Professional Documents
Culture Documents
Risk Assessment No1 - Mob-demob_Ver2
Risk Assessment No1 - Mob-demob_Ver2
Risk Assessment
Mobilisation At Lobito
Work Site Location / Operation / Project Reference Procedures
Acergy Eagle GI-25 Flexible Jumper Replacement
Approvals
Stage 1 : Denis MOREAU Stage 2 :
Meeting Attendees
Date Name Job Company Name Job Company
06 Oct 2010
Num Task Hazard Consequences Risk Level Corrective measures Residual risk
General Mobilisation 1) Injury to personnel E3 = H 1) D2 = M
1 Activities: Cargo Communications or Damage to vessel Define single point of
Transfer - Gerenal co-ordination failure. Damage to equipment command before each lift
Welding Activities - 2) Damage to environment Communication protocol
Lashing Activities Poor access/lighting between deck / quayside
(quayside) English to be the language
3) used
Trips and falls Perform pre-mobilisation
4) meeting with all parties
Lifting ops – swinging involved
load, inadequate rigging, 2)
dropped objects. Ensure proper lighting on
5) quayside during night shift
Falling from quayside. High visibility work vests.
6) Use of gangway /
Hotwork on deck. Awareness
7) Apply ISPS code (acess to
Working at height vessel)
8) 3)
Lack of familiarisation for Regular Safety walks /
new personnel Housekeeping
9) Proper lighting (night time)
Parallel activities on board Remove/ mark potential
the Eagle tripping hazards
10) 4)
Manual handling/pinch Certified equipment
point Colour coded
11) Rigging inspection prior
Inadequate PPE (3rd party use
personnel) Follow GR-OPS-008
12) Use of tag lines (as
Congested deck required)
3rd Party rigging to be
inspected to make sure it
is 'fit for purpose'.
Visual inspection prior to
each lift by vessel
personnel.
5)
Restricted area /
awareness
Security / Access
procedure to be confirmed
Work vest when working
2m of edges (quay)
Life saving equipment
available
6)
Hot Work permit, fire
watch and use of fire
blanket (when required).
Keep clear of mooring
ropes or protect them
Good housekeeping
Refer to vessel generic
HIRA + PTW
7)
Follow Group procedure
HSE-015 / W@H rescue
kit available
Container pre-rigged adn
rigging accessible from
deck.
8)
Vessel induction for all
new comers (including 3rd
party personnel)
ISPS - notification of
visitors 24hrs in advance
9)
Permit To Work as
appropriate
Awareness
Single point of contact
10)
Follow good manual
handling practice,
personnel awareness
11)
Ensure 3rd party
personnel boarding have
appropriate protective
equipment
12)
Deck layout to include
enough clearance between
equipment and escape
route
Num Task Hazard Consequences Risk Level Corrective measures Residual risk
Reel Lift 1) Heavy lift / Swinging Injury to personnel. E2 = M 1) Heavy lift permit (incl. E1 = M
2 Loads / Unbalanced lift / Damage to ballasting checks, no
vessel stability due to quayside/vessel. personnel on gangway)
offset heavy lift / water Damage to equipment. Follow stability analysis
depth Damage to third report conclusions for reel
2) Rigging failure party/client asset lifting sequence
3) Unsecured craddles / Tag / tugger lines (where
loose packing / dropped required)
object / loose product Restricted access to work
4) Uncoordinated activities area
between vessel / crane / Checked performed with
quayside regards to maximum tilt of
5) Potential interference the reel.
between reel and RDS Check port activity before
during lift starting the lift.
6) Working at height 2) Certified rigging / rigging
(lashing inspection after set-up and
removal/installation) prior to starting lift
7) Leak of inert gas 3)
underpressure (Jumper Check of cradles
filled with Nitrogen) seafastening to the reel
8) Unsufficient fendering Pre-lift checks (reel
inspection for loose item /
lift beam / end termination
location) prior EACH lift
Check product packing
prior to lift
Stay clear of lift areas
4)
Good communications /
define communication
protocol and
responsibilities
Single Point of Command
5)
If required, move RDS
towers.