05) U/G Plumbing Piping - Installation
S95.22.CHV02.4120 (Process Interface Building / PIB-05) A/G Plumbing Piping - Installation 66 24-Feb-26 11-May-26 (Process Interface Building / PIB-05) A/G Plumbing Piping - Installation
S95.22.CHV02.4130 (Process Interface Building / PIB-05) Plumbing Equipment - Installation 30 07-Apr-26 11-May-26 (Process Interface Building / PIB-05) Plumbing Equipment - Installation
S95.22.CHV02.4140 (Process Interface Building / PIB-05) Plumbing System - SAT 24 12-May-26 08-Jun-26 (Process Interface Building / PIB-05) Plumbing System - SAT
Steel Structure
Piperack
S95.22.CSS01.1110 (Produced Water Treatment Plant Injection) Piperack Installation 156 01-Jul-25 29-Dec-25 (Produced Water Treatment Plant Injection) Piperack Installation
S95.22.CSS01.1120 (Produced Water Treatment Plant Injection) Misc. Steel Installation 78 30-Dec-25 30-Mar-26 (Produced Water Treatment Plant Injection) Misc. Steel Installation
Platform & Ladder
S95.22.CSS02.1110 (Produced Water Treatment Plant Injection) Equipment Platform Installation 102 31-Mar-26 27-Jul-26 (Produced Water Treatment Plant Injection) Equipment Platform Installation
Static Equipment
Tank
S95.22.CMS01.1141 [S95-D-0010 A/B] Reservoir Injection Water Buffer Tank 258 06-May-25 02-Mar-26 [S95-D-0010 A/B] Reservoir Injection Water Buffer Tank
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 59 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
S95.22.CMS01.1143 [S95-D-0005 A/B] Corrosion Inhibitor Tank 108 06-May-25 08-Sep-25 [S95-D-0005 A/B] Corrosion Inhibitor Tank
S95.22.CMS01.1144 [S95-D-0006 A/B] Scale Inhibitor Tank 108 06-May-25 08-Sep-25 [S95-D-0006 A/B] Scale Inhibitor Tank
S95.22.CMS01.1145 [S95-D-0007 A/B] Biocide Tank 108 06-May-25 08-Sep-25 [S95-D-0007 A/B] Biocide Tank
S95.22.CMS01.1146 [S95-D-0008 A/B] pH Correction Tank 108 06-May-25 08-Sep-25 [S95-D-0008 A/B] pH Correction Tank
S95.22.CMS01.1147 [S95-D-0009 A/B] Oxygen Scavenger Tank 108 06-May-25 08-Sep-25 [S95-D-0009 A/B] Oxygen Scavenger Tank
Rotating Equipment
Pump
S95.22.CMR02.1114 [S95-G-0001 A/B/C/D] NSF Backwash Feed Pump 54 28-Oct-25 29-Dec-25 [S95-G-0001 A/B/C/D] NSF Backwash Feed Pump
S95.22.CMR02.1115 [S95-G-0002 A/B/C/D] Sand Cleaning Package Feed Pump 54 28-Oct-25 29-Dec-25 [S95-G-0002 A/B/C/D] Sand Cleaning Package Feed Pump
S95.22.CMR02.1122 [S95-G-0012 A~M] Treated Water Injection Booster Pump 96 10-Mar-26 29-Jun-26 [S95-G-0012 A~M] Treated Water Injection Booster Pump
S95.22.CMR02.1123 [S95-G-0013 A~M] Treated Water Injection Pump 96 10-Mar-26 29-Jun-26 [S95-G-0013 A~M] Treated Water Injection Pump
S95.22.CMR02.1141 [S93-G-0705 A/B/C] Lift Station 3 Low Flow Pump 36 03-Mar-26 13-Apr-26 [S93-G-0705 A/B/C] Lift Station 3 Low Flow Pump
S95.22.CMR02.1142 [S93-G-0706 A/B] Lift Station 3 High Flow Pump 36 03-Mar-26 13-Apr-26 [S93-G-0706 A/B] Lift Station 3 High Flow Pump
Packaged Equipment
S95.22.CMR07.1159 [S95-U-0003] Corrosion Inhibitor Package 108 28-Oct-25 02-Mar-26 [S95-U-0003] Corrosion Inhibitor Package
S95.22.CMR07.1160 [S95-U-0004] Scale Inhibitor Package 108 28-Oct-25 02-Mar-26 [S95-U-0004] Scale Inhibitor Package
S95.22.CMR07.1161 [S95-U-0005] Biocide Package 108 28-Oct-25 02-Mar-26 [S95-U-0005] Biocide Package
S95.22.CMR07.1162 [S95-U-0006] pH Correction Package 108 28-Oct-25 02-Mar-26 [S95-U-0006] pH Correction Package
S95.22.CMR07.1163 [S95-U-0007] Oxygen Scavenger Dosing Package 108 28-Oct-25 02-Mar-26 [S95-U-0007] Oxygen Scavenger Dosing Package
S95.22.CMR07.3110 [S95-U-XXX7] 7.5T Overhead Crane for EDG-05 12 07-Oct-25 20-Oct-25 [S95-U-XXX7] 7.5T Overhead Crane for EDG-05
S95.22.CMR07.3120 [S90-U-1016] Emergency Diesel Generator - Installation 24 16-Dec-25 12-Jan-26 [S90-U-1016] Emergency Diesel Generator - Installation
Piping
