Scope of Work

1. Introduction

This document provides a detailed scope of work for the construction of a two-story
residential building located in Quezon City, Philippines. The project aims to deliver a
modern and functional residential space that meets the client's specifications and
adheres to local building codes and regulations. The following sections outline the
specific tasks and activities to be carried out during the construction process.

Project Name: Two-Story Residential Building Construction

Location: Quezon City, Philippines

Client: [Client's Name]

Contractor: [Contractor's Name]

Project Duration: [Start Date] to [End Date]

2. Detailed Scope

1. Site Preparation

- Clearing and Grubbing

- Excavation and Backfilling

- Site Grading

2. Foundation Works

- Excavation for Foundation

- Concrete Footing Installation

- Reinforcement Works
3. Structural Works

- Column and Beam Construction

- Slab Construction

- Staircase Construction

4. Masonry Works

- Bricklaying

- Wall Plastering

5. Roofing Works

- Truss Fabrication and Erection

- Roof Sheeting Installation

6. Finishing Works

- Interior and Exterior Painting

- Tiling and Flooring

- Door and Window Installation

7. Plumbing and Electrical Works

- Plumbing Pipe Installation

- Electrical Wiring and Fixtures

8. Miscellaneous Works

- Landscaping

- Driveway and Pathway Construction


Measurement and Payment
Unit of Measurement: Metric system

Bill of Quantities (BOQ)


Item No. Description Unit Quantity Unit Price Total Cost
(PHP) (PHP)

1 Site sq.m 200 150 30,000


Preparation

2 Foundation cu.m 50 5,000 250,000


Works

3 Structural sq.m 400 2,000 800,000


Works

4 Masonry sq.m 300 1,000 300,000


Works

5 Roofing sq.m 200 1,500 300,000


Works

6 Finishing sq.m 400 800 320,000


Works

7 Plumbing and lot 1 150,000 150,000


Electrical
Works

8 Miscellaneous lot 1 50,000 50,000


Works

Payment Schedule
Mobilization Payment: 10% of the total contract amount upon signing the contract.

Progress Payments: Based on the actual work completed, to be certified by the project
engineer.

Final Payment: Upon project completion and final acceptance.


Labor Cost
Laborers: PHP 500 per day

Skilled Workers: PHP 800 per day

Foreman: PHP 1,200 per day