Professional Documents
Culture Documents
Project Estimate of Raha 15.44 Crore (Final)
Project Estimate of Raha 15.44 Crore (Final)
The project estimate of Raha town water supply scheme has been prepared
based on CPWD DSR 2021, APHED Schedule of rates for the year of 2015-16,
and analysis rates for Non-Schedule Works (with Ground Water source by
installing DTW) including 2 (two) month trial run after commissioning for
providing 3.60 MLD (24x7) treated water as per CPHEEO's Standard
8.1.7
8.1.3
8.1.2
8.1.1
8.2.1
8.2.3
8.2.5
55
8.2.2
8.24
8.2.6
8.5.1
8.5.6
8.5.5
(ANNEXURE-C )
DETAIL ESTIMATE FOR DRAWING POWER LINE AND 100 KVA SUB STATION
AT TREATMENT PLANT SITE
(APPROXIMATE LENGTH OF THE POWER LINE = 1250.00 M)
Note :1. This Estimate is based on Approved Rate A.P.D.C.L.
2. The raw water pumps of water supply project for CRPF camp at Kashipur shall also be installed on the intake station at
River Barak for thewater supply project for CRPF camp at Doyapur. Therefore, the electrical power line to the Intake
Station and the Substation there shall have to cater for the load of kashipur project.
Item - : Starter for the Electrical Motor for the above Pump
a) Soft Starter for the Drive Motor for the above pump
including cost of connection cable 1 No. @ Rs. 34688.00 = Rs. 34688.00
b) T & P (LS) = Rs. 50.00
c) Labour charge for fitting, fixing of the pump set on board
of the barge @ 10 % cost of starter = Rs. 3468.80
Sub Total = Rs. 38206.80
d) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 3820.68
Total Cost = = Rs. 42027.48
Say, = Rs. 42027.00
Item - : Earthing
a) Cost of Earth Strip 15 Rm @
Rs. 210.00 = Rs. 3150.00
b) Cost of Copper plate Earthing 1 No @
Rs. 16522.50 = Rs. 16522.50
c) Connection cable and nuts bolts etc. 10 Rm @
Rs. 275.00 = Rs. 2750.00
d) T & P (LS) = Rs. 50.00
e) Labour charge for fitting, fixing @10 cost of nmaterials = Rs. 2242.25
Sub Total = Rs. 24714.75
f) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 2471.48
Total Cost = = Rs. 27186.23
Say, = Rs. 27186.00
Item - : 3.5 core cable for connecting the pump starter with elecrical power connection
a) Cost of Cable 1 RM @ Rs 725.00 = Rs. 725.00
b) Cost of Glands etc. @ 10% of the above = Rs. 72.50
Sub Total = Rs. 797.50
c) Contractor's profit & overhead @ 10% of the above = Rs. 79.75
Total = Rs. 877.25
Say, = Rs. 877.00
A)Flanged Adopter
200 mm dia. 10
1 10 Each 2300.00 23000.00
B) Collar coupling
200 mm dia. 10
1 10 Each 2700.00 27000.00
4 Supply D.I.D.S Sluice valve conforming to IS 14846-
2000 of PN1.0
200 mm dia. 1 1 1 Each 18668.00 18668.00
5 Supply of DI Non- Return Valve
Item : Supplying, laying of the pipes in line and level in trenches and / or over supports,
jointing, testing
(A) 300 dia pipeand
: commissioning of D.I. / S.S. Pipe including taking delivery of the pipe from
i) FoR Rate of pipe excluding GST @ = Rs. 3950.00 per metre K7 = Rs. 3950.00
ii) Labour charge for laying, jointing etc. @ 10 % cost of the pipe including taking delivery of = Rs. 395.00
the pipe from the stock yard & transportation of the same upto work site;, handling charges; Cost = Rs.
Sub Total 4345.00
Add Contractor's profit & Overhead @ 10 % = Rs. 434.50
Grand Total = Rs. 4779.50
Say, Rs. 4780.00
(B) 250 dia pipe : K7
i) FoR Rate of pipe excluding GST @ = Rs. 3500.00 per metre K7 = Rs. 3500.00
ii) Labour charge for laying, jointing etc. @ 10 % cost of the pipe including taking delivery of = Rs. 350.00
the pipe from the stock yard & transportation of the same upto work site;, handling charges; Cost = Rs.
Sub Total 3850.00
Add Contractor's profit & Overhead @ 10 % = Rs. 385.00
Grand Total = Rs. 4235.00
Say, Rs. 4235.00
(C) 200 dia pipe :
i) FoR Rate of pipe excluding GST @ = Rs. 2950.00 per metre K7 = Rs. 2950.00
ii) Labour charge for laying, jointing etc. @ 10 % cost of the pipe including taking delivery of = Rs. 295.00
the pipe from the stock yard & transportation of the same upto work site;, handling charges; Cost = Rs.
Sub Total 3245.00
Add Contractor's profit & Overhead @ 10 % = Rs. 324.50
Grand Total = Rs. 3569.50
Say, Rs. 3570.00
(D) 150 dia pipe :
i) FoR Rate of pipe excluding GST @ = Rs. 2200.00 per metre K7 = Rs. 2200.00
ii) Labour charge for laying, jointing etc. @ 10 % cost of the pipe including taking delivery of = Rs. 220.00
the pipe from the stock yard & transportation of the same upto work site;, handling charges; Cost = Rs.
Sub Total 2420.00
Add Contractor's profit & Overhead @ 10 % = Rs. 242.00
Grand Total = Rs. 2662.00
Say, Rs. 2662.00
i) FoR Rate of pipe excluding GST @ = Rs. 1600.00 per metre K7 = Rs. 1600.00
ii) Labour charge for laying, jointing etc. @ 10 % cost of the pipe including taking delivery of = Rs. 160.00
the pipe from the stock yard & transportation of the same upto work site;, handling charges; Cost = Rs.
Sub Total 1760.00
Add Contractor's profit & Overhead @ 10 % = Rs. 176.00
Item : Supplying, fitting and fixing of Ductile Iron (DI) plain ended / flanged
specials such
Considering as bend
special , tee
of 100 Kg., weight
reducer / enlarger , end plug , socket , spigot , etc., all
a) Cost of DI Special = 100 Kg.@ Rs. 102.5.00/Kg. including inspection & transportation = Rs. 10250.00
b) Machining & Febrication charge = NIL = Rs. 0.00
c) Transportation of specials from Manufacturer's shop (considering Kolkata) to work site @ = Rs. 1350.00
Rs.13.50 /Kg. including handling charges etc. Total = Rs. 11600.00
d) Labour charge for laying, jointing etc. including Cost of T&P materials; Sundries viz., Manila = Rs. 1160.00
Rope, Soap Solution etc.; and, Water charge (as per APHED approved norms) @ 10% cost of Total = Rs. 12760.00
Add Contractor's profit & Overhead @ 10 % = Rs. 1276.00
Grand Total = Rs. 14036.00
Say, Rs. 14036.00
Therefor, Cost per Unit Weight = Rs. 140.36
Say, Rs. 140.00
Item : Supplying , fitting , fixing of cast iron double flanged (CI/DF) sluice
valve with
(A) 100 mmhand
Diawheel
Valve (Class PN-1.6) conforming to relevant BIS Specification
a) landed Cost of valve at including all taxes & duties @ Rs. 8500.00 per m. = Rs. 8500.00
b) T & P (LS) = Rs. 50.00
c) Labour charge for fitting, fixing of the item @ 10 % cost of Materials = Rs. 850.00
Sub Total = Rs. 9400.00
d) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 940.00
Total Cost = Rs. 10340.00
Say, Rs. 10340.00
(B) 125 mm Dia Valve
a) landed Cost of valve at including all taxes & duties @ Rs. 10625.00 per m. = Rs. 10625.00
b) T & P (LS) = Rs. 50.00
c) Labour charge for fitting, fixing of the item @ 5 % cost of Materials = Rs. 531.25
Sub Total = Rs. 11206.25
d) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 1120.63
Sub Total = Rs. 12326.88
Add GST @ 12 % = Rs. 1479.23
Total Cost = = Rs. 13806.10
Say, Rs. 13806.00
Item : Supplying , fitting , fixing of cast iron double flanged (CI/DF) Non Return
Valve
(A) 100conforming to relevant BIS Specification (with current amendment ), of
mm Dia Valve
a) Cost of valve at kolkata + Excise+ freight 1 No. @ Rs. 4675.00 = Rs. 4675.00
b) T & P (LS) = Rs. 50.00
c) Labour charge for fitting, fixing of the item @ 5 % cost of Materials = Rs. 233.75
Sub Total = Rs. 4958.75
d) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 495.88
Total Cost = Rs. 5454.63
Say, Rs. 5455.00
Item : Supplying , fitting , fixing of 80 mm dia cast iron flanged spring operated
