Nineteen M
DETAILED ESTIMATES
a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Marine Plywood 2.00 pcs 600.00 1,200.00
Coco lumber 75.00 bd.ft. 45.00 3,375.00
Tarpaulin 64.00 sq.ft. 35.00 2,240.00
Common Wire Nails 5.00 kgs 120.00 600.00
Sub - Total 7,415.00
b. Labor
Description Qty No. of Day Rate/Day Total
Mason/Carpentry 1.0 1.0 600.00 600.00
Laborer/Helper 1.0 1.0 450.00 450.00
Sub - Total 1,050.00
a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Safety Shoes(Different Sizes) 18.00 pairs 700.00 12,600.00
Safety Helmet (free size) 18.00 pcs. 700.00 12,600.00
Safety Gloves (free size) 18.00 pairs 700.00 12,600.00
Sub - Total 37,800.00
b. Labor
Description Qty No. of Day Rate/Day Total
Safety Officer 1.0 90.0 450.00 40,500.00
Sub - Total 40,500.00
Embankment from
Roadway/Structure
Excavation (Common
804(1)a Soil) Qty.= 63.30 cu.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Embankment from
Roadway/Structure
Excavation (Common
Soil) 63.3 cu.m. 180.00 11,394.00
Sub - Total 11,394.00
Embankment from
Borrow (Common
Soil) 131.2 cu.m. 800.00 104,960.00
Sub - Total 104,960.00
Structural Concrete
(3000 psi, Class A, 28
900(1)c Days) Qty.= 556.65 Cu.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Structural Concrete
(3000 psi, Class A, 28
Days) 556.7 Cu.m. 7,200.00 4,007,880.00
Sub - Total 4,007,880.00
Reinforcing Steel
(Deformed, Grade
902(1)a 40) Qty.= 71,526.00 Kg.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Reinforcing Steel
(Deformed, Grade
40) 71526.0 Kg. 68.00 4,863,768.00
Sub - Total 4,863,768.00
Formworks and
903(2) Falseworks Qty.= 1,964.30 sq.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Formworks and
Falseworks 1964.3 sq.m. 685.00 1,345,545.50
Sub - Total 1,345,545.50
Soil Poisoning
40.0 L 1,000.00 40,000.00
Sub - Total 40,000.00
Painting Works
1032(1)a (Masonry/Concrete) Qty.= 1,050.33 sq.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Painting Works
(Masonry/Concrete) 1050.3 sq.m. 300.00 315,099.00
Sub - Total 315,099.00
Pre-painted Metal
Sheets (Corrugated,
1014(1)a2 Long Span, 0.5mm thk) Qty.= 833.00 sq.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Pre-painted Metal
Sheets (Corrugated,
Long Span, 0.5mm thk) 833.0 sq.m. 450.00 374,850.00
Sub - Total 374,850.00
Fabricated Metal
Roofing Accessory
1013(2)b (Flashing, Gauge 26) Qty.= 117.00 l.m.
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Fabricated Metal
Roofing Accessory
(Flashing, Gauge 26)
117.00 l.m. 220.00 25,740.00
25,740.00
Structural Steel,
1047(8)a Trusses Qty.= 9,775.34 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Structural Steel,
Trusses 9775.34 kg 145.00 1,417,424.30
1,417,424.30
Metal Structure
Accessories
1047(4)b (Turnbuckle) Qty.= 24.00 each
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories
(Turnbuckle) 24.00 each 450.00 10,800.00
10,800.00
Metal Structure
Accessories
1047(5)c (Crossbracing) Qty.= 364.03 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories
(Crossbracing) 364.03 kg 65.00 23,661.95
23,661.95
Metal Structure
Accessories (Steel
1047(5)d Plates) Qty.= 710.92 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories (Steel
Plates) 710.92 kg 65.00 46,209.80
46,209.80
Metal Structure
Accessories (Bolts and
1047(5)a Rods) Qty.= 214.87 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories (Bolts and
Rods) 214.87 kg 150.00 32,230.50
32,230.50
Metal Structure
1047(5)b Accessories (Sagrods) Qty.= 136.84 kg
a. Materials/Labor/Equipment
Description QTY. UNIT UNIT COST AMOUNT
Metal Structure
Accessories (Sagrods)
136.84 kg 45.00 6,157.80
6,157.80
PREPARED BY:
CONTRACT I.D. NO. : 24GN0100
PROJECT NAME: Rehabilitation of Multi-Purpose Building (Manuel Y. Torres Sports Center Grand Stand), Barangay
Poblacion, Bago City, Negros Occidental
Prepared By:
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Contract ID: 24GN0100
Contract Name: Rehabilitation of Multi-Purpose Building (Manuel Y. Torres Sports Center Grand Stand), Barangay Poblacion,
Bago City, Negros Occidental
Contract Location: Bago City, Negros Occidental
Part No. 1
BILL OF QUANTITIES
one hundred twenty eight thousand one hundred twenty eight thousand
B.3 (1) Permits and Clearances l.s. 1.00
eight hundred pesos eight hundred pesos
Occupational Safety and ninety six thousand four hundred ninety six thousand four hundred
B.7(1) 1.00
.