Underground (U/G) Piping
S95.22.CPI01.1110 (Produced Water Treatment Plant Injection) U/G Piping Field Installation (with Pressure Test) 312 29-Oct-24 27-Oct-25 (Produced Water Treatment Plant Injection) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S95.22.CPI02.1110 (Produced Water Treatment Plant Injection) A/G Piping Shop Fabrication 234 01-Apr-25 29-Dec-25 (Produced Water Treatment Plant Injection) A/G Piping Shop Fabrication
S95.22.CPI02.1120 (Produced Water Treatment Plant Injection) A/G Piping Field Installation 234 28-Oct-25 27-Jul-26 (Produced Water Treatment Plant Injection) A/G Piping Field Installation
S95.22.CPI02.1121 (Produced Water Treatment Plant Injection) A/G Piping Support Installation 210 30-Dec-25 31-Aug-26 (Produced Water Treatment Plant Injection) A/G Piping Support Installation
S95.22.CPI02.1130 (Produced Water Treatment Plant Injection) A/G Piping Pressure Test 132 31-Mar-26 31-Aug-26 (Produced Water Treatment Plant Injection) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S95.22.CPA01.1110 (Produced Water Treatment Plant Injection) Piping Painting 79 28-Jul-26 27-Oct-26 (Produced Water Treatment Plant Injection) Piping Painting
Insulation
S95.22.CPA02.1110 (Produced Water Treatment Plant Injection) Piping Insulation 79 28-Jul-26 27-Oct-26 (Produced Water Treatment Plant Injection) Piping Insulation
Refractory
S95.22.CPA03.1110 (Produced Water Treatment Plant Injection) Refractory 132 28-Jul-26 28-Dec-26 (Produced Water Treatment Plant Injection) Refractory
Electrical
S95.22.CEL06.1210 (Produced Water Treatment Plant Injection) Motor Solo-run Test (for MV) 54 11-May-27 12-Jul-27 (Produced Water Treatment Plant Injection) Motor Solo-run Test (for MV)
Cabling Work (Tray / Pulling & Termination)
S95.22.CEL01.1110 (Produced Water Treatment Plant Injection) Electrical Cable Tray & Conduit 120 30-Dec-25 18-May-26 (Produced Water Treatment Plant Injection) Electrical Cable Tray & Conduit
S95.22.CEL01.1120 (Produced Water Treatment Plant Injection) Electrical Cable Pulling & Termination 126 03-Mar-26 27-Jul-26 (Produced Water Treatment Plant Injection) Electrical Cable Pulling & Termination
S95.22.CEL01.2110 (Substation 01-05 / SS-05) Electrical Cable Tray & Conduit 120 02-Sep-25 19-Jan-26 (Substation 01-05 / SS-05) Electrical Cable Tray & Conduit
S95.22.CEL01.2120 (Substation 01-05 / SS-05) Electrical Cable Pulling & Termination 138 14-Oct-25 23-Mar-26 (Substation 01-05 / SS-05) Electrical Cable Pulling & Termination
S95.22.CEL01.3110 (EDG Building / EDG-05) Electrical Cable Tray & Conduit 36 09-Sep-25 20-Oct-25 (EDG Building / EDG-05) Electrical Cable Tray & Conduit
S95.22.CEL01.3120 (EDG Building / EDG-05) Electrical Cable Pulling & Termination 30 07-Oct-25 10-Nov-25 (EDG Building / EDG-05) Electrical Cable Pulling & Termination
S95.22.CEL01.4110 (Process Interface Building / PIB-05) Electrical Cable Tray & Conduit 114 28-Oct-25 09-Mar-26 (Process Interface Building / PIB-05) Electrical Cable Tray & Conduit
S95.22.CEL01.4120 (Process Interface Building / PIB-05) Electrical Cable Pulling & Termination 138 09-Dec-25 18-May-26 (Process Interface Building / PIB-05) Electrical Cable Pulling & Termination
Transformer
S95.22.CEL02.2120 (Substation 01-05 / SS-05) Distribution Transformer - Installation 60 23-Dec-25 02-Mar-26 (Substation 01-05 / SS-05) Distribution Transformer - Installation
S95.22.CEL02.2130 (Substation 01-05 / SS-05) Neutral Grounding Resistor (NGR) - Installation 36 23-Dec-25 02-Feb-26 (Substation 01-05 / SS-05) Neutral Grounding Resistor (NGR) - Installation
S95.22.CEL02.2210 (Substation 01-05 / SS-05) Cablebus - Installation 42 03-Feb-26 23-Mar-26 (Substation 01-05 / SS-05) Cablebus - Installation
Switchgear & MCC (Motor Control Center)
