71120124212167VTWKUA1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Megha Engineering & Infrastructures Ltd.

An ISO 9001-2015 ComPanY


Rmeil S-2, Technocrat lndl. Estate, Balanagar, Hyderabad-500037, Telangana, INDIA
Tel: +91 -40-44336700 Fax: +91 -40-44336800
E-mai | : i nfo@meil. in Visit us : www. meil. in U452O2T G2O06PLC05027 1

L/CG D Rang aReddy/Forest/Permissionl20'l 9-20 I 025


Date: 10-07-2020
Ref: M El

+
to
The Principle Chief Conservator of Forests,
(Head of Forest Force),
Aranya Bhavan, Saifabad, Hyderabad
Telangana - 500004

ion f
cros noK - Thu Road ch.
rame teel

Dear Sir,
we have
We, Megha Engineering & Infrastructures Limited (MEIL) proudly claim that
been coitributing in Nation's progress by executing various projects in hydro carbons,
irrigation, po*eilcas based and Solarl, domestic water supply schemes, roads and
buildings, etc.
Gas
We are pleased to inform that we have been authorized by Petroleum and Natural
Regutatory Board (PNGRB), vide schedule D dated 14th November 2018 to Lay, Build
Op[rate oi Expand City or iocal Natural Gas Distribution Network to cater commercial,
Industrial and domestic consumption in the Geographical Area of Medchal-Malkajgiri,
Ranga Reddy & Vikarabad Districts and copy of the same is enclosed herewith. You
*oui-d appreiiate that the natural gas being used is clean,. safe and affordable by re-
ducing pollution and improving the living conditions of the citizens.

a) M/s MEIL is planning to lay4" steel Pipe, DN 125mm PE100 SDR11 MDPE of length
of 1 1 18,22 Mts from- Potharam to Kotthur Cross along Keesara - Thurkapally Road i.e.
from Ch. 20/350 to 21/300
b) We wish to mention that pipeline will be laid at a depth of 1'0
to 1'20 mtr' From ground
level depending on soil condition. Allthe road crossings will be restored to normal/orig-
with
inal condition. National Highways, state Highway and Railways shall be crossed
movement. Pipe
Jacking and boring methoJ / Open cut without disrupting the vehicular
for
line lafrng shal be carried out following good construction practices and safety rules
cross toJntry and city Gas pipe line project and as per local authority
guidelines & in

line with State Highway & National Highway guidelines'


per-
We are confident to complete the project in time with the cooperation and timely
mission. Therefore we solicit your timely permissions and support as the pipeline laying
contract is going to be awarded very shortly and work is to be executed on round the
clock basis.

# Page 1 of 2
The following documents are attached for reference:

1. FORM-ADraft
2. Authenticated Pipeline route map.
3. Authenticated Letter
4. Acceptance of Government authorization by pNGRB and relangana Govt.

Further we request your good selves to advise/arrange the joint inspection with
respective
concerned officials to know the exact length of Pipeiine in ihe above Jurisdictions of po-
tharam - Kolthur and surrounding areas to enable us for further necessary action please.

Thanking you.

Yours Faithfully,

\Nf,
Anil Kumar D R.
Megha Engineering &
CGD Ranga Reddy.
Ph no: +91 - 9900491856

Encl:As above

Page 2 of 2

You might also like