double
a) Cost ofacting
valve atair valve
kolkata conforming
+ Excise+ CST +tofreight
relevant BIS Specification (with
1 No. @ Rs. current = Rs.
6375.00 6375.00
b) T & P (LS) = Rs. 50.00
c) Labour charge for fitting, fixing of the item @ 10 % cost of Materials = Rs. 637.50
Sub Total = Rs. 7062.50
d) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 706.25
Total Cost = Rs. 7768.75
Say, Rs. 7769.00
Item : Construction of RCC Padestal for supporting pipe line in depressed areas,
valley
a) Earth etc.
Workofinsize 400 mm x 400 mm x 4.0 mm average7.050
excavation height
C.m.(2000
@ Rs. mm below
286.85 = Rs. 2022.29
b) Shuttering nad Shoring 10.800 S.m. @ Rs. 132.90 = Rs. 1435.32
4.860 S.m. @ Rs. 145.55 = Rs. 707.37
c) PCC 0.200 C.m. @ Rs. 733.30 = Rs. 146.66
d) Flat Brick Soling 1.960 S.m. @ Rs. 368.71 = Rs. 722.67
e) Plastering 3.36 S.m. @ Rs. 307.45 = Rs. 1033.03
f) R.C.C. work (M25) 1.100 C.m. @ Rs. 7997.30 = Rs. 8797.03
g) Reinforcing Steel (TMT Bar) 0.870 Qtl. @ Rs. 8965.00 = Rs. 7799.55
h) Form Work (Shuttering) 8.16 S.m. @ Rs. 307.95 = Rs. 2512.87
Sub Total as per CPWD DSR 2021 = Rs. 25176.80
Add extra for GST increment from 12% to 18% with increment multiplying = Rs. 1581.00
factor (0.2127-0.1405)=0.0722 over the above amount excluding CPOH
Sub15% =
Total = Rs. 26758.00
Add for Price escallation as per Notification of Spl. Director General (R.G), = Rs. 5619.00
CPWD, Guwahati No.17(6)/Spl.D.G(R.G.)/Ghy/Works/Vol-II/ 2021/1779(H) Say, = Rs. 32377.00
Item : Construction of RCC 1.0 m x 1.0 m, x 1.0 m RCC Anchor / Thrust Block
withof Gradein excavation
a) Earth Work M25 with 100 mm thick cement concrete base
3.840 C.m.of@prop.
Rs. 1:3:6 (1
286.85 = Rs. 1101.50
b) Shuttering nad Shoring 9.600 S.m. @ Rs. 132.90 = Rs. 1275.84
c) PCC 0.140 C.m. @ Rs. 6833.40 = Rs. 956.68
d) Flat Brick Soling 1.440 S.m. @ Rs. 733.30 = Rs. 1055.95
f) R.C.C. work (M25) 1.000 C.m. @ Rs. 7997.30 = Rs. 7997.30
g) Reinforcing Steel (TMT Bar) 0.630 Qtl. @ Rs. 8965.00 = Rs. 5647.95
h) Form Work (Shuttering) 4.00 S.m. @ Rs. 307.95 = Rs. 1231.80
Sub Total as per CPWD DSR 2021 = Rs. 19267.02
Add extra for GST increment from 12% to 18% with increment multiplying = Rs. 1210.00
factor (0.2127-0.1405)=0.0722 over the above amount excluding CPOH
Sub15% =
Total = Rs. 20477.00
Add for Price escallation as per Notification of Spl. Director General (R.G), = Rs. 4300.00
CPWD, Guwahati No.17(6)/Spl.D.G(R.G.)/Ghy/Works/Vol-II/ 2021/1779(H) Say, = Rs. 24777.00
2 laying & Jointing of Pipe 100 dia pipe = 0.0 RM 0.000 Rm 0.00
150 dia pipe = 0.0 RM 0.000 Rm 0.00
200 dia pipe = 550.0 RM 550.000 Rm 550.00
250 dia pipe = 0.0 RM 0.000 Rm 0.00
300 dia pipe = 0.0 RM 0.000 Rm 0.00
5 Sluice Valve
100 dia valve 0 0 Nos 0.00
150 dia valve 0 0 Nos 0.00
200 dia valve 2 2 Nos 2.00
250 dia valve 0 0 Nos 0.00
300 dia valve 0 0 Nos 0.00
6 NRV
100 dia valve 0 0 Nos 0.00
150 dia valve 0 0 Nos 0.00
200 dia valve 2 2 Nos 2.00
250 dia valve 0 0 Nos 0.00
300 dia valve 0 0 Nos 0.00
9 Valve Chamber
for Sluice Valves only 2 2.000 Nos. 2
2 Shuttering and shoring upto 1.5 m 1 1.8 1.8 1.5 10.800 Sq.m. 10.80
3 Shuttering and shoring from 1.5 to 3.0 m 1 1.8 1.8 0.675 4.860 Sq.m. 4.86
6 Reinforcing steel
1% of Gross vo;lume of concrete 0.011 Cu.m.
Weight @ 7850 Kg/ Sq.m.
86.664
= Kg
= 0.867 Qtl. 0.87
2 Shuttering and shoring upto 1.5 m 1 1.5 1.5 1.5 9.000 Sq.m. 9.00
5 Bk. Work in Sub Structure 4 1.23 0.23 1.8 2.037 Cu.m. 2.04
7 Reinforcement
0.8% of Gross vo;lume of concrete 0.003 Cu.m.
Weight @ 7850 Kg/ Sq.m. = 20.096 Kg
= 0.201 Qtl. 0.20
Rounded
Sl. Item No. L B H Qty Unit up Qty
2 Shuttering and shoring upto 1.5 m 1 1.6 1.6 1.5 9.600 Sq.m. 9.60
9 Reinforcement
0.8% of Gross vo;lume of concrete 0.008 Cu.m.
Weight @ 7850 Kg/ Sq.m. = 62.800 Kg
1 (CPWD, DSR' 21, Item No.- 2.8):- Earth work in excavation by mechanical means (Hydraulic
excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or
Footing (800X800)-14 nos 1 14 1.20 1.20 1.00 20.16 M3
Steps 1 2 1.50 1.20 0.20 0.72 M3
Total = 20.88 M3 286.85 5989.43
2 (CPWD, DSR' 21, Item No.-2.27):- Supplying and filling in plinth with sand under floors,
including watering, ramming, consolidating and dressing complete.
