Professional Documents
Culture Documents
DPR 26-06-2024 E&M (HEI) - Copy
DPR 26-06-2024 E&M (HEI) - Copy
DPR 26-06-2024 E&M (HEI) - Copy
WAPDA: Tarbela
5th Extension Project HEI-HMC JV
Time Temp. (oC) Sun (Yes/No) Rainfall (Heavy, Moderate, Light) Wind (Strong, Medium, Light)
24:00h 25 °C No No Light
General Conditions:
A
Start/ stop
Plant, Eqpt, Labour Hr
time (hrs)
(Idle)
Unit-18: 8:00
1. 18 seats
Welding of draft tube segment 7 has been completed. 8:00-12:00 minibus=1
2. Pick up= 0
Welding of vertical ribs on draft tube remained in progress.
13:00-17:00 3. 30 seats Coaster
Installation of draft tube segment 4 remained in progress. bus=1
4. 25t mobile crane=0
Unit-18 MIV: 5. 60t trailer=0
No activity. 6. SMAW welding
plants=10
Unit- 19: 7. GTAW plants=2
No activity. 8. Electrode oven=1
9. Grinder=4
Unit-19 MIV: 10. Measuring
instruments
No activity. 11. Total station=1
Unit- 20: 12. Manpower= 45
Including,
Installation of spiral case dewatering pipe from EL:324.3m to Labours=23 (Pak.)
EL:326.5m has been completed and its pressure test carried Supervisor=7 (Ch.)
out. Electrician =1 (Ch)
Driver/operator=2
Unit-20 MIV: (Pak)
No activity. HSE=1
Welders=9 (Pak)
Sump pit: Surveyor=2
No activity.
Erection bay:
No activity.
Loading bay:
No activity.
Downstream:
No activity.
Intake:
No activity.
HEI workshop
B 8:00
8:00-12:00
1. 18 seats
Prefabrication of cooling water system, drainage and minibus=0
13:00-17:00 2. 60t trailer=1
dewatering pipes remained in progress (site support work).
3. 10t overhead
Fit up of U-18’s draft tube cone lower segment remained in
crane=1
progress. 4. 25 t mobile
crane=1
5. 4.4t truck crane=1
6. Pickup=0
7. SMAW welding
plant=3
8. GTAW welding
machine=1
9. Electrode oven=1
10. Grinders=5
11. Measuring tape.
12. Air compressor=1
13. Hydraulic jacks
14. Manpower= 26
Including:
Labours=15 (Pak.)
Supervisor=2 (Ch.)
Electricians =2
(1Ch.+1Pak.)
Driver/operator=3
(Pak)
HSE=0 (Pak.)
Welders=2 (Pak)
Storekeeper=2
(Pak.)
Remarks:
Chinese (Office /
09 6 15
Administrative Staff)
Local (Office /
06 6 12
Administrative Staff)
Total: 117
Stoppages in work
No No No No
No
Drawings
Site Instruction
Visitors
NIL
Signatures