Three Mill
DETAILED ESTIMATES
a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Marine Plywood 2.00 pcs 600.00 1,200.00
Coco lumber 75.00 bd.ft. 45.00 3,375.00
Tarpaulin 64.00 sq.ft. 35.00 2,240.00
Common Wire Nails 5.00 kgs 120.00 600.00
Sub - Total 7,415.00
b. Labor
Description Qty No. of Day Rate/Day Total
Mason/Carpentry 1.0 1.0 600.00 600.00
Laborer/Helper 1.0 1.0 450.00 450.00
Sub - Total 1,050.00
a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Safety Shoes(Different Sizes) 15.00 pairs 700.00 10,500.00
Safety Helmet (free size) 15.00 pcs. 700.00 10,500.00
Safety Gloves (free size) 15.00 pairs 700.00 10,500.00
Sub - Total 31,500.00
b. Labor
Description Qty No. of Day Rate/Day Total
Safety Officer 1.0 60.0 450.00 27,000.00
Sub - Total 27,000.00
Removal of
Structures and
801(1) Obstruction Qty.= 1.00 l.s.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Removal of
Structures and
Obstruction 1.00 l.s. 150,950.00 150,950.00
Sub - Total 150,950.00
Embankment from
Roadway/Structure
804(1)a Excavation Qty.= 32.54 cu.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Embankment from
Roadway/Structure
Excavation 32.5 cu.m. 180.00 5,857.20
Sub - Total 5,857.20
Embankment from
Borrow (Common
Soil) 67.8 cu.m. 800.00 54,200.00
Sub - Total 54,200.00
Structural Concrete
(3000 psi, Class A, 28
900(1)c Days) Qty.= 98.17 Cu.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Structural Concrete
(3000 psi, Class A, 28
Days) 98.2 Cu.m. 7,200.00 706,824.00
Sub - Total 706,824.00
Reinforcing Steel
(Deformed, Grade
902(1)a 40) Qty.= 5,476.64 Kg.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Reinforcing Steel
(Deformed, Grade
40) 5476.6 Kg. 60.00 328,598.40
Sub - Total 328,598.40
Formworks and
903(2) Falseworks Qty.= 301.06 sq.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Formworks and
Falseworks 301.1 sq.m. 600.00 180,636.00
Sub - Total 180,636.00
Painting Works
1032(1)a (Masonry/Concrete) Qty.= 318.50 sq.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Painting Works
(Masonry/Concrete) 318.5 sq.m. 260.00 82,810.00
Sub - Total 82,810.00
Pre-painted Metal
Sheets (Rib Type, Long
1014(1)b2 Span, 0.5mm thk) Qty.= 247.84 sq.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Pre-painted Metal
Sheets (Rib Type, Long
Span, 0.5mm thk)
247.84 sq.m. 650.00 161,096.00
161,096.00
Fabricated Metal
Roofing Accessory
1013(2)a (Ridge Roll, Gauge 26) Qty.= 11.00 l.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Fabricated Metal
Roofing Accessory
(Ridge Roll, Gauge 26)
11.00 l.m. 450.00 4,950.00
4,950.00
Fabricated Metal
Roofing Accessory
1013(2)b (Flashing, Gauge 26) Qty.= 123.60 l.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Fabricated Metal
Roofing Accessory
(Flashing, Gauge 26)
123.60 l.m. 450.00 55,620.00
55,620.00
Structural Steel,
1047(8)a Trusses Qty.= 3,591.96 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Structural Steel,
Trusses 3591.96 kg 100.00 359,196.00
359,196.00
Metal Structure
Accessories
1047(4)b (Turnbuckle) Qty.= 36.00 ea
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories
(Turnbuckle) 36.00 ea 450.00 16,200.00
16,200.00
Metal Structure
Accessories
1047(5)c (Crossbracing) Qty.= 201.53 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories
(Crossbracing)
201.53 kg 55.00 11,084.15
11,084.15
Metal Structure
Accessories (Steel
1047(5)d Plates) Qty.= 348.89 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories (Steel