Health Program sixty five pesos and 60/100 sixty five pesos and 60/100
l.s
two hundred six thousand eighty two hundred six thousand eighty
B.9(1) Mobilization/Demobilization 1.00
.
pesos pesos
l.s
BILL OF QUANTITIES
PART C - EARTHWORKS
In words: Pesos In words: Pesos
Embankment from
Roadway/Structure two hundred thirty one pesos and fortheen thousand six hundred
804(1)a cu.m. 63.30
Excavation (Common 84/100 seventy five pesos and 47/100
Soil)
804(7) Gravel Fill cu.m. 53.24 one thousand five hundred forty eighty two thousand two hundred
five pesos and 60/100 eighty seven pesos and 74/100
BILL OF QUANTITIES
PART D - REINFORCED CONCRETE
In words: Pesos In words: Pesos
BILL OF QUANTITIES
PART E - FINISHING AND OTHER CIVIL WORKS
In words: Pesos In words: Pesos
one thousand two hundred eighty fifty one thousand five hundred
1000(1) Soil Poisoning 40.00
eight pesos twenty pesos
five hundred eighty two thousand five hundred eighty two thousand
1051(1)a Railing l.s. 1.00
one hundred seventy six pesos one hundred seventy six pesos
BILL OF QUANTITIES
PART E - FINISHING AND OTHER CIVIL WORKS
In words: Pesos In words: Pesos
Fabricated Metal
two hundred eighty three pesos thirty three thousand one hundred
1013(2)b Roofing Accessory l.m. 117.00
and 36/100 fifty three pesos and 12/100
(Flashing, Gauge 26)
Metal Structure
five hundred seventy nine pesos thirteen thousand nine hundred ten
1047(4)b Accessories each 24.00
and 60/100 pesos and 40/100
(Turnbuckle)
BILL OF QUANTITIES
PART E - FINISHING AND OTHER CIVIL WORKS
In words: Pesos In words: Pesos
Metal Structure
thirty thousand four hundred
1047(5)c Accessories 364.03 eighty three pesos and 72/100
seventy six pesos and 59/100
(Crossbracing)
Metal Structure
fifty nine thousand five hundred
1047(5)d Accessories (Steel kg 710.92 eighty three pesos and 72/100
eighteen pesos and 22/100
Plates)
Metal Structure
one hundred ninety three pesos forty one thousand five hundred
1047(5)a Accessories (Bolts and kg 214.87
and 20/100 twelve pesos and 88/100
Rods)
Nineteen Million Seven Hundred Eighty Eight Thousand One Hundred Twenty Two Pesos and 86/100
Submitted by:
CONTRACT I.D. NO. : 24GN0100
PROJECT NAME: Rehabilitation of Multi-Purpose Building (Manuel Y. Torres Sports Center Grand Stand),
Barangay Poblacion, Bago City, Negros Occidental
Total 19,788,122.86
Amount in word:
Nineteen Million Seven Hundred Eighty Eight Thousand One Hundred Twenty Two Pesos and 86/100
Prepared By: