Professional Documents
Culture Documents
86_4201236450-CR-Commissioning Report 18-Feb-2022- KEBQPS1 U5
86_4201236450-CR-Commissioning Report 18-Feb-2022- KEBQPS1 U5
86_4201236450-CR-Commissioning Report 18-Feb-2022- KEBQPS1 U5
Daily
Report #86 Page 1 of 7
Daily Report
For
This page is a record of all revisions of this document. All previous issues are hereby superseded and are to be
destroyed.
CONTRACTOR
Rev Date COMPANY Revision History
Prepared By Reviewed By Approved By
CONTENTS
1. Executive Summary....................................................................................................... 4
2. 3rd Party........................................................................................................................ 4
3. Project Progress ............................................................................................................ 4
4. Health Safety and Environment ..................................................................................... 4
4.1. HSE Statistics................................................................................................................ 5
5. Hazard Table ................................................................................................................. 5
6. Description of Work Scheduled for next Day.................................................................. 6
7. Sub-contractor (of ABB) ................................................................................................ 6
8. Personnel at Site ........................................................................................................... 6
9. Equipment at Site .......................................................................................................... 6
10. Support & Action Required ............................................................................................ 6
11. Risk & Mitigation Plan.................................................................................................... 7
12. Additional tasks in DCS Commissioning. ....................................................................... 7
13. Attachments .................................................................................................................. 7
DCS for BQPS1-Unit-5 ABB AETAD & PKABB
Daily
Report #86 Page 4 of 7
1. Executive Summary
2. 3rd Party
• Fire detector, Fire Suppression panel and MCP installation has been completed. FM-200 cylinders
installation activity is in progress.
3. Project Progress
Project progress details are available in Annexure-A of this report.
are encouraged to submit Hazard reports. No Lost Time Injury due to ABB/ sub-contractors
employed for this particular project till date.
5. Hazard Table
8. Personnel at Site
ABB Italy 2
9. Equipment at Site
Sub-Contractor
13. Attachments
• Annexure-A - Project Schedule Rev C with % work Completed