Building out to out ex. Plinth wall 1 1 15.02 6.02 1.00 90.42 M3
Total = 90.42 M3 2161.20 195416.57
3 (CPWD DSR 2021 ITEM NO -11.2):- Dry brick on edge flooring in required pattern with bricks
of class designation 7.5 on a bed of 12 mm mud mortar, including filling joints with Jamuna
Footing (900X900)-14 nos 1 14 0.90 0.90 11.34 M2
Tie beam Ex. Column L/S 1 2 13.85 0.40 11.08 M2
Tie beam Ex. Column S/S 1 2 5.54 0.40 4.43 M2
Building floor 1 1 15.00 6.00 90.00 M2
Steps 1 2 1.50 1.00 3.00 M2
Total = 119.85 M2 733.30 87887.47
4 (CPWD, DSR' 21, Item No.-4.11):- Providing and laying damp-proof course 50mm thick with
cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources :2 4
Tie beam Ex. Column L/S 1 2 13.85 0.12 3.32 M
Tie beam Ex. Column S/S 1 3 5.54 0.12 1.99 M2
Less D 1000 -1 2 1.20 0.12 -0.29 M2
Total = 5.03 M2 452.25 2275.00
5 (CPWD DSR 2021 ITEM NO - 4.1.5):- Plain cement concrete works with coarse aggregate of
sizes 13mm to 32mm in foundation bed for footing steps, walls, brick works etc. as directed
Footing (900X900)-14nos 1 14 0.90 0.90 0.10 1.13 M3
Tie beam Ex. Column L/S 1 2 13.85 0.40 0.10 1.11 M3
Tie beam Ex. Column S/S 1 2 5.54 0.40 0.10 0.44 M3
Building floor 1 1 15.00 6.00 0.10 9.00 M3
Steps 1 2 1.50 1.00 0.10 0.30 M3
Total = 11.99 M3 6833.40 81899.67
6 CPWD, DSR' 21, Item No.-5.22.6:- Steel reinforcement for R.C.C. work including straightening,
cutting, bending,
Footing jali placing
F800X800 10#in position and binding all complete upto plinth level.- 5.22.6
@150c/c 12 14 0.90 0.62 93.74 Kg
14 nos Column Vertical 12# 4 14 5.13 0.89 255.68 Kg
Column ties 8# UPTO PL 9 14 0.84 0.39 41.28 Kg
Column ties 8# above PL 17 14 0.84 0.39 77.97 Kg
Tie beam full length 12# 1 5 52.92 0.89 235.49 Kg
Stirrups 6# @ 125c/c 300 1 0.87 0.22 57.42 Kg
8 (CPWD, DSR' 21, Item No.-5.9):- Centering and shuttering including strutting, propping etc. and
removal of form for- 5.9.5 Lintels, beams, plinth beams, girders, bressumers and
Tie beam Ex. Column L/S 2 2 13.85 0.305 16.90 M2
Tie beam Ex. Column S/S 2 2 5.54 0.305 6.76 M2
Roof tie & Lintel Beam 2 2 42.92 0.15 25.75 M2
Opening top W1000 1 12 1.00 0.12 1.44 M2
Opening top D1200 1 2 1.20 0.12 0.29 M2
Total = 23.66 M2 608.35 14391.01
9 (CPWD, DSR' 21, Item No.-5.9):- Centering and shuttering including strutting, propping etc. and
removal of form for-5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts
14 Nos Colm. (230 x 230)UPTO PL 4 18 1.50 0.23 24.84 M2
14 Nos Colm. (120 x 120) above PL 4 18 3.30 0.112 26.61 M2
Total = 51.45 M2 804.25 41379.63
10 (CPWD, DSR' 21, Item No.-5.9):- Centering and shuttering including strutting, propping etc. and
removal of form for- 5.9.3-Suspended floors, roofs, landings, balconies and access platform 2
Chajja over W1000 1 12 1.50 0.70 12.60 M
Chajja over D1200 1 2 1.50 0.70 2.10 M2
Total = 14.70 M2 766.55 11268.28
11 CPWD, DSR' 21, Item No.-5.2.1:- Providing and laying in position specified grade of reinforced
cement concrete, excluding the cost of centering, shuttering, finishing & reinforcement – All
Footing (800X800) 1 14 0.80 0.80 0.150 1.34 M3
12 CPWD, DSR' 21, Item No.-5.2.2:- Reinforced cement concrete work in walls (any thickness),
including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,
14 Nos Colm. (230 x 230) 1 14 3.30 0.23 0.23 2.44 M3
Lintel & roof Tie beam (120X150) 1 2 41.24 0.12 0.15 1.48 M3
Chajja over W1000 1 12 1.30 0.60 0.075 0.70 M3
Chajja over D1200 1 2 1.30 0.60 0.075 0.12 M3
Total = 4.75 M3 10185.05 48354.75
13 (CPWD DSR 2021 ITEM NO -6.1):- Brick work with common burnt clay F.P.S. (non modular)
bricks of class designation 7.5 in foundation and plinth in: 6.1.1 Cement mortar 1:4 (1 cement3 :
Tie beam Ex. Column L/S 1 1 41.24 0.23 0.70 6.64 M
Steps 1 2 1.50 1.00 0.25 0.75 M3
Steps 1 2 1.50 0.75 0.15 0.34 M3
1 2 1.50 0.50 0.15 0.22 M3
1 2 1.50 0.25 0.15 0.11 M3
Total = 8.06 M3 6882.00 55500.85
14 (CPWD DSR 2021 ITEM NO -6.13):- Half brick masonry with common burnt clay F.P.S. (non
modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level.-
Wall L/S+S/S 1 1 41.24 3.00 123.72 M2
Gable ends 0.5 2 6.23 0.90 5.61 M2
Less Door -1200X2100 -1 2 1.20 2.10 -5.04 M2
Less window- W1000X1200 -1 12 1.00 1.20 -14.40 M2
Less V-1000X600 -1 14 1.00 0.60 -8.40 M2
15 (CPWD, DSR' 21, Item No.-6.15):- Extra for providing and placing in position 2 Nos 6mm dia.
M.S. bars at every third course of half brick masonry.
Quantity as above item 101.49 M2 86.45 8773.81
16 (CPWD, DSR' 21, Item No.-13.2):- 15 mm cement plaster on the rough side of single or half
brick wall of mix : 13.2.1:- 1:4 (1 cement: 4 fine sand)
Wall L/S 2 2 15.23 3.30 201.04 M2
Wall S/S 2 2 6.23 3.30 82.24 M2
Gable ends 0.5 4 6.23 0.90 11.21 M2
Chajja- W1000X1200 2 12 1.30 0.60 18.72 M2
Less Door -1200X2100 -1 2 1.20 2.10 -5.04 M2
Less window W1000X1200 -1 12 1.00 1.20 -14.40 M2
Total = 293.77 M2 339.70 99792.31
17 (CPWD, DSR' 21, Item No.-11.6):- Cement plaster skirting up to 30 cm height, with cement
mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement. 11.6.1 18
EXTERNAL wall Plinth- L/S 1 2 15.25 0.75 22.88 M2
S/S 1 2 7.15 0.75 10.73 M2
Hall L/S 1 2 14.95 0.20 5.98 M2
S/S 2 2 5.95 0.20 4.76 M2
Less Door1000X2100 -1 2 1.20 0.20 -0.48 M2
Total = 43.86 M2 570.75 25033.10
18 (CPWD, DSR' 21, Item No.-11.5):- 62 mm thick cement concrete flooring with concrete
hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand :2 4
Hall 1 1 14.95 5.95 88.95 M
Total = 88.953 M2 928.65 82605.74
19 (CPWD, DSR' 21, Item No.-4.17) :- Making plinth protection 50mm thick of cement concrete
1:3:6 (1 cement: 3 coarse sand (zone-III) derived from natural sources : 6 graded stone
EXTERNAL wall- L/S 1 2 15.25 0.60 18.30 M2
S/S 1 2 8.63 0.60 10.36 M2
Total = 28.66 M2 681.65 19533.36
20 (CPWD, DSR' 21, Item No.-9.1):- Providing wood work in frames of doors, windows, clerestory
windows and other frames, wrought framed and fixed in position with hold fast lugs or with
Door1200X2100 (H) 1 2 1.20 0.100 0.075 0.02 M3
Vertical 2 2 2.10 0.100 0.075 0.06 M3
Window W1000X1200 2 12 1.00 0.100 0.075 0.18 M3
Vertical 2 12 1.20 0.100 0.075 0.22 M3
V1000X600 2 14 1.00 0.100 0.075 0.21 M3
Vertical 2 14 0.60 0.100 0.075 0.13 M3
Total = 0.813 M3 74199.70 60324.36
21 (CPWD, DSR' 21, Item No.-9.53):- Providing 40x5 mm flat iron hold fast 40 cm long including
fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement
Door-1200X2100 6 2 12.00 Nos
Window W-1000X1200 4 12 48.00 Nos
V-1000X600 2 14 28.00 Nos
Total = 88.00 Nos 194.35 17102.80
22 (CPWD, DSR' 21, Item No.-9.20):- Providing and fixing ISI marked flush door shutters
conforming to IS : 2202 (Part I) decorative type, core of block board construction with frame of
With ist class hollock wood- 30 thk paneled door shutter.