S95.22.CEL03.2110 (Substation 01-05 / SS-05) MV Switchgear & MCC - Installation 78 04-Nov-25 02-Feb-26 (Substation 01-05 / SS-05) MV Switchgear & MCC - Installation
S95.22.CEL03.2120 (Substation 01-05 / SS-05) LV Switchgear & MCC - Installation 132 04-Nov-25 06-Apr-26 (Substation 01-05 / SS-05) LV Switchgear & MCC - Installation
S95.22.CEL03.2210 (Substation 01-05 / SS-05) PSA - Installation 102 04-Nov-25 02-Mar-26 (Substation 01-05 / SS-05) PSA - Installation
S95.22.CEL03.2220 (Substation 01-05 / SS-05) Electrical Panel - Installation 156 04-Nov-25 04-May-26 (Substation 01-05 / SS-05) Electrical Panel - Installation
S95.22.CEL03.2230 (Substation 01-05 / SS-05) Telecommunication System - Installation 102 02-Sep-25 29-Dec-25 (Substation 01-05 / SS-05) Telecommunication System - Installation
S95.22.CEL03.2310 (Substation 01-05 / SS-05) MV Switchgear & MCC - Test 36 03-Mar-26 13-Apr-26 (Substation 01-05 / SS-05) MV Switchgear & MCC - Test
S95.22.CEL03.2320 (Substation 01-05 / SS-05) LV Switchgear & MCC - Test 72 07-Apr-26 29-Jun-26 (Substation 01-05 / SS-05) LV Switchgear & MCC - Test
S95.22.CEL03.2330 (Substation 01-05 / SS-05) PSA - Test 54 03-Mar-26 04-May-26 (Substation 01-05 / SS-05) PSA - Test
S95.22.CEL03.3310 (EDG Building / EDG-05) EDG - Test 24 13-Jan-26 09-Feb-26 (EDG Building / EDG-05) EDG - Test
S95.22.CEL03.4210 (Process Interface Building / PIB-05) Electrical Panel - Installation 144 06-Jan-26 22-Jun-26 (Process Interface Building / PIB-05) Electrical Panel - Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 60 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
UPS & DC System
S95.22.CEL04.2110 (Substation 01-05 / SS-05) UPS & DC System - Installation 54 04-Nov-25 05-Jan-26 (Substation 01-05 / SS-05) UPS & DC System - Installation
S95.22.CEL04.2120 (Substation 01-05 / SS-05) UPS & DC System - Test 24 20-Jan-26 16-Feb-26 (Substation 01-05 / SS-05) UPS & DC System - Test
S95.22.CEL04.4110 (Process Interface Building / PIB-05) UPS & DC System - Installation 54 06-Jan-26 09-Mar-26 (Process Interface Building / PIB-05) UPS & DC System - Installation
S95.22.CEL04.4120 (Process Interface Building / PIB-05) UPS & DC System - Test 24 10-Mar-26 06-Apr-26 (Process Interface Building / PIB-05) UPS & DC System - Test
Lighting System
S95.22.CEL05.1110 (Produced Water Treatment Plant Injection) Lighting System Installation 132 31-Mar-26 31-Aug-26 (Produced Water Treatment Plant Injection) Lighting System Installation
S95.22.CEL05.2110 (Substation 01-05 / SS-05) Lighting System - Installation 132 04-Nov-25 06-Apr-26 (Substation 01-05 / SS-05) Lighting System - Installation
S95.22.CEL05.2120 (Substation 01-05 / SS-05) Grounding - Installation 264 04-Mar-25 05-Jan-26 (Substation 01-05 / SS-05) Grounding - Installation
S95.22.CEL05.3110 (EDG Building / EDG-05) Lighting System - Installation 42 07-Oct-25 24-Nov-25 (EDG Building / EDG-05) Lighting System - Installation
S95.22.CEL05.3120 (EDG Building / EDG-05) Grounding - Installation 144 27-May-25 10-Nov-25 (EDG Building / EDG-05) Grounding - Installation
S95.22.CEL05.4110 (Process Interface Building / PIB-05) Lighting System - Installation 132 06-Jan-26 08-Jun-26 (Process Interface Building / PIB-05) Lighting System - Installation
S95.22.CEL05.4120 (Process Interface Building / PIB-05) Grounding - Installation 246 13-May-25 23-Feb-26 (Process Interface Building / PIB-05) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S95.22.CCI01.1110 (Produced Water Treatment Plant Injection) I&C Cable Tray & Conduit 144 30-Dec-25 15-Jun-26 (Produced Water Treatment Plant Injection) I&C Cable Tray & Conduit
S95.22.CCI01.1120 (Produced Water Treatment Plant Injection) I&C Cable Pulling & Termination 156 03-Mar-26 31-Aug-26 (Produced Water Treatment Plant Injection) I&C Cable Pulling & Termination
