Professional Documents
Culture Documents
Manual PAQUES IC_1era parte (1)
Manual PAQUES IC_1era parte (1)
MINIMUM PACKAGE
No part of this document may be reproduced, stored in a retrieval system or transmitted, in any form
or by any means, electronic, mechanical, photocopying, recording or otherwise, for any purpose,
without the prior written permission of Paques bv.
Page II
Project- and document information
Project number: Number appears automaticaly if document is made project specific
Technology: BIOPAQ®IC
Customer:
Subtitle:
Authors: WOB
Page III
Table of contents
1 Introduction 1
1.1 Support 1
2 Safety instructions 2
2.1 Safety at work 2
2.2 Dosing 2
2.3 Sludge and process liquids 3
2.4 Hazardous gases and vapours 3
2.4.1 Biogas 3
2.4.2 Hydrogen 4
2.4.3 Ventilation and chemicals vapours 4
2.4.4 Hazardous area classification 4
2.5 Working at a height 6
2.6 Working in confined spaces 6
2.7 Malfunctions 7
2.8 Disasters 7
2.8.1 Shutting down the installation 7
3 Process description 8
®
3.1 BIOPAQ IC reactor 8
®
3.1.1 The process in the BIOPAQ IC reactor 9
3.2 Biogas treatment 11
3.2.1 Biogas flow metering 11
3.2.2 Condensate separation 11
3.2.3 Overpressure protection 12
3.2.4 Buffering 13
3.2.5 Gas flare 13
3.3 Ventilation 13
3.4 Influent 14
3.4.1 Nitrite & nitrate 14
3.4.2 Sulphite & sulphate 14
3.4.3 Fats, oils & greases (FOG) 14
3.5 Control parameters 15
3.5.1 Biomass (granular sludge) 15
3.5.2 Chemical Oxygen Demand (COD) 16
Page IV
3.5.3 COD load and volatile fatty acid concentration 16
3.5.4 Pre-acidification degree 17
3.5.5 Specific biogas production 17
3.5.6 pH 17
3.5.7 Alkalinity (pH buffering) 18
3.5.8 Temperature 18
3.5.9 Nutrients 18
3.5.10 Calcium (precipitation) 19
3.5.11 Hydrogen sulphide 20
3.5.12 Summary of control parameters 20
4 Start up procedure 21
4.1 Technical inspection 21
4.1.1 Leakage test 21
4.1.2 Hydraulic test (water run) 21
4.1.3 Checking of functional specification 21
4.2 Technological start up 22
4.2.1 Start up conditions 22
4.2.2 Inerting biogas system 22
4.2.3 Sludge inoculation 23
4.3 Start up 24
4.4 Normal operation 25
4.5 Restart 25
4.5.1 With external recirculation or shorter than 5 days 25
4.5.2 Without external recirculation or longer than 5 days 25
5 Operating instructions 27
5.1 General process control 27
5.2 Routine work 27
5.2.1 Daily 27
5.2.2 Weekly 28
5.2.3 Monthly 28
5.3 Cleaning instructions 28
5.4 Temporary shut down 28
5.5 Major maintenance 29
5.6 Emptying the installation 29
5.7 Dismantling and disposal of the installation 29
Page V
5.8 Protection against frost 29
5.9 Spare parts 29
Appendices 37
Page VI
1 Introduction
The BIOPAQ® Internal Circulation (IC) reactor is designed to convert dissolved and degradable organic
impurities from wastewater into biogas.
This operating manual describes the safety aspects, functioning and operation of the
BIOPAQ® IC reactor.
In section 2 the safety aspects regarding the BIOPAQ® IC reactor are described. Then, in section 3 the
process description of the installation is given. The start up procedure of the BIOPAQ® IC process is
described in section 4. Section 5 gives a summary with regard to recommended maintenance and
monitoring procedures. For process malfunction and troubleshooting please refer to section 6.
Note: All figures given are illustrative examples. These can differ with respect to actual delivery.
1.1 Support
For components not made by Paques, please refer to the relevant supplier’s manual.
Paques Services
services@paques.nl
Tel: +31 514 608 759 (direct)
Fax +31 514 603 342
2.2 Dosing
Advice and instructions on safe handling of chemicals can be found in the MSDS of the relevant
supplier(s). An MSDS can be obtained from the supplier and must be affixed by the dosing installation.