Door1200X2100 1 2 0.89 2.03 3.61 M2
Total = 3.61 M2 2818.50 10184.37
23 (CPWD, DSR' 21, Item No.-9.9):- Providing and fixing glazed shutters for doors, windows and
clerestory windows using 4 mm thick float glass panes, including ISI marked M.S. pressed butt
(i) With ist class Bhola/ Gamari wood- 30 thk glazed window shutter.
Window W1000X1200 2 12 0.89 1.09 23.28 M2
V 1000X600 1 14 0.89 0.49 6.11 M2
Total = 29.388 M2 2896.60 85124.70
24 (CPWD, DSR' 21, Item No.-9.7 ):- Providing and fixing panelling or panelling and glazing in
panelled or panelled and glazed shutters for doors, windows and clerestory windows (Area 2of
Window W1000X1200 1 12 0.64 0.96 7.37 M
V 1000X600 1 14 0.76 0.36 3.83 M2
Total = 11.20 M2 1897.10 21253.59
25 (CPWD, DSR' 21, Item No.-9.96):- Providing and fixing aluminium sliding door bolts, ISI marked
anodised
a) Sliding (anodic coatingmmX
door bolts-250 not less than grade AC 10 as per IS : 1868),transparent or dyed to
16 mm
1 2 2.00 Nos 260.30 520.60
26 (CPWD, DSR' 21, Item No.-9.97):- Providing and fixing aluminium tower bolts, ISI marked,
anodised (anodicbolt-250mm
9.97.2-a) Tower coating not Xless than grade AC 10 as per IS : 1868 ) transparent or dyed to
10 mm
3 2 6.00 Nos 104.40 626.40
27 (CPWD, DSR' 21, Item No.-9.100):- Providing and fixing aluminium handles, ISI marked,
anodised (anodic coating-125
a) Door/ handle-9.100.1 not mm
less than grade AC 10 as per IS : 1868) transparent or dyed to
2 2 4.00 Nos 60.05 240.20
28 (CPWD DSR 2021 ITEM NO.9.48):- Providing and fixing M.S. grills of required pattern in frames
of windows
M.S. etc.
flat = 20 mm with
X 5M.S.
mmflats, square or round bars etc. including priming coat with approved
Window- W1200X1350 1 12 0.89 1.09 11.64 M2
V1000X600 1 14 0.89 0.49 6.11 M2
17.747 M2
,@ 15.00 Kg /sqm Kg 197.70
266.20 52627.54
29 (CPWD DSR 2021 ITEM NO.12.1):-Providing corrugated G.S. sheet roofing including vertical /
curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with
Roofing sheets 1 2 16.43 4.15 136.37 M2
Total = 136.37 M2 978.00 133368.88
30 (CPWD DSR 2021 ITEM NO.12.4):- Providing ridges or hips of width 60 cm overall width plain
G.S. sheet fixed with polymer coated J or L hooks, bolts and nuts 8 mm dia G.I. limpet and
Ridgings 1 1 16.43 16.43 Rm 750.85 12336.47
31 (CPWD DSR 2021 ITEM NO.10.16):- Steel work in built up tubular (round, square or
rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and
applying a priming coat of approved steel primer, including welding and bolted with special
shaped washers etc. complete. -10.16.2 Hot finished seamless type tubes kg
32 (CPWD DSR 2021 ITEM NO.10.1):- Structural steel work in single section, fixed with or without
connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of
Hall ceiling peripheri 30X5 ISA- L/S 1 2 15.00 2.20 kg/m 66.00 kg
Hall perpheri 30X5 ISA-S/S 1 2 6.00 2.20 kg/m 26.40 kg
Intermediate cross tee 30X30x4-L/S 1 4 15.00 1.80 kg/m 108.00 kg
Intermediate cross tee 30X30x4-S/S 1 12 6.00 1.80 kg/m 129.60 kg
Total = 330.00 kg 93.05 30706.50
33 (CPWD DSR 2021 ITEM NO.12.26):- Providing and fixing plain multipurpose cement
board(Hight pressure steam cured) with suitable screws for cement particle board in ceiling
Hall ceiling 1 1 15.00 6.00 90.00 M2
Total = 90.000 M2 773.40 69606.00
34 (CPWD DSR 2021 ITEM NO.13.43.1):- Applying one coat of water thinnable cement primer of
approved brand and manufacture on wall surface .
EXTERNAL wall plaster- L/S 1 2 15.25 3.30 100.65 M2
S/S 1 2 6.25 3.30 41.25 M2
Gable ends 0.5 2 6.23 0.90 5.61 M2
Chajja- W1200X1350 2 12 1.50 0.60 21.60 M2
Less Door -1200X2100 -0.5 2 1.20 2.10 -2.52 M2
Less window W1000X1200 -0.5 14 1.00 1.20 -8.40 M2
Total = 158.19 M2 64.45 10195.15
35 (CPWD DSR 2021 ITEM NO.13.111.1):- Finishing walls with Acrylic Smooth exterior paint of
required shade . Old work (Two or more coat applied @ 1.67 ltr/10 sqm on existing cement
Wall L/S 1 2 15.23 3.30 100.52 M2
Wall S/S 1 2 6.23 3.30 41.12 M2
Gable ends 0.5 2 6.23 0.90 5.61 M2
Chajja- W1000X1200 2 12 1.30 0.60 18.72 M2
Less Door -1200X2100 -0.5 2 1.20 2.10 -2.52 M2
Less window W1000X1200 -0.5 12 1.00 1.20 -7.20 M2
Total = 156.24 M2 111.60 17436.72
36 (CPWD DSR 2021 ITEM NO.13.39:- Colour washing such as green, blue or buff to give an even
shade :13.39.1 New work (two or more coats) with a base coat of white washing with lime 2
Quantity as above internal plastering+ceiling 205.59 M 44.25 9097.49
37 (CPWD DSR 2021 ITEM NO.13.50):- Applying priming coat: 13.50.1 With ready mixed pink or
Grey primer of approved brand and manufacture on wood work (hard and soft wood)
Door1200X2100 2 2 1.20 2.10 1.30 13.10 M2
Window W1000X1200 2 12 1.00 1.20 0.50 14.40 M2
V1000X600 2 14 1.00 0.60 0.50 8.40 M2
Total = 35.90 M2 61.45 2206.30
38 (CPWD DSR 2021 ITEM NO.13.61):- Painting with synthetic enamel paint of approved brand
and manufacture to give an even shade : 13.61.1 Two or more coats on new work
Quantity as above wood primer 35.90 M2 131.45 4719.58
39 (CPWD DSR 2021 ITEM NO.13.50):- Applying priming coat: 13.50.3 With ready mixed red oxide
zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel
Window W1000X1200 1 12 0.86 1.06 10.94 M2
V900X600 1 14 0.86 0.46 5.54 M2
Roof truss= Tie beam 65# (M) 1 4 6.23 0.236 5.88 M2
Rafter 65# (M) 2 6 4.10 0.236 11.61 M2
King post 65 #(M) 1 4 0.90 0.236 0.85 M2
Queen post 65# (M) 2 4 1.20 0.236 2.27 M2
Prince 65# (M) 2 4 0.30 0.236 0.57 M2
Princess 65# (M) 1 4 1.08 0.236 1.02 M2
Purlin 40# (M) 4 2 16.25 0.236 30.68 M2
40 (CPWD DSR 2021 ITEM NO.13.61):- Painting with synthetic enamel paint of approved brand
and manufacture to give an even shade : 13.61.1 Two or more coats on new work