S95.22.CCI01.2110 (Substation 01-05 / SS-05) I&C Cable Tray & Conduit 96 04-Nov-25 23-Feb-26 (Substation 01-05 / SS-05) I&C Cable Tray & Conduit
S95.22.CCI01.2120 (Substation 01-05 / SS-05) I&C Cable Pulling & Termination 114 16-Dec-25 27-Apr-26 (Substation 01-05 / SS-05) I&C Cable Pulling & Termination
S95.22.CCI01.4110 (Process Interface Building / PIB-05) I&C Cable Tray & Conduit 138 28-Oct-25 06-Apr-26 (Process Interface Building / PIB-05) I&C Cable Tray & Conduit
S95.22.CCI01.4120 (Process Interface Building / PIB-05) I&C Cable Pulling & Termination 156 09-Dec-25 08-Jun-26 (Process Interface Building / PIB-05) I&C Cable Pulling & Termination
Field Instrument
S95.22.CCI02.1110 (Produced Water Treatment Plant Injection) Field Instrument Installation (with Calibration) 102 02-Jun-26 28-Sep-26 (Produced Water Treatment Plant Injection) Field Instrument Installation (with Calibration)
PCS (MAC) & Instrument Panel
S95.22.CCI03.4110 (Process Interface Building / PIB-05) PCS - Installation 96 06-Jan-26 27-Apr-26 (Process Interface Building / PIB-05) PCS - Installation
S95.22.CCI03.4120 (Process Interface Building / PIB-05) PCS - Installation 132 28-Apr-26 28-Sep-26 (Process Interface Building / PIB-05) PCS - Installation
Loop Test
S95.22.CCI04.1110 (Produced Water Treatment Plant Injection) Loop Test 114 16-Jun-26 26-Oct-26 (Produced Water Treatment Plant Injection) Loop Test
Pre-commissioning
S95.22.CPC03.1110 (Produced Water Treatment Plant Injection) Leak Test 78 29-May-27 26-Aug-27 (Produced Water Treatment Plant Injection) Leak Test
S95.22.CPC03.1120 (Produced Water Treatment Plant Injection) Mechanical Running Test 78 29-May-27 26-Aug-27 (Produced Water Treatment Plant Injection) Mechanical Running Test
Flushing & Blowing
S95.22.CPC01.1110 (Produced Water Treatment Plant Injection) Mechanical Cleaning 102 01-Sep-26 28-Dec-26 (Produced Water Treatment Plant Injection) Mechanical Cleaning
Function Test
S95.22.CPC02.1110 (Produced Water Treatment Plant Injection) Function Test 78 29-Sep-26 28-Dec-26 (Produced Water Treatment Plant Injection) Function Test
Pipeline Hub
Civil
Foundation (Equipment & Piperack)
S95.23.CCV02.1110 (Pipeline Hub) Equipment Foundation 66 02-Sep-25 17-Nov-25 (Pipeline Hub) Equipment Foundation
S95.23.CCV02.1120 (Pipeline Hub) Piperack Foundation 156 04-Mar-25 01-Sep-25 (Pipeline Hub) Piperack Foundation
Misc. Foundation & Paving
S95.23.CCV03.1110 (Pipeline Hub) Misc. Foundation & Concrete Paving 132 26-May-26 26-Oct-26 (Pipeline Hub) Misc. Foundation & Concrete Paving
S95.23.CCV03.1120 (Pipeline Hub) Asphalt Paving & Road 42 27-Oct-26 14-Dec-26 (Pipeline Hub) Asphalt Paving & Road
Architecture
Reinforced Concrete Building
S95.23.CAR01.5110 (Operator Shelter / OPS-05) Substructure 60 25-Mar-25 02-Jun-25 (Operator Shelter / OPS-05) Substructure
S95.23.CAR01.5120 (Operator Shelter / OPS-05) Superstructure (Wall / Roof) 156 03-Jun-25 01-Dec-25 (Operator Shelter / OPS-05) Superstructure (Wall / Roof)
S95.23.CAR01.5130 (Operator Shelter / OPS-05) Interior Work 78 02-Dec-25 02-Mar-26 (Operator Shelter / OPS-05) Interior Work
S95.23.CAR01.5140 (Operator Shelter / OPS-05) Finishing Work 168 03-Mar-26 14-Sep-26 (Operator Shelter / OPS-05) Finishing Work
HVAC
HVAC System
S95.23.CHV01.5110 (Operator Shelter / OPS-05) HVAC Equipment - Installation 36 03-Mar-26 13-Apr-26 (Operator Shelter / OPS-05) HVAC Equipment - Installation
S95.23.CHV01.5120 (Operator Shelter / OPS-05) HVAC Duct - Installation 66 03-Mar-26 18-May-26 (Operator Shelter / OPS-05) HVAC Duct - Installation
S95.23.CHV01.5130 (Operator Shelter / OPS-05) HVAC Piping - Installation 48 14-Apr-26 08-Jun-26 (Operator Shelter / OPS-05) HVAC Piping - Installation
S95.23.CHV01.5140 (Operator Shelter / OPS-05) HVAC Control System - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-05) HVAC Control System - Installation
