AMRUT VARIATION DETAILS
AMRUT VARIATION DETAILS
S.No Name of Scheme Scheme Code Project Cost (In CB Cost (in Lacs) CB Cost (in Lacs) Revised CB Cost Revised CB Cost Status of Variation
Lacs) witout GST with GST after Variation (in after Variation (in
Lacs) without GST Lacs) with GST
1 2 3 4 5 6 7 8 9
1 Gorakhpur Sewerage Scheme Variation Approved by
Zone A-1, Northern Part UTT-GOR-003 13627.81 9429.09 10560.58 8077.04 9085.62 Chief Engineer on DT
(Upper Part) 05.12.2023
2 Gorakhpur Sewerage Scheme
Zone A-1, Southern Part
(Lower Part)
Variation Approved by
Chief Engineer on DT
Gorakhpur Septage
27.10.2023 and Extra
3 Management Solution (Co- UTT-GOR-025 167.488 149.74 167.71 149.74 175.42
Amount of 17.80 Lacs is
Treatment)
approved in 19th SLTC
but 3rd GO is pending
4 Variation Approved by
Gorakhpur Sewerage Scheme
UTT-GOR-026 22385.75 12416.93 14589.41 12582.94 14785.95 Chief Engineer on DT
Zone C-2, Part-1
30.12.2023