Plates) 348.89 kg 55.00 19,188.95
19,188.95
Metal Structure
1047(5)b Accessories (Sagrods) Qty.= 33.64 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories (Sagrods) 33.64 kg 45.00 1,513.80
1,513.80
PREPARED BY:
CONTRACT I.D. NO. : 23GN0118
PROJECT NAME: Construction/Completion of Multi-Purpose Building, Barangay
Tabao-Rizal, Municipality of San Enrique, Negros Occidental
95 Days Duration
Description 1st 2nd 3rd 4th
QUARTERLY % ACCOMPLISHMENT 25.00 25.00 25.00 25.00
PHYSICAL
ACCOMPLISHMENT QUARTERLY CUMULATIVE % 50.00
ACCOMPLISHMENT 25.00 75.00 100.00
QUARTERLY CASHFLOW 945,695.35 945,695.35 945,695.35 945,695.35
FINANCIAL
ACCOMPLISHMENT QUARTERLY CUMULATIVE CASH
FLOW 945,695.35 1,891,390.70 2,837,086.05 3,782,781.40
Total 3,782,781.40
Prepared By:
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Contract ID: 23GN0118
Contract Name: Construction/Completion of Multi-Purpose Building, Barangay
Tabao-Rizal, Municipality of San Enrique, Negros Occidental
Contract Location: San Enrique, Negros Occidental
Part No. 1
BILL OF QUANTITIES
Occupational Safety and Seventy Two Thousand Seventy Seventy Two Thousand Seventy
B.7(1) 1.00
s.
Ninety Four Thousand Twenty Four Ninety Four Thousand Twenty Four
B.9(1) Mobilization/Demobilization 1.00
.
BILL OF QUANTITIES
PART III - CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A - EARTHWORKS
In words: Pesos In words: Pesos
Embankment from
804(1)a Roadway/Structure cu.m. 32.54 Two Hundred Thirty One & 84/100 Seven Thousand Five Hundred
Excavation Pesos Only Forty Four & 7/100 Pesos Only
Embankment from
One Thousand Thirty & 40/100 Sixty Nine Thousand Eight
804(2)a Borrow (Common cu.m. 67.75
Pesos Only Hundred Nine & 60/100 Pesos Only
Soil)
BILL OF QUANTITIES
PART III - CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART B - PLAIN AND REINFORCED CONCRETE WORKS
In words: Pesos In words: Pesos
Structural Concrete Nine Thousand Two Hundred Nine Hundred Ten Thousand Three
900(1)c (3000 psi, Class A, 28 Cu.m. 98.17 Seventy Three & 60/100 Pesos Hundred Eighty Nine & 31/100
Days) Only Pesos Only
BILL OF QUANTITIES
PART III - CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART C - FINISHING
In words: Pesos In words: Pesos
BILL OF QUANTITIES
PART III - CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART C - FINISHING
In words: Pesos In words: Pesos
Fabricated Metal
Five Hundred Seventy Nine & Six Thousand Three Hundred
1013(2)a Roofing Accessory l.m. 11.00
60/100 Pesos Only Seventy Five & 60/100 Pesos Only
(Ridge Roll, Gauge 26)
BILL OF QUANTITIES
PART III - CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART C - FINISHING
In words: Pesos In words: Pesos
Metal Structure
Five Hundred Seventy Nine & Twenty Thousand Eight Hundred
1047(4)b Accessories 36.00
60/100 Pesos Only Sixty Five & 60/100 Pesos Only
(Turnbuckle)
Metal Structure
Fourteen Thousand Two Hundred
1047(5)c Accessories kg 201.53 Seventy & 84/100 Pesos Only
Seventy Six & 38/100 Pesos Only
(Crossbracing)
Metal Structure
One Hundred Ninety Three & Fourteen Thousand One Hundred
1047(5)a Accessories (Bolts and kg 73.18
20/100 Pesos Only Thirty Eight & 37/100 Pesos Only
Rods)
BILL OF QUANTITIES
In words: Pesos
Three Million Seven Hundred Eighty Two Thousand Seven Hundred Eighty One & 40/100 Pesos Only
Submitted by:
CONTRACT I.D. NO. : 23GN0118
Total 3,782,781.40
Amount in word:
#NAME?
Prepared By: