Professional Documents
Culture Documents
KP_Water Jet Pump_SOP_June-2022
KP_Water Jet Pump_SOP_June-2022
KP_Water Jet Pump_SOP_June-2022
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 1 of 7
WORK INSTRUCTIONS
FOR
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 2 of 7
Amendment Record
Rev Page
No. No.
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 3 of 7
1.0 Purpose:
This Procedure is intended to provide guidance and instructions for carrying out the water jet
pump start-up operation and STOP sequences.
2.0 Responsibility:
1. All the personnel involved in carrying out /supervising the above activities are required to
ensure implementation of this procedure.
2. In the event of any changes required in the procedure such changes may be requested
with Site in charge, who would take appropriate action with approval from respective
departmental heads.
4.0 CHECKLIST:
1. Check pump suction isolation valve and keep it in full open condition.
2. Check pump discharge line isolation valve and keep it in full close condition.
3. Check pump discharge header isolation valve (which ejector need to be taken in line) and
keep it in full open condition.
4. Check pump bearing house oil level, if it low top up with appropriate oil up to normal
level.
5. Check both ejectors airline (from condenser) isolation valves and keep close condition.
6. Check Jet pump tank drain line isolation valve and keep it full close condition.
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 4 of 7
7. Check Jet pump tank level and maintain 750 MM, if low open the initial filling line
isolation valve and increase tank level up to 750 MM.
8. Check coupling guard provided or not, it should be must provide.
9. Ensure all instruments are lined up (i.e., pump discharge pressure gauge and header
pressure gauges root are valve are open).
10. Ensure work permit closed or not, it should be must close before start the pump.
11. Take clearance from all (mechanical, instrument & electrical) departments.
12. Check the breaker is in service and remote/local switch in remote position.
13. After pre check is complete start the Motor.
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 5 of 7
Parameter Value
Jet pump discharge pressure. 0.47 MPa
Jet pump motor current 59 Amps
Water storage tank level 750 MM
Header pressure 0.46 MPa
Jet pump motor winding Temperature < 85 ºC
Jet pump motor bearing Temperature < 85 ºC
Jet pump bearing vibration. < 8 mm/sec
Jet pump Motor bearing vibration < 8 mm/sec
Jet pump bearing Temperature < 85 ºC
Jet pump speed 2900 rpm
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 6 of 7
8.0 Isolation procedures for water jet pump for long Shutdown:
1. Make electrical isolation for Jet pump motor & disable it from DCS, put switch in local
& switch off DC power supply & rack out the breaker.
2. Close the suction line isolation valve.
3. Close the discharge line isolation valve.
4. Close discharge header appropriate isolation valve.
5. Open the pump casing drain dummy plug and drain the water.
6. Issue PTW for isolation and normalization.
9.0 When one Jet is running then isolation procedure for 2nd Jet pump:
Electrical-
1. Electrical- stopped & disable from DCS
2. Selector switch OFF
3. Feeder rack-out
4. DC supply OFF
5. Tagged with PTW NO.
Operation-
1. Close the suction line isolation valve.
2. Close the discharge line isolation valve.
3. Close discharge header appropriate isolation valve.
4. Open the pump casing drain dummy plug and drain the water.
5. Issue PTW for isolation and normalization.
2 X 15 MW Power Plant
KP / SOP / WJP
SOP for WATER JET PUMP
Issue Date: Revision Date:
Issue No: 01 05/01/2018 Revision: 02 10/06/2022 File no: 01 Page 7 of 7
5. Check pump bearing house oil level, if it low top up with appropriate oil up to normal
level.
6. Check coupling guard provided or not, it should be must provide.
7. Ensure all instruments are lined up (i.e., pump discharge pressure gauge and header
pressure gauges root are valve are open).
8. Ensure work permit closed or not, it should be must close before start the pump.
9. Take clearance from all (mechanical, instrument & electrical) departments.
10. Check the breaker is in service and remote/local switch in remote position.
11. After pre check is complete start the stand-by jet pump from DCS/Local.
12. Open discharge valve gradually up to full and check pump discharge pressure.
13. Observe vibration and Bearing Temp. It must be normal.
14. Close the discharge valve of previously running pump and STOP.
15. Keep the pump on standby or isolate for maintenance.
Effect:
1. Condenser vacuum will fall.
2. Turbine exhaust temperature will rise.
3. Condenser pressure will go positive side and chances to fail rupture disk.
4. Unit has to be tripped unless the jet pump can be restored immediately
5. If one jet pump has tripped see that the stand by jet pump has started on auto or not,
if not start it manual immediately.
6. Reduce the unit load if stand by jet pump is not available to control the vacuum and
rectify the problem in the jet pump which has tripped.
**********