All process liquids in the reactors and tanks may contain chemicals and micro-organisms. For this
reason it is recommended that these process liquids be treated with extreme caution. Take the right
personal protection measures such as the use of waterproof shoes, gloves and safety goggles.
2.4.1 Biogas
Biogas has approximately the following composition:
Methane (CH4) 50 - 90 vol. %
Carbon dioxide (CO2) 10 - 45 vol. %
Hydrogen sulphide (H2S) 0.2 – 3.5 vol. %
Water (H2O) 0 - 5 vol. %
The exact biogas composition depends on the wastewater characteristics and the pre-treatment. Biogas is
potentially flammable, suffocating, toxic and/or explosive because it contains methane and hydrogen
sulphide.
Methane (CH4)
Lower explosion limit (LEL) 4.4 vol. % in air.
Upper explosion limit (UEL) 16.0 vol. % in air.
2.4.2 Hydrogen
Hydrogen may be produced during the acidification of wastewater. If the relevant tanks are
continuously ventilated the hydrogen concentration remains sufficiently low. However, if the ventilation
fails or is manually shut down, within a few hours the hydrogen concentration may rise to a critical
level.
The vapours of chemicals used may have the same harmful effect as the liquid or solid form. For this
consult the MSDS of the supplier.
This hazard zone is schematically drawn in Figure 2.1. Please check the applicable ‘Hazardous area
classification’ for reactor specific details.
Everyone, present in the hazard zone of the reactor, must work in accordance with the local applicable
safety provisions. The following general regulations must be taken into account as a minimum:
The entrance to the top of the reactor must be restricted.
Only instructed and authorize personal may enter the top of the reactor.
Workers must carry a mobile gas detector for H2S, LEL (Lower Explosion Limit) and OX (low
oxygen alarm) and an escape gasmask with a proper filter. Workers must know how to use
these personal safety guards.
Workers must withdraw immediately, with the use of an escape gasmask with a proper filter,
when the H2S alarm sounds.
The BIOPAQ®IC reactor is equipped with a high biogas pressure- and a low water level- alarm
[see figure 3.4 and 3.5]. Both alarms warn for the possibility of biogas escaping at the top of
the reactor. An alarm situation should be indicated by an optical and/or acoustic alarm and
workers should withdraw before the explosion conditions are reached.
For all other maintenance the reactor has to be taken out of operation, inertisized and emptied
according to operating procedures Shutting down the reactor, Shutting down and inerting the biogas
system and Emptying the reactor (Appendix B).
Before and during the inspection or work it must be established whether the empty tank is safe for the
operating personnel to do the work or inspection. To do this, the following measurements need to be
carried out:
1 LEL measurement: the concentration of explosive gases must be lower than 1 % LEL
(H2 < 0.04 vol. % and/or in combination CH4 < 0.04 vol. %).
2 OX measurement: the oxygen concentration must be between 20 and 21 vol. %.
These measurements can be carried out with a portable gas detector. If, despite all the precautionary
measures, the gas alarm does go off, everyone in the area should stop work immediately and leave.
Work in confined spaces should always be carried out by at least two people. One person keeps watch
outside the confined space and keeps in contact with the person in the confined space. This ‘tank
watcher’ raises the alarm if there is an accident. The tank watcher must, under all circumstances,
remain outside the confined space and should never enter it to help other employees.
2.7 Malfunctions
A malfunction results in an unusual situation. Take extra care during a malfunction, because this can
create hazardous situations. For example:
Accumulation of hazardous gasses, causing higher pressures.
Extreme pH value of a process liquid.
Release of biogas into unusual and unexpected places.
2.8 Disasters
During disasters always follow the locally applicable safety provisions. Shut the installation down and,
during an evacuation, leave the site calmly; do not run! Always walk at right angles to the wind
direction from the source.
The shut down of the installation is further described in the operating procedures Shutting down the
reactor and Shutting down and inerting the biogas system (Appendix B).
The internal circulation is based on the gas lift principle that is caused by the difference in gas hold-up
between the riser (4) and the downer (6). A high loading requires more mixing. The internal
recirculation flow rate depends on the quantity of biogas produced and hence depends on the
biodegradable COD load. This principle makes the system self-regulating.