Quantity as above wood primer 70.30 M2 131.45 9240.28
Total cost of works as per CPWD DSR'21 and old Board Approved rate =Rs. 1975573.00
Add extra for GST increment from 12% to 18% with increment multiplying factor (0.2127-
0.1405)=0.0722 over the above amount excluding CPOH 15% = Rs. 124032.00
Add for Price escallation as per Notification of Spl. Director General (R.G), CPWD,
Guwahati No.17(6)/Spl.D.G(R.G.)/Ghy/Works/Vol-II/ 2021/1779(H) dtd.06-08-
2021 @ 20% over the above amount= Rs. 419921.00
Sub total=Rs. 2519526.00
Add for labour welfare cess @1% over above amount= Rs. 25195.26
Total estimated value for 90.00 sqm=Rs. 2544721.00
Chemical House, Laboratory, water works office and Back Wash Water
4 Rs. 8813947.60
Tank
5 Mechanical & Electrical Installation Work in the Treatment Plant Rs. 4577114.00
6 Mechanical & Electrical Installation Work in the Chemical House Rs. 1597630.00
Grand Total cost for 3.6 MLD (in 16 Hrs Operation) Treatment Plant Rs. 32562268.24
0
5.33.1 All works upto plinth leve 0
Concrete of M30 grade with minimum cement
content of 350 kg /cum Cum 8599.35 24.29 208878.21
5.33.2 All works above plinth level upto floor V level 0
Concrete of M30 grade with minimum cement
content of 350 kg /cum Cum 10221.7 45.52 465291.78
Reinforced cement concrete work in walls (any
thickness), including attached pilasters, buttresses,
plinth and string courses, fillets, columns, pillars,
piers, abutments, posts and struts etc. above plinth
level up to floor five level, excluding cost of
centering, shuttering, finishing and reinforcement :
0
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)
derived from natural sources : 3 graded stone
aggregate 20 mm nominal size derived from
natural sources)
Cum 10185.05 4.84 49295.64
5 5.9 Centering and shuttering including strutting,
propping etc. and removal of form for- 0
5.9.1 Foundations, footings, bases of columns, etc. for
mass concrete Sqm 307.95 13.31 4098.81
5.9.6 Columns, Pillars, Piers, Abutments, Posts and
Struts Sqm 804.25 73.98 59498.42
0
10.6.1 10.6.1 80x1.25 mm M.S. laths with 1.25 mm thick
top cover Sq.m. 3008.8 2.1 6318.48
0
0.4243 Fixing with 15 x 3 mm lugs 10 cm long embedded
in cement concrete block 15 x 10 x 10 cm of CC
1:3:6 )1 cement : 3 coarse : sand : 6 graded stone
aggregate 20 mm nominal size)
Kg 175.65 100.8 17705.52
17 4.17 Making plinth protection 50mm thick of cement
concrete 1:3:6 (1 cement : 3 coarse sand (zone-III)
derived from natural sources : 6 graded stone
aggregate 20 mm nominal size derived from
natural sources) over 75mm thick bed of dry brick
ballast 40 mm nominal size, well rammed and
consolidated and grouted with fine sand, including
necessary excavation, levelling & dressing &
finishing the top smooth.
0
20.3.2 (iii) 400 mm dia Rm 3178 450 1430100
Free standing pile portion ( avr. 3.0m) Rm 3178 0 0
0
d) Pile Dia 400 mm Each 2433.8 45 109521
20 5.22.6 Steel reinforcement for R.C.C. work including
straightening, cutting, bending, placing in position
and binding all complete upto plinth level.- 5.22.6
Thermo-Mechanically Treated bars of grade Fe-
500D or more.
Qtl 8965 78.7 705545.5
21 20.6 Vertical load testing of piles in accordance with IS
2911 (Part IV) including installation of loading
platform by Kentledge/Anchor piles method and
preparation of pile head or construction of test cap
and dismantling of test cap after test etc. complete
as per specification & the direction of Engineer in-
charge. Note: 1. Initial and Routine Load Test shall
not be carried out by Dynamic method of testing.
Note: 2. Testing agency shall submit the design of
loading platform for the approval of Engineer-in-
charge. 20.6.1 Single pile upto 50 tonne Safe
capacity 20.6.1.1 Initial test (Test Load 2.5 times
the Safe capacity) per test 51510.60
Sl. Item Sub Head No. Length Bredth Height Quantity Unit Rounded up Qty.
1 Earth Work in Excavation
For the CWR 1 10.80 m. dia. 4.05 370.83 Cu.m.
Total 370.83 Cu.m. 370.83 Cu.m.
2 Extra for addl. Depth
From 2.0 to 3.0 m. 1 10.80 m. dia. 2.05 187.70 34.6
From 3.0 to 4.0 m. 1 10.80 m. dia. 1.05 96.14
From 4.0 to 4.25 m. 1 10.80 m. dia. 0.05 4.58
Total for Addl. Depth = 288.42 Cu.m. 288.42 Cu.m.
4 PCC WORK
Gross area for outer periphery 1 10.00 m. dia. 0.10 7.85 Cu.m.
Net Total area = 7.85 Cu.m. 7.85 Cu.m.
8 Form Work
8.1 Foundation etc.
Base Slab 1 10.60 m. O/D 0.40 13.31 Sq.m. 13.31 Cu.m.
6.6 Walls
Outer face 1 9.00 m. O/D 4.15 117.28 Sq.m.
Inner face 1 8.50 m. I/D 4.00 106.76 Sq.m.
Total Form work in Wall etc. = 224.04 Sq.m. 224.04 Sq.m.
8 20 mm CC Topping
Tank Floor 1 8.50 m. dia. 56.72 Sq.m. 56.72 Sq.m.
9 Plastering 10 mm.
Column 4 0.30 0.30 3.30 15.84 Sq.m.
Tank Roof Beam
Sides 8 7.95 0.20 12.72 Sq.m.
Soffit 4 7.95 0.30 9.54 Sq.m.
CWP Rm Roof Beam
Sides 8 3.00 0.25 6.00 Sq.m.
Soffit 4 3.00 0.30 3.60 Sq.m.
Lintel
11 Reinforcing Steel :
1.3 % of the gross volume of concrete = 7124.87 Kg
Add 10 % for laps / wastage etc. = 712.49 Kg
Grand total = 7837.36 Kg. 78.37 Qtl.
12 Plinth Protection
For Base of the CWR 1 10.20 m. O/D
18.09 Sq.m. 18.1 Sq.m.
1 9.00 m. I/D
15 GI Water Stopper
At junction of Base Slab &
Wall 1 8.75 m. dia 27.48 Rm
At 1.5 m. height of the Wall
1 8.75 m. dia 27.48 Rm
Total Length = 54.95 Rm. 54.95 Rm.
21 CI Puddle Flange
(a) Inlet 1 1.00 No
(b) Outlet 1 1.00 No
(c) Overflow 1 1.00 No
Total = 3.00 Nos 3.00 Nos
21 CI Lugs
On Wall of the Tank 13 13.00 Nos 13.00 Nos
22 Reinf in Pile
Verticals 16 # 360 10.60 3816.00 Rm
Wt. @ 1.58 Kg/m. = 6029.28 Kg.
Ring 8 # ### 1.26 m. 3748.50 Rm
Wt. @ 0.39 Kg/m. = 1461.92 Kg.
Total Wt. = 7491.20 Kg.
Add 5 % for lapping & wastage etc. = 374.56 Kg.
Grand total of Reinforcement in pile = 7865.75 Kg.