S95.23.CHV01.5150 (Operator Shelter / OPS-05) HVAC System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-05) HVAC System - SAT
Plumbing System
S95.23.CHV02.5110 (Operator Shelter / OPS-05) U/G Plumbing Piping - Installation 18 29-Apr-25 19-May-25 (Operator Shelter / OPS-05) U/G Plumbing Piping - Installation
S95.23.CHV02.5120 (Operator Shelter / OPS-05) A/G Plumbing Piping - Installation 60 14-Apr-26 22-Jun-26 (Operator Shelter / OPS-05) A/G Plumbing Piping - Installation
S95.23.CHV02.5130 (Operator Shelter / OPS-05) Plumbing Equipment - Installation 30 19-May-26 22-Jun-26 (Operator Shelter / OPS-05) Plumbing Equipment - Installation
S95.23.CHV02.5140 (Operator Shelter / OPS-05) Plumbing System - SAT 30 23-Jun-26 27-Jul-26 (Operator Shelter / OPS-05) Plumbing System - SAT
Steel Structure
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 61 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
Piperack
S95.23.CSS01.1110 (Pipeline Hub) Piperack Installation 150 02-Sep-25 23-Feb-26 (Pipeline Hub) Piperack Installation
S95.23.CSS01.1120 (Pipeline Hub) Misc. Steel Installation 78 24-Feb-26 25-May-26 (Pipeline Hub) Misc. Steel Installation
Platform & Ladder
S95.23.CSS02.1110 (Pipeline Hub) Equipment Platform Installation 54 26-May-26 27-Jul-26 (Pipeline Hub) Equipment Platform Installation
Rotating Equipment
Pump
S95.23.CMR02.1152 [S93-G-0734 A/B/S] Sewage Lift Station 10 Pump 36 18-Nov-25 29-Dec-25 [S93-G-0734 A/B/S] Sewage Lift Station 10 Pump
Packaged Equipment
S95.23.CMR07.1175 [S93-U-0717] Sanitary Odour Control Unit 10 36 18-Nov-25 29-Dec-25 [S93-U-0717] Sanitary Odour Control Unit 10
Piping
Underground (U/G) Piping
S95.23.CPI01.1110 (Pipeline Hub) U/G Piping Field Installation (with Pressure Test) 258 31-Dec-24 27-Oct-25 (Pipeline Hub) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
S95.23.CPI02.1110 (Pipeline Hub) A/G Piping Shop Fabrication 204 03-Jun-25 26-Jan-26 (Pipeline Hub) A/G Piping Shop Fabrication
S95.23.CPI02.1120 (Pipeline Hub) A/G Piping Field Installation 156 30-Dec-25 29-Jun-26 (Pipeline Hub) A/G Piping Field Installation
S95.23.CPI02.1121 (Pipeline Hub) A/G Piping Support Installation 126 03-Mar-26 27-Jul-26 (Pipeline Hub) A/G Piping Support Installation
S95.23.CPI02.1130 (Pipeline Hub) A/G Piping Pressure Test 78 28-Apr-26 27-Jul-26 (Pipeline Hub) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
S95.23.CPA01.1110 (Pipeline Hub) Piping Painting 78 30-Jun-26 28-Sep-26 (Pipeline Hub) Piping Painting
Insulation
S95.23.CPA02.1110 (Pipeline Hub) Piping Insulation 78 30-Jun-26 28-Sep-26 (Pipeline Hub) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
S95.23.CEL01.1110 (Pipeline Hub) Electrical Cable Tray & Conduit 108 24-Feb-26 29-Jun-26 (Pipeline Hub) Electrical Cable Tray & Conduit
S95.23.CEL01.1120 (Pipeline Hub) Electrical Cable Pulling & Termination 120 28-Apr-26 14-Sep-26 (Pipeline Hub) Electrical Cable Pulling & Termination
S95.23.CEL01.5110 (Operator Shelter / OPS-05) Electrical Cable Tray & Conduit 120 02-Dec-25 20-Apr-26 (Operator Shelter / OPS-05) Electrical Cable Tray & Conduit
S95.23.CEL01.5120 (Operator Shelter / OPS-05) Electrical Cable Pulling & Termination 138 13-Jan-26 22-Jun-26 (Operator Shelter / OPS-05) Electrical Cable Pulling & Termination
Lighting System
S95.23.CEL05.1110 (Pipeline Hub) Lighting System Installation 84 26-May-26 31-Aug-26 (Pipeline Hub) Lighting System Installation
S95.23.CEL05.5110 (Operator Shelter / OPS-05) Lighting System - Installation 126 03-Mar-26 27-Jul-26 (Operator Shelter / OPS-05) Lighting System - Installation
S95.23.CEL05.5120 (Operator Shelter / OPS-05) Grounding - Installation 258 03-Jun-25 30-Mar-26 (Operator Shelter / OPS-05) Grounding - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