The liquid recirculation flow rate is on typically 0.7 – 1.1 times the biogas flow rate.
The distribution system in the mixing section ensures that the reactor has a proportionate influent
distribution to the expanded sludge bed by using special nozzles and the sludge roof.
The biogas produced is collected under the gas hoods of the separation modules. It flows upwards
through the riser and drags along granular sludge and process water, due to the gaslift principle as
explained previously.
Polishing (7)
In the upper compartment effective polishing of the wastewater occurs due to the low sludge loading
rate, the relatively long hydraulic retention time and the gentle flow character. In this compartment the
turbulence and the upflow velocity are low due to small biogas production and the absence of the
internal circulation. These conditions also create extra space for sludge from the expanded sludge bed,
which prevents sludge loss during short peak loads.
Figure 3.3: Gas/liquid separator (5) [4a = riser lower separation module (granular sludge, water and
biogas), 4b = gas line upper separation module (biogas), 6 = downer (valve), A = spray
water line, B = inspection glass, C = nitrogen dosing point A, D = water separator and E =
biogas pipeline]
The gas/liquid separator is equipped as standard with a spray water connection (A), two inspection
glasses (B), a liquid level sensor (figure 3.4), a water separator (D) and two connections for nitrogen
gas dosing (figure 3.3: C and figure 3.5: B). These components are necessary to ensure internal
circulation during operation, to prevent fouling of the biogas pipeline (E) and to suppress foaming.
These aspects will be further explained in the following sections.
Figure 3.5: Downer valve (A) and connection for nitrogen gas dosing on the downer (B)
The overpressure protection can be effected both mechanically [figure 3.6, B] and by means of a water
seal [figure 3.7, B]. The mechanical overpressure protection device must be located at the highest
point in the gas line, as close as possible to the BIOPAQ ® IC reactor. This principle is shown
schematically in figure 3.6. Contact the owner of the installation when neither of these safety measures
is in place, because safe operation of the installation is impaired.
Figure 3.6: BIOPAQ® IC reactor with mechanical overpressure protection device [B, 45 cm water
column (mbar)], reactor effluent level alarm (L) and overpressure alarm (P), scrubber
(optional), gas buffer, gas flare and condensate separation via water seal [A, 60 cm
water column (mbar)].
An example of overpressure protection using a water seal is shown schematically in figure 3.7. The
blow off of the overpressure protection device must be located near the highest point in the gas line, as
close as possible to the BIOPAQ® IC reactor.
3.2.4 Buffering
The biogas produced leaves the BIOPAQ® IC reactor with an irregular, pulsating flow. Paques
recommends that these fluctuations are being buffered using a pressure-resistant buffer (operating
pressure of 31 cm water column) with variable volume.
3.3 Ventilation
According to Paques’ standards, the top of the reactor should always be actively ventilated with the
help of the ventilation system. This prevents odour emission and possible accumulation of biogas. The
ventilation flow is set during start up.
During shut down the reactor contents (process water and granular sludge) may NOT flow out of the
reactor via the influent pump and influent line. This would result in biomass loss. If the liquid level in
the reactor falls too low, biogas may escape from the reactor via the separation modules. Backflow of
the reactor contents must be prevented at all times by a well-functioning non-return (check) valve and an
actively controlled valve that closes when the pressure or level drops.
A good understanding of the influent is the basis for optimum process control, because it enables
identification of a process malfunctions at an early stage. To prevent a process malfunction the influent
may not contain any toxic or disrupting substances, such as poly-aluminium chloride and quaternary
ammonium compounds.
Sulphate (SO42-) is a relatively inert compound. Biomass requires small quantities as a nutrient (as a
source of sulphur). Sulphate reducing biomass can convert sulphate into hydrogen sulphide (H2S) under
the consumption of biodegradable COD. Sulphate has no COD but the COD contents of H2S is 2 g
COD/g H2S.
The sludge bed is present in the lower compartment of the BIOPAQ® IC reactor. Due to biomass growth
the quantity of granular sludge in the reactor increases in time. In addition to biomass growth, wash
out and natural death of bacteria also takes place, which results in the loss of a certain fraction of the
biomass. The net biomass increase depends on the ratio between growth and biomass loss.