Taxes and dutie and transportation charge 1 No @ Rs. 2850.00 = Rs. 2850.00
2) Labour charge @ 20 % = Rs. 712.50
5553.45
Total amount of civil, water supply, sanitary & electrical cost = Rs. 34065.67
7153.79
Grand total cost per SQM of G.F. plan area 41219.47
ANNEXURE-J
DETAILED ESTIMATE FOR SECURITY WALL AND GATE AT TREATMENT PLANT SITE OF BADARPUR
TOWN WATER SUPPLY SCHEME
DSR SOR
Sl. Item description Unit Rate (Rs) Quattity Amount (Rs)
21
1 2.8 Earth work in excavation by mechanical
means (Hydraulic excavator) / manual
means in foundation trenches or drains
(not exceeding 1.5 m in width or 10 sqm on
plan), including dressing of sides and
ramming of bottoms, lift upto 1.5 m,
including getting out the excavated soil and
disposal of surplus excavated soil as
directed, within a lead of 50 m.
8364.20
5.2 Reinforced cement concrete work in walls
(any thickness), including attached
pilasters, buttresses, plinth and string
courses, fillets, columns, pillars, piers,
abutments, posts and struts etc. above
plinth level up to floor five level, excluding
cost of centering, shuttering, finishing and
reinforcement :
10185.05
6 5.9 Centering and shuttering including
strutting, propping etc. and removal of form
for-
5.9.1 Foundations, footings, bases of columns,
etc. for mass concrete Sqm 307.95 58.88 18132.10
5.9.5 Lintels, beams, plinth beams, girders,
bressumers and cantilevers Sqm 608.35 126.00 76652.10
5.9.6 Columns, Pillars, Piers, Abutments, Posts
and Struts Sqm 804.25 271.40 218273.45
5.9.21 Lintels, beams, plinth beams, girders,
bressumers and cantilevers with water Sqm 699.45 151.20 105756.84
proof ply 12 mm thick
7 6.4 Brick work with common burnt clay F.P.S.
(non modular) bricks of class designation
7.5 in superstructure above plinth level up
to floor V level in all shapes and sizes in :
6.4.1 Cement mortar 1:4 (1 cement : 4
coarse sand)
6.4.1 Brick work upto plinth level. Sqm 8512.10 18.63 158580.42
6.13.1 Cement mortar 1:3 (1 cement :3 coarse Sqm 1043.10 415.80 433720.98
sand)
13.2 15 mm cement plaster on the rough side of
single or half brick wall of mix : 13.2.1:- 1:4
(1 cement: 4 fine sand)
6 RCC in Fdn
For Ftng. 92 0.8 0.8 0.2 11.78 Cu.m.
92 1/3h1x[A1+A2+(A1xA2)0.5] 0.05 Cu.m.
For Grade Beam 90 2.8 0.23 0.25 14.49 Cu.m.
Total RCC in Fdn= 26.32 Cu.m. 26.32
15 Extra for Exterior plastering fair side plaster + rough side plaster = 1069.20 Sq.m. 1069.20
21 Reinforcing Steel
@ 1.0 % volume of the Gross RCC work (abstracted from design file) = 0.54 Cu.m.
Weight @ 7850 Kg/Cu.m. = 4234.29 Kg
= 42.34 Qtl 42.34
22 Raising low site of the trea 1 45.0 90.0 1.20 4860.00 cum 4860.00
with 250 W SV lamp, including all taxes and Duties 1.00 No. @ Rs. 6500.00 = Rs. 6500.00
b) Cost of 40 mm dia 3.0 m long GI (H) pipe post with
clamping devices including all taxes and Duties 1.00 Set @ Rs. 2885.00 = Rs. 2885.00
c) Cost of 6.0 mm2 PVC insulated wire (in Loop for
connecting at least 4 such lamp) through PVC flexible
conduit laid below GL, including all taxes and Duties, and
including cost of necessary earth work 6.00 Rm. @ Rs. 475.00 = Rs. 2850.00
d) Cost of PCC base of size 400 mm x 400 mm x 75 mm
deep below GL. including cost of necessary earth work 1.00 Job @ Rs. 1000.00 = Rs. 1000.00
Sub total = = Rs. 13235.00
e) Sundries @ 2 % = Rs. 264.70
f) T&P (LS) = Rs. 25.00
Sub total = = Rs. 13524.70
g) Add Contractor's Proffit and Over Head Exenditure 10 % = Rs. 1352.47
Sub Total = Rs. 14877.17
Add 18 % GST = Rs. 2434.45
Grand Total = = Rs. 17311.62
Say, = Rs. 17312.00
width / m. length
Add for Price escallation as per Notification of Spl. Director General (R.G), CPWD, Guwahati
No.17(6)/Spl.D.G(R.G.)/Ghy/Works/Vol-II/ 2021/1779(H) dtd.06-08-2021 @ 21% over the 1877000.00
above amount= Rs.
Sub Total -1 = 10815095.76
Total of analysed Item of Works = 23949.00
Add 18 % GST on analysis item 4310.82
Sub Total-2 = 28259.82
Grand Total cost for 500.00 m long road (1+2) =Rs 10843355.58
Road length= 500 m, Road top width= 5.76m; Filling depth = 1.50m ; Road base with = 8.76m
5 Laying and spreading of Granular materia 1 500.00 3.75 0.30 562.50 Cu.m. 562.50
7 Concrete Pavement (300 mm tk.) 1 500.00 3.75 0.20 375.00 Cu.m. 375.00
Analysis of rate for non schedule Item ( 300 mm dia RCC pipe NP4)
a) 82.5 KVA- 3 PHASE - Approx size - 3240 mm x No. 1.00 1018126.00 1018126.00
1440 mm x 1585 mm - Approx Wt 1950 Kg.,
COOLING - W/C. (Rate as per Item 41.1.1.42 of
APWD Schedule plus escallation @ 5 % per annum
since 2013-14)
2 PCC Padding for the Generator (@ 5 % Cost of the Job 1.00 50906.30 50906.30
Generator)
3 Changeover Control Panel including connection Cable Job 1.00 101812.60 101812.60
& other Accessories (@ 10 % Cost of the Generator)
Item - : Starter for the Electrical Motor for the above Pump
a) Soft Starter for the Drive Motor for the above pump
including cost of connection cable 1 No. @ Rs. 46368.00 = Rs. 46368.00
b) T & P (LS) = Rs. 50.00
c) Labour charge for fitting, fixing of the pump set on board
of the barge @ 10 % cost of starter = Rs. 4636.80
Sub Total = Rs. 51054.80
d) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 5105.48
Total Cost = = Rs. 56160.28
Say, = Rs. 56160.00
Item - : Earthing
a) Cost of Earth Strip 15 Rm @ Rs. 210.00 = Rs. 3150.00
b) Cost of Copper plate Earthing 1 No @ Rs. 16522.50 = Rs. 16522.50
c) Connection cable and nuts bolts etc. 10 Rm @ Rs. 275.00 = Rs. 2750.00
d) T & P (LS) = Rs. 50.00
e) Labour charge for fitting, fixing @10 cost of nmaterials = Rs. 2242.25
Sub Total = Rs. 24714.75
f) Contractor' profit and over head @ 10 % of above labour charge only = Rs. 2471.48
Total Cost = = Rs. 27186.23
Say, = Rs. 27186.00
Item - : 3.5 core cable for connecting the pump starter with main control panel
a) Cost of Cable 1 RM @ Rs 850.00 = Rs. 850.00
b) Cost of Glands etc. @ 10% of the above = Rs. 85.00
Sub Total = Rs. 935.00
c) Contractor's profit & overhead @ 10% of the above = Rs. 93.50
Total = Rs. 1028.50
Say, = Rs. 1029.00
ANNEXURE-P
DETAILED ESTIMATE FOR MANIFOLD TYPE COMMON HEADER AT TREATMENT PLANT FOR
THE CLEAR WATER MAIN FOR CONNECTING THE SAME WITH THE CLEAR WATER PUMPS.
