Professional Documents
Culture Documents
Book1(AutoRecovered)(AutoRecovered)(AutoRecovered)
Book1(AutoRecovered)(AutoRecovered)(AutoRecovered)
Book1(AutoRecovered)(AutoRecovered)(AutoRecovered)
நீளம் அகலம்
உயர
ம் m total Measurement 3.398
Mix Design
volune 1.25 net volume
Cemant
1 Bags
1
Sand 1
1 Unit
Aggegate 3 Unit
3
Foundation Work
Home Measurement
Eaethwork Excavation in Foundation ft m m3
Footing number of
Length Width Height total of Total volume
Dimension footing Volume footing
1 4 4 5
F1 2.27 27.18 m3
1.219 1.2192 1.524 12
1 4 5 6
F2
1.219 1.524 1.8288
3.40 12
40.78 m3
total quantity
24 67.96 m3
2 Super structure
Labour cost
Hard soil
Soft soil man bower 900 Labour cost
JCB
0
6000 0 0
#DIV/0!
Amount per m^
#DIV/0!
Go
total
500
4
4.00
RCC Conerete Measuremant
Sum of
Mix Ratio cemant sand aggegate
Mix
Day volume
M20 1 1.5 3 5.5 Concrete Dry volume 1.54
Brick m m m
Voiume of 1 Brick With Mortar
size 1 1 1 Volume of Brick Wall
Foundation Footing
Measurement
நீளம்அகலம் உயரம் m
mm mm mm m^3
1600 1800 200
0.576
1.6 1.8 0.2
A1 A2 H m^3
300 600 150 0.5184
0.3 0.6 0.15 0.72
0.18 2.88 0.05 0.189
Cemant 1 Bags 1
mm m ft in
1000 0.381
work Calcuation
ut Data Cement
Sand
305 230 25 6 0 2 0 3 2
(2*B14)+(2*C14)-(8*D14)+(G14*10*E14)-(I14*2*E14)-(J14*3*E14)-(8*F14)
Measurement
நீளம்அகலம்உயரம் m
Cutting Laangth Numbars of Bar
Y axis X axis Y axis
5.6 10 12
Length of
Bar
mm mm 1 9 in
footing
918 in 0.0393700787 0.354331 36.14173
Footing Conerete Measuremant
Mix Ratiocemant sand aggegateSum of Mix Day volume
M5 1 5 10 16 Concrete Dry volume 1.54
M7.5 1 4 8 13 Plaster Dry voiume 1.33
Measurement
mm m^2 sq mm
cm cu cm sq cm
m m^2 m^3
km cu km sq km
in cu in sq in
ft ft^2 sq ft
yd cu yd sq yd
mi cu mi sq mi
Nm cu Nm sq Nm
mil cu mil sq mil
Construction Material price list
No's Material Barnd Kg Price
Steel Brand
1 TATA