The actual quantity of granular sludge and the ratio between biomass (VSS) and inorganic solids (ash
residue of TSS) is determined in the light of a sludge profile (Determination of sludge profile – Appendix
B). In general it can be stated that the BIOPAQ® IC reactor contains too much or too heavy granular
sludge if the 4th sampling point contains more than 50 ml/l sludge and/or the 1st sampling point more
than 250 g/l TSS and/or 50 – 60% ash residue of TSS.
Heavy sludge needs to be (partial) removed from the reactor on a regular basis, because excess
amounts can:
Oust the biomass (inert material replaces the biomass).
Damage the reactor internals.
Disturb or stop the internal circulation.
The (Heavy) sludge removal procedure is described in appendix B.
A surplus of granular sludge can easily be tapped off and stored (Storage of anaerobic granular sludge -
Appendix B). Even after a storage period of more than two years this sludge can be reactivated almost
as fast as fresh biomass. Consequently, the reactor can be quickly started up again after a process
malfunction by inoculation with the stored granular sludge. In addition stored granular sludge can also
be used to start up new reactors. You can contact Paques Services to organise this.
Wastewater usually contains a dissolved and solid COD fraction. This fraction distribution can be
obtained by means of filtration. The colloidal material is also found in the dissolved fraction. Both the
dissolved and the solid COD fraction contain an inert and a degradable part.
Note: The final fraction distribution depends on the analysis method used (for example centrifugation,
filtration, pore size of the filter, etc.).
For stable operation of the BIOPAQ® IC reactor it is important that the load is proportionate to the
activity of the granular sludge. The granular sludge and biodegradable COD load are well adjusted to
each other when the VFA concentration measured in the effluent is less than 5 meq/l. In addition to
remaining VFA, the residual COD concentration in the effluent depends on the inert COD fraction [see
Figure 3.9] and the quantity of sulphide produced. This varies per type of wastewater.
The VFA concentration of the water phase is determined by means of titration; this method is described
in operating procedure Determination of alkalinity and volatile fatty acid (VFA) concentration (Appendix
B).
The pre-acidification degree is determined using the calculation method in the operating procedure
Calculations (Appendix B).
The specific biogas production is determined using the calculation method in the operating procedure
Calculations (Appendix B).
3.5.6 pH
Optimum
The optimum pH in the sludge bed is between 6.5 and 7.5. For stable operation of the BIOPAQ ® IC
reactor the pH must be kept within this range.
Checking
The pH in the sludge bed of the BIOPAQ® IC reactor can be measured with an on-line pH meter. If the
reactor is not designed with an on-line measurement, Paques recommends that the pH be regularly
checked manually. Use the second sampling valve for this (Technical Data Sheets - Appendix A).
Note:
In the case of manual pH checking the pH measured is usually higher than the actual
pH in the sludge bed. This is caused by the escape of CO 2. The reliability of the
manual pH measurement can be increased as far as possible by preventing contact
with outside air and the pH in the liquid measured during sampling.
Acidification
VFA and sulphides (H2S) occur both dissociated (charged, like HS-) and undissociated (uncharged, like
H2S). The ratio between the dissociated and undissociated fraction depends on the pH. If the pH of the
process water is reduced the undissociated fraction increases. This undissociated fraction is the
problematic form, because it can penetrate through the cell membrane, which poisons the cell. A
decrease in the reactor pH below 6.5 must therefore be prevented at all times.
3.5.8 Temperature
Optimum
The temperature has a strong effect on the growth rate and the activity of the bacteria in the granular
sludge, in particular on the biogas producing bacteria. These bacteria have a temperature optimum
between 30 and 38C. Above 40°C their activity decreases considerably. It is therefore necessary to
keep the reactor temperature below 38C.
Considerable temperature fluctuations within a short time must be avoided because they almost always
cause a reduction in the biodegradable COD removal efficiency.
3.5.9 Nutrients
Biomass needs macro- and micro-nutrients for growth. Normally the wastewater contains sufficient
nutrients and extra dosing is not necessary. In some industries, such as for example in the pulp &
paper industry, the wastewater contains insufficient nutrients. In these industries extra nutrient dosing
is necessary because a long-term nutrient deficit has a negative effect on the sludge quality and
ultimately the removal efficiency.