Sl. Description of Works Unit Rate Quantity Amount
1 (Market rated item):- 400 mm dia. x 2.0 m. long manifold type
M.S. fabricated common header with 2 nos. 125 mm dia., 300
mm long flanged inlets and one 200 mm dia. 400 mm long
flanged outlet (barrel fabricated out of 10 mm Tk. plate and
Flanges fabricated out of 12 mm Tk. plate), for connecting
delivery ends of both the Clear Water Pump set at clear water
pump house to one 200 mm dia clear water riser main,
including all necessary supporting structures, clamping
devices, jointing materials etc. and including connecting and
hooking up of the same with the raw water pumps & the riser
main including all necessary appurtenances etc., all complete,
as directed and specified.
2 Shuttering and shoring upto 1.5 m 1 1.20 1.20 1.5 7.200 Sq.m. 7.20
3 Shuttering and shoring from 1.5 to 1 1.20 1.20 0.675 3.240 Sq.m. 3.24
8 Reinforcing steel
1.0 % of Gross vo;lume of concrete 0.007 Cu.m.
Weight @ 7850 Kg/ Sq.m. = 51.182 Kg
= 0.512 Qtl. 0.51
Materials Required :
8 mm plate for common header = 251.4198 Kg.
8 mm plate for inlet = 31.058 Kg.
8 mm plate for outlet = 25.635 Kg.
te for lange &blank flange of common header = 241.56 Kg.
12 mm plate for blank flange of inlet = 22.18 Kg.
12 mm plate for blank flange of outlet = 15.10 Kg.
Total = 586.95 Kg.
wastage etc. @ 10% of above = 58.70 Kg.
Total Weight = 645.6 Kg., Say. 646.0 Kg.
a) Cost of MS Plate @ Rs. 95.50 Per Kg = Rs. 61693.00
b) Machining & Febrication charge @ Rs. 35.00 Per Kg = Rs. 22610.00
Page-81 of 121
Sl. Item No. L B H Qty Unit R/o Qty
c) Transportation of Manifold from Workshop to work site (L.S.) = Rs. 500.00
d) Hire Charge of Crane for lifting and placing the Common Header on Pade= Rs. 1000.00
e) Skilled labour = 1.0 Nos. @ Rs. 750.00 Per Kg = Rs. 750.00
f) Ordinary Labour = 1 No. @ Rs. 500.00 Per Kg = Rs. 500.00
g) Supervisor = 1 Nos. @ Rs. 1000.00 Per Kg = Rs. 0.00
h) 3 mm. thick Permanent Ruber Gasket @ Rs. 195.00 Per Kg = Rs. 3900.00
i) Machine Made Nuts & Bolts (TVS) wi @ Rs. 155.00 Per Kg = Rs. 1860.00
j) T & P (L.S.) = Rs. 50.00
Total = Rs. 92863.00
g) Sundries viz., Manila Rope, . @ 2 % = Rs. 1857.26
Total = Rs. 94720.26
Tax etc. @ 5.0 % = Rs. 4736.01
Total = Rs. 99456.27
Add Contractor's profit & Overhead @ 10 % = Rs. 9945.63
Grand Total = Rs. 109401.90
Say, Rs. 109402.00
Page-82 of 121
(ANNEXURE-Q )
DETAILED ESTIMATE FOR THE CLEAR WATER PUMPING MAIN
(INCLUDING COST OF PIPE,VALVES, SPECIALS & OTHER APPURTENANCES) OF RAHA
TOWN WATER SUPPLY SCHEME
SL. Description of
No. work No. Length Breadth Depth Quantity Unit Rate (Rs.) Amount (Rs.)
A)Flanged Adopter
2 laying & Jointing of Pipe 100 dia pipe = 0.0 RM 0.000 Rm 0.00
150 dia pipe = 0.0 RM 0.000 Rm 0.00
200 dia pipe = 0.0 RM 0.000 Rm 0.00
250 dia pipe = 50.0 RM 50.000 Rm 50.00
300 dia pipe = 0.0 RM 0.000 Rm 0.00
5 Sluice Valve
100 dia valve 0 0 Nos 0.00
150 dia valve 0 0 Nos 0.00
200 dia valve 0 0 Nos 0.00
250 dia valve 1 1 Nos 1.00
300 dia valve 0 0 Nos 0.00
6 NRV
100 dia valve 0 0 Nos 0.00
150 dia valve 0 0 Nos 0.00
200 dia valve 0 0 Nos 0.00
250 dia valve 1 1 Nos 1.00
300 dia valve 0 0 Nos 0.00
9 Valve Chamber
for Sluice Valves only 1 1.00 Nos. 1
Rounded
Sl. Item No. L B H Qty Unit up Qty
2 Shuttering and shoring upto 1.5 m 1 1.8 1.8 1.5 10.800 Sq.m. 10.80
3 Shuttering and shoring from 1.5 to 3.0 m 1 1.8 1.8 0.675 4.860 Sq.m. 4.86
6 Reinforcing steel
1% of Gross vo;lume of concrete 0.011 Cu.m.
Weight @ 7850 Kg/ Sq.m.
86.664
= Kg
= 0.867 Qtl. 0.87
Rounded
Sl. Item No. L B H Qty Unit up Qty
2 Shuttering and shoring upto 1.5 m 1 1.5 1.5 1.5 9.000 Sq.m. 9.00
5 Bk. Work in Sub Structure 4 1.23 0.23 1.8 2.037 Cu.m. 2.04
7 Reinforcement
0.8% of Gross vo;lume of concrete 0.003 Cu.m.
Weight @ 7850 Kg/ Sq.m. = 20.096 Kg
= 0.201 Qtl. 0.20
i) 15 mm thick plaster
d) In cement mortar 1:4 Sqm 60.55 2895.21 175304.97
13.25 Extra for plastering: 13.25.1 Spherical
ceiling Sqm 146.65 1604.88 235355.65
13.22 Extra for plastering exterior walls of height
more than 10 m from ground level for every
additional height of 3 m or part thereof. Sqm 72.80 4034.34 293699.95
Add extra for GST increment from 12% to 18% with increment multiplying factor
(0.2127-0.1405)=0.0722 over the above amount excluding CPOH 15% 2467023.00
Add for Price escallation as per Notification of Spl. Director General (R.G), CPWD,
Guwahati No.17(6)/Spl.D.G(R.G.)/Ghy/Works/Vol-II/ 2021/1779(H) dtd.06-08-2021 @
21% over the above amount
8769959.00
Sub Total = (1)= 50531668.52
Total items of analysis 1028600.67
Add GST on analysis items 185148.12
Sub Total = (2)= 1213748.79
Total =(1+2)= 51745417.00
Sl. Item Sub Head No. Length Bredth Height Quantity Unit R/O Qty.
1 Earth Work in Excavation
For the ESR 1 15.0 outer dia 1.9
278.254 Cum. 751.410 Cum.
1 6.2 inner dia 1.9
4 PCC WORK
Below Pile Cap 10 9.950 Sq. m. per cap 0.10 9.950 Cum.
Below Grade Beam 10 0.585 0.80 0.1 0.468 Cum.
Total = 10.418 Cum. 28.1 Cum.
5 RCC Work :
Roof Dome 12.5 m rd. of sphare
1 0.150 29.438 Cum.
2.5 m rise of dome
Top Ring beam circular 1 15.45 m. Av dia 0.45 0.3 6.549 Cum.
Tank Wall 1 15.175 m. Av dia 0.175 2.10 17.511 Cum.
Bottom Ring beam circular 1 15.80 m. Av dia 0.80 0.50 19.845 Cum.
Cantilever deck 1 17.300 m. Av dia 0.70 0.125 4.753 Cum.
Conical Dome 1 11.25 m. Av dia 3.536 0.35 43.712 Cum.
Bottom Dome 7.25 m rd. of sphare
1 0.250 22.765 Cum.
