Critical Path Method

Aktivitas Preceending Activity Duration per week


A - 2
B A 1
C A 3
D B 4
E C 4
F B 3

Activity Total Float


A TF (1,2)=2-0-2=0
B TF (2.3)=4-1-2=1
C TF (2,4)=5-3-2=0
D TF (3,5)=9-4-4=1
E TF (4,5)=9-4-5=0
F TF(5,6) =12-3-0=0

JALUR KRISIS
1-3-5-6