As for all mirco-nutrients, Paques B.V. supplies the BIOPAQ® Micromix. This is a balanced solution of
trace metals, specifically developed for the BIOPAQ® IC process.
After start up, control can best be carried out on the ammonium and phosphate concentration in the
effluent of the BIOPAQ® IC reactor, taking into account any variations in the biodegradable COD load. The
following guidelines apply for this: NH4+-N > 5 mg N/l and PO43--P > 1 mg P/l.
Calcium improves the granule forming properties of the sludge. In wastewater with high calcium
concentrations there is a high risk of calcium carbonate precipitation formation, because calcium
carbonate is poorly soluble. To keep the dissolved calcium concentration high, the pH must be kept low.
In wastewater with low calcium concentrations Paques recommends dosing a soluble calcium salt until the
dissolved calcium concentration in the wastewater is 70 mg Ca2+/l.
There is usually sufficient magnesium present. In wastewater with a high sodium concentration (> 5000
mg Na+/l) Paques recommends that the dissolved magnesium concentration be increased to 10 – 20 mg
Mg2+/l, by dosing a soluble magnesium salt.
Extra potassium dosing also depends on the sodium concentration (> 5000 mg Na+/l). Sodium and
potassium are optimal balanced when the Na : K ratio is around 20 : 1.
Biogas consists mainly of methane (CH4) and carbon dioxide (CO2). Depending on the pH, part of the
carbon dioxide produced as bicarbonate (HCO3-) and/or carbonate (CO32-) is left in the water phase,
In addition to the pH the COD/Sulphate (SO42-) ratio in the influent is also an indication that there is a
chance of toxic effects due to sulphide. With a COD/SO42- ratio of 10:1 the effects are negligibly small.
Once the granular sludge is accustomed to sulphide the reactor can be operated without problems at a
ratio rising to 5:1.
All the equipment must be started up in accordance with the suppliers’ specifications.
The leakage test is preferably carried out with clean (industrial or river) water (for the reactor) and
compressed air (for the gas system). If this is not present, the leakage test may if necessary be carried
out with process water. Pay attention here to the quality of the process water used. Think particularly
about the biodegradable COD concentration, TSS concentration, pH and temperature.
Always carry out the hydraulic test with water with a low COD concentration!
Set the height of the level measurement in the gas/liquid separator in accordance with operating
procedure Setting level measurement of gas/liquid separator (Appendix B).
Process conditions
The water already present in the BIOPAQ® IC reactor must meet the conditions given in table 4.1.
Table 4.1: Process conditions during start up
Alkalinity (meq/l) 15 - -
Temperature (°C) 25 30 – 38 40
Influent
The influent of the BIOPAQ® IC reactor must comply with the output data described in the contract.
Set the influent distribution system as described in Setting of influent distribution system (appendix B).
Inert the biogas system with nitrogen gas in accordance with operating procedure Inerting biogas
system in appendix B.
The gas system of the BIOPAQ®IC reactor must be tested and guaranteed gas-tight
before the reactor may be inoculated with anaerobic granular sludge.
In the ideal case the reactor is inoculated with anaerobic granular sludge, with a volume of 50 - 65% of
the reactor contents, up to a maximum of 1 metre below the underside of the lower separation module.
The ideal sludge volume for start up depends on the reactor type and the anticipated biodegradable
COD load. It takes more time to bring the reactor to the design COD conversion capacity if the reactor
is started up with less sludge than recommended.
It is recommended to analyse the anaerobic granular sludge (or have it analysed) beforehand for the dry
matter content (TSS), the organic matter content (VSS) and the biological activity. With these data the
total biodegradable COD conversion capacity of the sludge inoculation can be calculated. This conversion
capacity determines the biodegradable COD load during start up. An example calculation is given in table
4.2.
Table 4.2: Example calculation of total conversion capacity of sludge inoculation. For the total
conversion capacity the conversion capacities of one or more sludge types are added
together. In this example a sludge mixture is assumed that comes from supplier A and
supplier B.