2.00 m rise of dome
Ring Girder circular 1 10.0 m. Av dia 0.80 1 25.120 Cum.
Columns 10 0.45 0.45 18.20 36.855 Cum.
Bracing Beam 60 2.690 0.400 0.50 32.280 Cum.
Pile cap 10 8.74 Sq. m. per cap 0.60 52.440 Cum.
6 Form Work
6.1 Foundation etc.
Pile cap 10 8.74 m. peri / Cap 0.60 52.440 Sqm.
Grade Beam 20 0.584 0.700 0.600 7.008 Sqm.
Total Form work in Fdn. = 59.448 Sqm. 160.4 Sqm.
Bracing Beam
Sides 120 2.690 0.50 161.400 Sqm.
Soffit 60 2.690 0.400 64.560 Sqm.
Total Form work in Beam etc. = 465.688 Sqm. 1257.4 Sqm.
6.7 Domes
7 25 mm CC Topping
Bottom Dome 1 91.060 Sqm.
Conical Dome 1 11.25 m. Av dia 3.5355 124.89274 Sqm.
Total CC work in topping = 215.953 Sqm. 583.2 Sqm.
8 CC Skirting
On Inner Faces of Wall 1 15.00 dia 2.900 136.590 Sqm. 368.8 Sqm.
9 Plastering
Column 10 0.45 0.00 0.45 0.00 18.20 327.600 Sqm.
Top Ring beam circular
Outer side of circular beam 1 15.90 dia 0.3 14.978 Sqm.
Soffit of circular Beam 1 15.763 dia 0.275 0.000 13.611 Sqm.
Top of Circular Beam 1 15.699 dia 0.201 9.896 Sqm.
Bottom Ring beam circular
Outer side of circular beam 1 16.60 dia 0.375 19.547 Sqm.
Soffit of circular Beam 1 16.447 dia 0.305 0.000 15.753 Sqm.
Top of Beam & cantilever 1 16.675 dia 1.325 69.376 Sqm.
Soffit of Cantilever 1 17.30m. Av dia 0.700 38.025 Sqm.
Edge of Cantilever 1 18.00 dia 0.100 5.652 Sqm.
Cylindrical Wall
Outer face 1 15.35 dia 2.100 101.218 Sqm.
Ring Girder circular
Outer side of Beam 1 10.800 dia 1.00 67.824 Sqm.
Inner side of Beam 1 9.200 dia 1.00 57.776 Sqm.
Soffit of circular Beam 1 10.000 dia 0.800 0.000 50.240 Sqm.
Bracing Beam
Sides 120 2.690 0 0.50 161.400 Sqm.
Soffit 60 2.690 0 0.400 0 64.560 Sqm.
Top 60 2.690 0.400 64.560 Sqm.
Roof dome 2 (both top & Bottom) 392.500 Sqm.
Soffit of Conical Dome 1 11.25 m. Av dia 3.536 124.893 Sqm.
Soffit of Bottom Dome 1 91.060 Sqm.
Total plastering = 1690.469 Sqm. 4564.3 Sqm.
12 Reinforcing Steel :
2.7 % of the gross volume of concrete = 62254.20 Kg
Add 5 % for laps / wastage etc. = 3112.710 Kg
Grand total = 65366.91 Kg. 1765.0 Qtl.
12.1 Extra Lift for Reinforcemenat Same Ratio of RCC Work 536343.9 Kg. 14481.2 Qtl.
13 Plinth Protection
For Base of the ESR 1 13.0 dia 132.665 Sqm. 358.3 Sqm.
15 MS Plate Insert
Weight of 200 x 200 x 12
mm M.S. Plate @ 7850
Kg/m. 58 0.2 0.2 0.012 218.544 Kg
16 GI Water Stopper
At junction of bottom ring
beam & wall 1 15.175 dia 47.650 m.
at 1.5 m. above bottom
ring beam 1 15.175 dia 47.650 m.
at 3.0 m. above bottom
ring beam 0 15.175 dia 0.000 m.
17.2 Ladder
Ladder post ISMC 125 2 18.75 m. height 37.50 Rm
2 3.65 m. height 7.30 Rm
Ladder Bracket ISMC 125 12 3.550 m. long 42.6 Rm
Total ISMC = 87.4 Rm.
@ 12.7 Kg. per m. = 504.19 Kg.
18 Average 200 mm dia DI Class K7 Pipe for inlet, outlet etc. piping arrangement
(a) Inlet Pipe from Base
upto entry point 1 23.400 23.40 m.
(b) Over flow Pipe upto
Base 1 23.400 23.40 m.
(c ) Outlet pipe = 1 20.000 20.00 m.
(d) Drain Pipe 1 18.000 18.00 m.
Total = 84.80 m. 84.8 m.
22 Reinf in Pile
Verticals 16 # 880 12.6 11088.00 Rm
Wt. @ 1.58 Kg/m. = 17519.04 Kg.
Ring 8 # 4200 1.3 m. 5275.20 Rm
Wt. @ 0.39 Kg/m. = 2057.33 Kg.
Total Wt. = 19576.37 Kg.
Add 5 % for lapping & wastage etc. = 978.82 Kg.
Grand total of Reinforcement in pile = 20555.19 Kg. 205.6 Qtl.
Item : Inlet, Outlet, overflow and Wash water draining piping arrangent
1) Considering 10.0 m. length of average 200 mm
dia.DI/DF) pipe : 10.00 Rm. @ Rs. 3767.24 = Rs. 37672.38
2) Cost of Specials viz. Bend, Socket, Reducer etc.
@ 15 % of Pipe Cost = Rs. 5650.86
Total = Rs. 43323.23
3) Labour charge for fitting, jointing, Fixing etc.
Rate analysis:- Supplying and laying of HDPE (PE80) pipe including all specials confirming to
IS 4984 and the specifications, including
(d) 160 mm ODthird
HDPEparty
PE-80inspection,
PN 16 all taxes and duties,
Rate analysis for 1.00 meter pipe
Sl. Particulars Unit Quantity Rate Amount (Rs)
A Base cost as per company price list ( BERELIA make or equivalent)-160
mm dia Rm 1.00 1502.00 1502.00
B Cost of fittings @ 20% of pipe cost L.S 1502.00 20.00% 300.40
Sub-total= 1802.40
C Carriage -Transportation including loading and unloading @ 10% of
above L.S 1802.40 10.00% 180.24
Sub-total= 1982.64
D Labour charge for laying @ 20% of pipe base cost L.S 1502.00 20.00% 300.40
Sub-total= 2283.04
E Water charge @ 1% of above L.S 2283.04 1.00% 22.83
Sub-total= 2305.87
F Add for GST @ 18% of above (multiplying factor 21.27%) L.S 2305.87 21.27% 490.46
Sub-total= 2796.33
G Add for labour welfare cess @ 1% of above L.S 2796.33 1.00% 27.96
Sub-total= 2824.29
H Add for contractor's profit & overhead @ 15% of above L.S 2824.29 15.00% 423.64
Total cost for 1.00 Rmt HDPE pipe of grade PN-16 = 3247.94
(ANNEXURE- T)
DETAILED ESTIMATE FOR TRIAL RUN OF RAHA TOWN WATER SUPPLY SCHEME
1.1 Wages for TP cum Pump Operator (Contractual) 3.00 Nos. 18000.00 54000.00
1.2 Wages for Khalashi cun Watch Man (Contractual) 3.00 Nos. 15000.00 45000.00
1.3 Wages for Casual Labour (Contractual) 6.00 Nos. 12000.00 72000.00
2.1 Wages for Pump operator (Contractual) 1.00 Nos. 18000.00 18000.00
2.2 Wages for Khalashi cun Watch Man (Contractual) 0.00 Nos. 15000.00 0.00
3.3 Fuel for Captive Power Generator @ 5 % of Electrical Energy Charge 12033.00
4 Maintenance of filter unit including Mechanical & Electrical Installation Work etc. 11355.05
@ 0.25% of above
Say, 465557.00