WORK METHOD STATEMENT

Prepared By : Project Department -Southern Tech Engineering (M) Sdn Bhd


Project Details
Site/Location: Various Location LG - L3 (6 Location)
On- Site AHU Blower Fan & Tray Cleaning
WMS For:
& Repainting Works
Client: Southkey Megamall Sdn Bhd
Quo/PO Reference: Quotation No.Q2404-014 Client In-Charge: Mr.Afiq
WMS Date: To Be Confirmed Work Duration: To Be Confirmed

Work Objective: To Clean & Repainting AHU Blower Fan & Tray

Work Scope Summary: To Supply Manpower & Tools For Cleaning & Repainting Blower Fan & Tray With Rust Proof Paint

General Work Method


No. Work Activity Required Working Days
1 Equipment Mobilization To Work Site
2 AHU Blower Fan 's Induction Motor Vibration Reading Recording (Pre-Job Data Collection)
3 Switch Off All Related Electrical Source & Implement LOTO
4 General Cleaning To Prepare Work Site
5 Close Blower's Suction & Discharge Points Using Canvas
6 Clean Equipment Surface From Rust & Old Paint Using Power Brush
7 Clean Debris From The Power Brushing Activity To Prepare Surface For 1st Layer Paint
8 Apply 1st Layer Paint
To Be Confirmed After Order
9 Allow 1st Layer Paint For Complete Drying
Confirmation
10 Apply 2nd Layer Paint
11 Allow Complete Drying For 2nd Layer Paint
12 Site Housekeeping
13 Remove Canvas Cover & Verify With Site PIC For The Paint Job Result
14 Remove LOTO & Swith On All Related Electrical Source
15 AHU Blower Fan 's Induction Motor Vibration Reading Recording (Post-Job Data Collection)
16 Vibration Reading Result Verification With Site PIC
17 Equipment Hand-Over

Remark:
1) STE(M)SB Will Use Appropriate Alternative Manual Drying Methods If The Paint Found Wet Through Normal/Natural Drying Process E.g UV Light, Portable
Blower Fan Or Etc.
2) If Manual Drying Method Still Not Works - STE(M)SB Team Will Have To Dismantle Equipment To Allow Painting To Be Done & Dry In Open
Air Condition.
3) If Any Vibration Identified During Post-Job Data Collection, STE(M)SB Will Proceed To Conduct Onsite Balancing Works for Pulley & Belt.

Work Procedures Stated Above May Change Upon Any Findings On-Site, STE(M)SB Will Only Proceed With Any Changes Of Work Procedures Upon Site PIC Prior
Approval.

By signing below, we hereby acknowledge the work method used for the above mention works scope and we have agreed that Southern Tech Engineering (M)
Sdn Bhd to proceed with the work progress based on the work method statement above.

Developed & Prepared By: Client Acknowledgment:


Name:
Project Department
Southern Tech Engineering (M) Sdn Bhd
Designation:
Date: 10/05/2024