Volume of sludge
Sludge inoculation A 300 m3
inoculation
VSS concentration 63 kg * m-3
kg COD * kg VSS-1 * day-
Sludge activity 0.6 1
Volume of sludge
Sludge inoculation B 100 m3
inoculation
VSS concentration 59 kg * m-3
kg COD * kg VSS-1 * day-
Sludge activity 0.6 1
During the initial start up the optimum reactor temperature is usually not yet reached and the biomass
still has to get accustomed to the new process conditions. This temporarily results in a lower sludge
activity. To prevent overload the reactor is loaded during the initial start up with a convertible COD load
Based on an anticipated efficiency of for example 75% the reactor can be loaded during the initial start
up with a total COD load of:
During the first two weeks of the biological start up 10% sludge loss is normal. This is the result of
natural selection and adaptation of the biomass to the new situation. Small granules of biomass can
usually be found in the effluent from the reactor. The effluent is then usually coloured black.
Fill the reactor with anaerobic granular sludge in accordance with operating procedure Filling the
reactor with granular sludge in appendix B.
4.3 Start up
The BIOPAQ® IC reactor is started up, charged with influent, as soon as the biogas system has been
inerted with nitrogen gas, the reactor filled with anaerobic granular sludge and the start up conditions
have been met.
Procedure
1. Determine the total conversion capacity of the sludge inoculation (see example calculation table
4.2).
2. Start up the BIOPAQ® IC reactor with a biodegradable COD load that is equal to 50% of the
total conversion capacity of the sludge inoculation.
3. Monitor the reactor as described in the Analysis schedule (appendix B).
4. Check the internal circulation (via the inspection glasses of the gas/water separator).
5. Increase the load in stages, depending on the analysis results.
The COD efficiency during the start up is normally 10 to 20% lower than the design efficiency. This is
caused by:
1. A reduced sludge activity, which gives a higher effluent VFA concentration.
2. Wash out of sludge (both sludge and VFA are measured as COD).
3. Too little (adapted) sludge in the reactor.
4.5 Restart
This paragraph describes how the BIOPAQ® IC reactor is restarted after this has been temporarily shut
down. The method depends on the configuration (with or without external recirculation) and the
duration of the shut down (longer or shorter than 5 days).
Unblock the mixing section by dosing the influent via a quarter of all influent nozzles and alternating
the open and closed nozzles every 5 minutes.
Unblock the downer in accordance with operating procedure Unblocking downer (Appendix B).
Refluidise the sludge bed in the lower reactor compartment in accordance with operating
procedure Refluidisation of sludge bed (Appendix B).
5.2.1 Daily
Process
Check whether any alarm situations exist and if so, rectify them.
Check the trending of the on-line measurements of the last 24 hours and check the
Troubleshooting procedures (Appendix C) in case of abnormal process values.
Carry out the analysis programme (Analysis schedule - Appendix B) and check that the values
found fall within the specified values ((Project-specific) control parameters - Appendix A).
Assess the quality of the influent and effluent; report and note deviations.
Check that the setting of the influent distribution system is in proportion to the current flow
rate and if necessary rotate between the number of opened and closed valves (see Setting
influent distribution system – Appendix B).
Mechanical
Check the operation of all pumps. Note leakage, flow rate and noise. Rectify the malfunction in
accordance with the supplier’s instructions.
Check the installation for leaks and blockages.
Check the levels of the chemical storage tanks and fill up if necessary.
5.2.2 Weekly
Clean and check metering equipment in accordance with the supplier’s instructions.
Check the usability of safety materials.
5.2.3 Monthly
Carry out the analysis programme (Analysis schedule - Appendix B) and check that the values
found fall within the specified values ((Project-specific) control parameters - Appendix A).
Check if the covers show signs of wear (top coating fades away, fibres become visible/tangible
and dirt is absorbed). Coat the covers with a polyurethane (PUR) coating if these signs are
present.
Check if the rubber cover seals are damaged. Replace worn seals.
Maintenance of equipment in accordance with the supplier manuals.
There is a HIGH chance of unwanted biogas release, if the seals of the covers
are being replaced. Consult § 2.4.4 Hazardous area classification before
starting this replacement.
The procedure is described in operating procedure Shutting down BIOPAQ® IC reactor in appendix B.
The restart procedure is described in paragraph 4.5.
Biogas production
After the influent has been stopped, the biogas production from readily degradable COD gradually falls
and will finally stop completely. Due to the reduction in the biogas production the mixing of the sludge
In the BIOPAQ® IC reactor are three manholes that each give access to a section of the reactor. The
first manhole is located in the lower section, the second manhole is below the lower separation module
and the third manhole is approximately two metres below the top of the reactor.
The emptying of the BIOPAQ® IC reactor is described in the operating procedure Emptying of the
reactor in appendix B.
Under normal process conditions biogas is formed by the biogas producing bacteria in the granular
sludge from VFA. The optimum pH for this is between 6.5 and 7.5. If the normal process is disrupted,
for example by one of the above causes, the pH in the sludge bed falls below 6.5 and the biogas
production is inhibited and/or the biogas producing bacteria may die.
The acidifying bacteria are less sensitive to low pH values. They remain active down to a pH of 4. So for
pH values of 4.0 and 6.5 the creation of VFA continues, while the breakdown ceases. As a result of this
the VFA will accumulate easily in the reactor liquid.
During acidification there is a chance that the BIOPAQ® IC reactor gets into a vicious cycle (figure 6.1).
Poisoning of methane
producing bacteria
VFA concentration increases
increases
Fraction of undissociated
VFA increases
pH falls
As long as the pH of the sludge bed is above 7.0 (preferably around 7.5), a VFA concentration of 10 to
15 meq/l has a slightly negative effect on the biogas producing bacteria.
In case of a blocked downer the liquid level in the gas/water separator increases up to the riser. The
water pushed upwards leaves the separator via this riser instead of via the downer. If this situation
occurs for a few minutes the level measurement in the gas/water separator gives a high level alarm,
after which the influent pump stops. Visual inspection of the internal recirculation via the inspection
glasses of gas/water separator remains necessary.
Biogas outlet Setting level measurement
Gland nut
Nitrogen
dosing point A
Spray water
Downer valve
Figure 6.2: Normal and high water level indication gas/water separator
The downer is unblocked by filling it a couple of times with nitrogen gas and blowing it off with great
force. This method is described in the operating procedure Unblocking downer in appendix B.
Formation of precipitation
Due to salt precipitation (for example calcium carbonate, CaCO3) sludge granules may become
heavy. In the case of precipitation formation, it is recommended that the sludge is regularly
discharged from the lower section of the reactor (using the ‘Sludge output connection’, see
operating procedure Emptying the reactor – Appendix B) to guarantee good mixing in the
reactor. Formation of precipitation on/in the sludge granules is determined by means of
operating procedure Determination of sludge profile (Appendix B).
6.1.3 Inhibitors
If, at a constant load, a slow but sure increase of effluent VFAs is observed, there may be an inhibitor
in the influent. This inhibitor affects the activity of the sludge with the result of a slowly deteriorating
situation. An inhibitor may also be present for a very short period, for example due to an unforeseen
discharge.
6.2 Troubleshooting
6.2.1 Process Troubleshooting
The troubleshooting instructions have been prepared in accordance with current knowledge. New
insights can result in changes to these procedures.
Process malfunctions that may affect the process parameters, mentioned in section 3, can result in a
reduction in activity of the biomass. In extreme situations the biomass can even be killed.
The reason for the reduction in the biological activity must be identified and resolved. The information
that is given in section 3, 4 and 5 is important for this.
The troubleshooting procedures in appendix C describe different events and measures that can be
taken. It is obvious that these procedures cannot be complete. Only the most probably events are
shown. You can contact Paques Services for advice when you encounter an event not mentioned.
ANAEROBIC
There is no dissolved oxygen present in the water phase.
BOD/COD ratio
This ratio is a measure of the biological degradability of a wastewater; readily degradable
wastewater has a BOD/COD ratio of between 0.5 and 0.9.
COD Balance
The anaerobic system must be in balance, i.e. as much COD must enter the reactor (influent) as
leaves it (effluent, biogas and sludge).
MSDS
Material Safety Data Sheet
RECIRCULATION - [m3/hour]
The quantity of effluent that is recirculated to the reactor.
SLUDGE LOADING RATE (SLR, Sludge Loading Rate) - [kg COD * (kg VSS)-1 * day-1]
The quantity of COD per quantity of biomass (VSS) that enters the reactor per day.
An indication that the anaerobic polishing is not functioning well is when butyric acid
contributes significantly to the total VFA (i.e. >5%). Butyric acid can be noticed by its
characteristic odour (sweaty feet).
Appendix A: Specifications
Appendix C: Troubleshooting