BENCHMARK APPROVAL (TRACKING)

REMARKS
SN REFERENCE NO. DOCUMENT DESCRIPTION DATE SUMBITTED DATE RESPONDED
REJECTED/CANCELL
ED/APPROVED
20017_SPRP_CP-0304_P2-BA-001 STRUCTURAL WORKS, RC COLUMN, WALLS AND SLAB, TECC-012, 066, 042 2/10/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-002 MASONRY WORKS, TEC-048 2/10/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-002.1 REVISED BENCHMARK FOR MASONRY WORK, TEC-048 3/22/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-003 PLASTERING WORKS, TEC-050, 0158 2/10/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-004 EXTERIOR WALL PAINTING ,TEC-157 7/3/2023 PENDING
20017_SPRP_CP-0304_P2-BA-005 ROOF TRUSS 14 & 15 2/10/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-006 EELV AT MAIN BUILDING (ROUGHING_INS/EMBEDMENTS CHECKLIST), TEC-316, 33.1, 31, 276 2/24/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-007 DOOR OPENING AT GUEST WING A2-UNIT2 2/24/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-008 PLUMBING INSTALLATION, TEC-40, 133 2/24/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-009 ROOF TILE, GUTTER AND ROOF EDGE, TEC-271 2/24/2023 RESUBMIT
20017_SPRP_CP-0304_P2-BA-010 PRECAST INSTALLATION FOR BEACH SUITE 2, TEC-349.1 2/24/2023 APPROVED 6/26/2023
20017_SPRP_CP-0304_P2-BA-011 WATERLINE INSTALLATION OF BEACH SUITE 4/21/2023 CANCEL
20017_SPRP_CP-0304_P2-BA-012 GUTTER AND DOWNSPOUT INSTALLATION 6/6/2023 RESUBMIT
20017_SPRP_CP-0304_P2-BA-013 ROOF EAVES EDGING 6/21/2023 PENDING
20017_SPRP_CP-0304_P2-BA-014 WIRE GUTTER INSTALLATION AND TERMINATION 2/20/2024 APPROVED 5/28/2024
20017_SPRP_CP-0304_P2-BA-015 PIPING LAYOUT FOR ELECTRICAL AND AUXILIARY FEEDER LINES (ROUGHING INS.) 2/24/2024 PENDING
20017_SPRP_CP-0304_P2-BA-016 LIMESTONE CLADDING 3/12/2024 APPROVED 4/25/2024
20017_SPRP_CP-0304_P2-BA-017 ELECTRICAL AND ELV FEEDER PIPING LAYOUT CROSSING WITH OTHER UTILITIES (ROUGHING INS.) 3/16/2024 APPROVED 3/19/2024
20017_SPRP_CP-0304_P2-BA-018 ElECTRICAL AND ELV PIPING TERMINATION TO PANEL (ROUGHING INS.) 3/16/2024 APPROVED 5/15/2024
20017_SPRP_CP-0304_P2-BA-019 ElECTRICAL AND ELV PIPING TERMINATION TO PANEL (ROUGHING INS.) AT BEACH SUITE 5/3/2024 APPROVED 6/19/2024
20017_SPRP_CP-0304_P2-BA-020 PEBBLES WASHOUT / INLAY 3/21/2024 APPROVED 04/25/2024
20017_SPRP_CP-0304_P2-BA-021 PYROTEK INSULATION FOR SANITARY PIPELINE 4/18/2024 APPROVED 5/8/2024
20017_SPRP_CP-0304_P2-BA-022 MEP'S UTILITIES PIPING/ EXPOSED LAYOUT 4/19/2024 PENDING
20017_SPRP_CP-0304_P2-BA-023 TERMINATION OF DECK SLAB AND STONE COATED & ROOFING 5/2/2024 APPROVED 6/19/2024
20017_SPRP_CP-0304_P2-BA-024 PEBBLES WASH OUT GUEST WINGS GROUND FLOOR 5/27/2024 APPROVED 6/19/2024
20017_SPRP_CP-0304_P2-BA-025 PIPE TERMINATION TO PANEL 5/28/2024 PENDING