S95.23.CCI01.1110 (Pipeline Hub) I&C Cable Tray & Conduit 132 24-Feb-26 27-Jul-26 (Pipeline Hub) I&C Cable Tray & Conduit
S95.23.CCI01.1120 (Pipeline Hub) I&C Cable Pulling & Termination 156 28-Apr-26 26-Oct-26 (Pipeline Hub) I&C Cable Pulling & Termination
Field Instrument
S95.23.CCI02.1110 (Pipeline Hub) Field Instrument Installation (with Calibration) 78 28-Jul-26 26-Oct-26 (Pipeline Hub) Field Instrument Installation (with Calibration)
Loop Test
S95.23.CCI04.1110 (Pipeline Hub) Loop Test 108 28-Jul-26 30-Nov-26 (Pipeline Hub) Loop Test
Pre-commissioning
S95.23.CPC03.1110 (Pipeline Hub) Leak Test 42 29-May-27 15-Jul-27 (Pipeline Hub) Leak Test
S95.23.CPC03.1120 (Pipeline Hub) Mechanical Running Test 54 29-May-27 29-Jul-27 (Pipeline Hub) Mechanical Running Test
Flushing & Blowing
S95.23.CPC01.1110 (Pipeline Hub) Mechanical Cleaning 108 28-Jul-26 30-Nov-26 (Pipeline Hub) Mechanical Cleaning
Function Test
S95.23.CPC02.1110 (Pipeline Hub) Function Test 54 27-Oct-26 28-Dec-26 (Pipeline Hub) Function Test
Water Supply Facilities (Zuluf CPF)
Water Supply Facilities within Safaniyah GOSP-1
Civil
Foundation (Equipment & Piperack)
A85.01.CCV02.1120 (Water Supply Facilities - Zuluf CPF) Piperack Foundation 126 04-Feb-25 30-Jun-25 (Water Supply Facilities - Zuluf CPF) Piperack Foundation
Misc. Foundation & Paving
A85.01.CCV03.1110 (Water Supply Facilities - Zuluf CPF) Misc. Foundation & Concrete Paving 198 30-Dec-25 17-Aug-26 (Water Supply Facilities - Zuluf CPF) Misc. Foundation & Concrete Paving
A85.01.CCV03.1120 (Water Supply Facilities - Zuluf CPF) Asphalt Paving & Road 36 18-Aug-26 28-Sep-26 (Water Supply Facilities - Zuluf CPF) Asphalt Paving & Road
Steel Structure
Piperack
A85.01.CSS01.1110 (Water Supply Facilities - Zuluf CPF) Piperack Installation 102 01-Jul-25 27-Oct-25 (Water Supply Facilities - Zuluf CPF) Piperack Installation
A85.01.CSS01.1120 (Water Supply Facilities - Zuluf CPF) Misc. Steel Installation 54 28-Oct-25 29-Dec-25 (Water Supply Facilities - Zuluf CPF) Misc. Steel Installation
Platform & Ladder
A85.01.CSS02.1110 (Water Supply Facilities - Zuluf CPF) Equipment Platform Installation 78 30-Dec-25 30-Mar-26 (Water Supply Facilities - Zuluf CPF) Equipment Platform Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 62 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
Rotating Equipment
Pump
A85.01.CMR02.1129 [A85-G-0001 A/B/C] Produced Water Transfer Pump 54 10-Mar-26 11-May-26 [A85-G-0001 A/B/C] Produced Water Transfer Pump
Piping
Underground (U/G) Piping
A85.01.CPI01.1110 (Water Supply Facilities - Zuluf CPF) U/G Piping Field Installation (with Pressure Test) 234 31-Dec-24 29-Sep-25 (Water Supply Facilities - Zuluf CPF) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
A85.01.CPI02.1110 (Water Supply Facilities - Zuluf CPF) A/G Piping Shop Fabrication 216 20-May-25 26-Jan-26 (Water Supply Facilities - Zuluf CPF) A/G Piping Shop Fabrication
A85.01.CPI02.1120 (Water Supply Facilities - Zuluf CPF) A/G Piping Field Installation 228 04-Nov-25 27-Jul-26 (Water Supply Facilities - Zuluf CPF) A/G Piping Field Installation
A85.01.CPI02.1121 (Water Supply Facilities - Zuluf CPF) A/G Piping Support Installation 204 06-Jan-26 31-Aug-26 (Water Supply Facilities - Zuluf CPF) A/G Piping Support Installation
A85.01.CPI02.1130 (Water Supply Facilities - Zuluf CPF) A/G Piping Pressure Test 102 05-May-26 31-Aug-26 (Water Supply Facilities - Zuluf CPF) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
A85.01.CPA01.1110 (Water Supply Facilities - Zuluf CPF) Piping Painting 78 28-Jul-26 26-Oct-26 (Water Supply Facilities - Zuluf CPF) Piping Painting
Insulation
A85.01.CPA02.1110 (Water Supply Facilities - Zuluf CPF) Piping Insulation 78 28-Jul-26 26-Oct-26 (Water Supply Facilities - Zuluf CPF) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
