Professional Documents
Culture Documents
SF832 D 0000-00-080 BLD 001 F&G Cable Block Diagrams
SF832 D 0000-00-080 BLD 001 F&G Cable Block Diagrams
SF832-D-0000-00-080-BLD-001
REVISION HISTORY
CONTENTS
1 GENERAL ............................................................................................................................................. 4
2 DEFINITIONS ....................................................................................................................................... 4
3 REFERENCE DRAWINGS AND DOCUMENTS............................................................................. 4
4 FIRE DETECTOR WIRING ................................................................................................................ 5
5 MANUAL CALL POINT WIRING........................................................................................................ 8
6 SOUNDER-BEACON WIRING .......................................................................................................... 8
7 FIELD DEVICE TERMINATION TO FIRE CONTROL PANEL ..................................................... 9
7.1 TERMINATING THE DETECTION AND ALARM (SOUNDER) CIRCUITS ................................. 9
7.2 CONNECTING THE MAINS POWER .............................................................................................. 10
7.3 CONNECTING THE BATTERIES ..................................................................................................... 10
8 PANEL TERMINATION CONNECTIONS ...................................................................................... 11
1 GENERAL
The scope of work to be performed by the Contractor “ ALTHAAER ALARABI CO.” is for Power Transmission
Line to Siba Remote Areas, which mainly includes but not limits to the following works:
To supply power to various remote sites in Siba gas field, KEIL intends to construct the permanent power
transmission network to reduce the operation and maintenance expenditures. In the field there are multiple
locations that fed power through temporary and solar power sources to the various remote facilities. This
project is intended to supply permanent MV/ LV power supply to the below locations from single power
source and the existing power sources shall be used as backup.
• Siba1
• Siba4
• Hub 1
• BOC Camp
• Raw Water Intake Station (RWI)
• BOC Main Check Point
2 DEFINITIONS
COMPANY: Kuwait Energy Iraq Limited Company (KEIL)
CONTRACTOR : Al-Thaer Al-Arabi Company
SUB-CONTRACTOR: Tareq Al-Qudra Company.
Project: EPC Power Transmission Line to Siba Remote Areas.
Work: All items and services to be provided as described within this technical document.
May: Indicates freedom of choice to comply with requirements
Shall: Indicates a mandatory requirement
Should: Indicates that the requirement is strongly recommended, and should be adhered to as best as
possible.
Figure 3—Wiring Connections - 2 Wire with Open and Short Circuit Monitoring
Figure 4—Typical Wiring - 2 Wire with Open and Short Circuit Monitoring
6 SOUNDER-BEACON WIRING