A85.01.CEL01.1110 (Water Supply Facilities - Zuluf CPF) Electrical Cable Tray & Conduit 144 28-Oct-25 13-Apr-26 (Water Supply Facilities - Zuluf CPF) Electrical Cable Tray & Conduit
A85.01.CEL01.1120 (Water Supply Facilities - Zuluf CPF) Electrical Cable Pulling & Termination 156 30-Dec-25 29-Jun-26 (Water Supply Facilities - Zuluf CPF) Electrical Cable Pulling & Termination
Lighting System
A85.01.CEL05.1110 (Water Supply Facilities - Zuluf CPF) Lighting System - Installation 102 30-Dec-25 27-Apr-26 (Water Supply Facilities - Zuluf CPF) Lighting System - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
A85.01.CCI01.1110 (Water Supply Facilities - Zuluf CPF) I&C Cable Tray & Conduit 180 28-Oct-25 25-May-26 (Water Supply Facilities - Zuluf CPF) I&C Cable Tray & Conduit
A85.01.CCI01.1120 (Water Supply Facilities - Zuluf CPF) I&C Cable Pulling & Termination 210 30-Dec-25 31-Aug-26 (Water Supply Facilities - Zuluf CPF) I&C Cable Pulling & Termination
Field Instrument
A85.01.CCI02.1110 (Water Supply Facilities - Zuluf CPF) Field Instrument Installation (with Calibration) 156 31-Mar-26 28-Sep-26 (Water Supply Facilities - Zuluf CPF) Field Instrument Installation (with Calibration)
Loop Test
A85.01.CCI04.1110 (Water Supply Facilities - Zuluf CPF) Loop Test 132 26-May-26 26-Oct-26 (Water Supply Facilities - Zuluf CPF) Loop Test
Pre-commissioning
A85.01.CPC03.1110 (Water Supply Facilities - Zuluf CPF) Leak Test 24 01-Dec-26 28-Dec-26 (Water Supply Facilities - Zuluf CPF) Leak Test
A85.01.CPC03.1120 (Water Supply Facilities - Zuluf CPF) Mechanical Running Test 24 01-Dec-26 28-Dec-26 (Water Supply Facilities - Zuluf CPF) Mechanical Running Test
Flushing & Blowing
A85.01.CPC01.1110 (Water Supply Facilities - Zuluf CPF) Mechanical Cleaning 78 01-Sep-26 30-Nov-26 (Water Supply Facilities - Zuluf CPF) Mechanical Cleaning
Function Test
A85.01.CPC02.1110 (Water Supply Facilities - Zuluf CPF) Function Test 54 29-Sep-26 30-Nov-26 (Water Supply Facilities - Zuluf CPF) Function Test
Water Supply Facilities (Safaniyah GOSP-1)
Water Supply Facilities within Zuluf CPF
Civil
Foundation (Equipment & Piperack)
G26.01.CCV02.1120 (Water Supply Facilities - Safaniyah GOSP-1) Piperack Foundation 96 04-Feb-25 26-May-25 (Water Supply Facilities - Safaniyah GOSP-1) Piperack Foundation
Misc. Foundation & Paving
G26.01.CCV03.1110 (Water Supply Facilities - Safaniyah GOSP-1) Misc. Foundation & Concrete Paving 198 25-Nov-25 13-Jul-26 (Water Supply Facilities - Safaniyah GOSP-1) Misc. Foundation & Concrete Paving
G26.01.CCV03.1120 (Water Supply Facilities - Safaniyah GOSP-1) Asphalt Paving & Road 42 14-Jul-26 31-Aug-26 (Water Supply Facilities - Safaniyah GOSP-1) Asphalt Paving & Road
Steel Structure
Piperack
G26.01.CSS01.1110 (Water Supply Facilities - Safaniyah GOSP-1) Piperack Installation 108 27-May-25 29-Sep-25 (Water Supply Facilities - Safaniyah GOSP-1) Piperack Installation
G26.01.CSS01.1120 (Water Supply Facilities - Safaniyah GOSP-1) Misc. Steel Installation 48 30-Sep-25 24-Nov-25 (Water Supply Facilities - Safaniyah GOSP-1) Misc. Steel Installation
Platform & Ladder
G26.01.CSS02.1110 (Water Supply Facilities - Safaniyah GOSP-1) Equipment Platform Installation 78 25-Nov-25 23-Feb-26 (Water Supply Facilities - Safaniyah GOSP-1) Equipment Platform Installation
Rotating Equipment
Pump
G26.01.CMR02.1130 [G26-G-244 A/B] Formation Water Booster Pump 54 10-Mar-26 11-May-26 [G26-G-244 A/B] Formation Water Booster Pump
G26.01.CMR02.1131 [G26-G-212 A/B] Formaton Water Injection Pump 54 10-Mar-26 11-May-26 [G26-G-212 A/B] Formaton Water Injection Pump
Piping
Underground (U/G) Piping
G26.01.CPI01.1110 (Water Supply Facilities - Safaniyah GOSP-1) U/G Piping Field Installation (with Pressure Test) 210 31-Dec-24 01-Sep-25 (Water Supply Facilities - Safaniyah GOSP-1) U/G Piping Field Installation (with Pressure Test)
Above-ground (A/G) Piping
G26.01.CPI02.1110 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Shop Fabrication 192 20-May-25 29-Dec-25 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Shop Fabrication
G26.01.CPI02.1120 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Field Installation 234 30-Sep-25 29-Jun-26 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Field Installation
G26.01.CPI02.1121 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Support Installation 204 02-Dec-25 27-Jul-26 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Support Installation
(BI-10-08598) Safaniyah AH Development - CFP / PKG #2 Implementation Schedule (Level. 3) Page 63 of 63

Activity ID Activity Name Original Start 2023


Finish 2024 2025 2026 2027 2028
Duration Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
G26.01.CPI02.1130 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Pressure Test 102 31-Mar-26 27-Jul-26 (Water Supply Facilities - Safaniyah GOSP-1) A/G Piping Pressure Test
Painting & Insulation & Refractory
Painting
G26.01.CPA01.1110 (Water Supply Facilities - Safaniyah GOSP-1) Piping Painting 78 30-Jun-26 28-Sep-26 (Water Supply Facilities - Safaniyah GOSP-1) Piping Painting
Insulation
G26.01.CPA02.1110 (Water Supply Facilities - Safaniyah GOSP-1) Piping Insulation 78 30-Jun-26 28-Sep-26 (Water Supply Facilities - Safaniyah GOSP-1) Piping Insulation
Electrical
Cabling Work (Tray / Pulling & Termination)
G26.01.CEL01.1110 (Water Supply Facilities - Safaniyah GOSP-1) Electrical Cable Tray & Conduit 144 30-Sep-25 16-Mar-26 (Water Supply Facilities - Safaniyah GOSP-1) Electrical Cable Tray & Conduit
G26.01.CEL01.1120 (Water Supply Facilities - Safaniyah GOSP-1) Electrical Cable Pulling & Termination 150 02-Dec-25 25-May-26 (Water Supply Facilities - Safaniyah GOSP-1) Electrical Cable Pulling & Termination
Lighting System
G26.01.CEL05.1110 (Water Supply Facilities - Safaniyah GOSP-1) Lighting System - Installation 108 25-Nov-25 30-Mar-26 (Water Supply Facilities - Safaniyah GOSP-1) Lighting System - Installation
Control & Instrument
Cabling Work (Tray / Pulling & Termination)
G26.01.CCI01.1110 (Water Supply Facilities - Safaniyah GOSP-1) I&C Cable Tray & Conduit 180 30-Sep-25 27-Apr-26 (Water Supply Facilities - Safaniyah GOSP-1) I&C Cable Tray & Conduit
G26.01.CCI01.1120 (Water Supply Facilities - Safaniyah GOSP-1) I&C Cable Pulling & Termination 204 02-Dec-25 27-Jul-26 (Water Supply Facilities - Safaniyah GOSP-1) I&C Cable Pulling & Termination
Field Instrument
G26.01.CCI02.1110 (Water Supply Facilities - Safaniyah GOSP-1) Field Instrument Installation (with Calibration) 156 03-Mar-26 31-Aug-26 (Water Supply Facilities - Safaniyah GOSP-1) Field Instrument Installation (with Calibration)
Loop Test
G26.01.CCI04.1110 (Water Supply Facilities - Safaniyah GOSP-1) Loop Test 132 28-Apr-26 28-Sep-26 (Water Supply Facilities - Safaniyah GOSP-1) Loop Test
Pre-commissioning
G26.01.CPC03.1110 (Water Supply Facilities - Safaniyah GOSP-1) Leak Test 30 27-Oct-26 30-Nov-26 (Water Supply Facilities - Safaniyah GOSP-1) Leak Test
G26.01.CPC03.1120 (Water Supply Facilities - Safaniyah GOSP-1) Mechanical Running Test 42 27-Oct-26 14-Dec-26 (Water Supply Facilities - Safaniyah GOSP-1) Mechanical Running Test
Flushing & Blowing
G26.01.CPC01.1110 (Water Supply Facilities - Safaniyah GOSP-1) Mechanical Cleaning 78 28-Jul-26 26-Oct-26 (Water Supply Facilities - Safaniyah GOSP-1) Mechanical Cleaning
Function Test
G26.01.CPC02.1110 (Water Supply Facilities - Safaniyah GOSP-1) Function Test 48 01-Sep-26 26-Oct-26 (Water Supply Facilities - Safaniyah GOSP-1) Function Test