Daily Diary / Inspection Report

WAPDA: Tarbela
5th Extension Project HEI-HMC JV

Site Diary: Powerhouse, HEI warehouse Date: 26-06-2024.


Day Shift Start: 08:00hr Day Shift Stop: 17:00hr (HEI)

Time Temp. (oC) Sun (Yes/No) Rainfall (Heavy, Moderate, Light) Wind (Strong, Medium, Light)

06:00h 23°C No No Light

12:00h 40°C Yes No Light

18:00h 31°C Yes No Light

24:00h 25 °C No No Light

General Conditions:

Powerhouse (HEI works)

A
Start/ stop
Plant, Eqpt, Labour Hr
time (hrs)
(Idle)
Unit-18: 8:00
1. 18 seats
 Welding of draft tube segment 7 has been completed. 8:00-12:00 minibus=1
2. Pick up= 0
 Welding of vertical ribs on draft tube remained in progress.
13:00-17:00 3. 30 seats Coaster
 Installation of draft tube segment 4 remained in progress. bus=1
4. 25t mobile crane=0
Unit-18 MIV: 5. 60t trailer=0
 No activity. 6. SMAW welding
plants=10
Unit- 19: 7. GTAW plants=2
 No activity. 8. Electrode oven=1
9. Grinder=4
Unit-19 MIV: 10. Measuring
instruments
 No activity. 11. Total station=1
Unit- 20: 12. Manpower= 45
Including,
 Installation of spiral case dewatering pipe from EL:324.3m to  Labours=23 (Pak.)
EL:326.5m has been completed and its pressure test carried  Supervisor=7 (Ch.)
out.  Electrician =1 (Ch)
 Driver/operator=2
Unit-20 MIV: (Pak)
 No activity.  HSE=1
 Welders=9 (Pak)
Sump pit:  Surveyor=2
 No activity.
Erection bay:
 No activity.
Loading bay:
 No activity.
Downstream:
 No activity.
Intake:
 No activity.

HEI workshop
B 8:00
8:00-12:00
1. 18 seats
 Prefabrication of cooling water system, drainage and minibus=0
13:00-17:00 2. 60t trailer=1
dewatering pipes remained in progress (site support work).
3. 10t overhead
 Fit up of U-18’s draft tube cone lower segment remained in
crane=1
progress. 4. 25 t mobile
crane=1
5. 4.4t truck crane=1
6. Pickup=0
7. SMAW welding
plant=3
8. GTAW welding
machine=1
9. Electrode oven=1
10. Grinders=5
11. Measuring tape.
12. Air compressor=1
13. Hydraulic jacks
14. Manpower= 26
Including:
 Labours=15 (Pak.)
 Supervisor=2 (Ch.)
 Electricians =2
(1Ch.+1Pak.)
 Driver/operator=3
(Pak)
 HSE=0 (Pak.)
 Welders=2 (Pak)
 Storekeeper=2
(Pak.)

Remarks:

General Waste Controlled Waste Contaminated Waste

Description Qty Description Qty Description Qty

Nil Nil Nil Nil Nil Nil

Manpower: EM: HEC-HEI Sub-Contractor (Bureaue-8) Sub-Total

Chinese (Site Staff) 5 14 19

Chinese (Office /
09 6 15
Administrative Staff)

Local (Site + Workshop 0 71 71


Staff)

Local (Office /
06 6 12
Administrative Staff)

Total: 117

Day Works (Ref/title/authority)

Stoppages in work

Weather Employer issues Contractor issues Industrial disputes Other

No No No No
No

Site Instructions/Drawings issued

Drawings

Site Instruction

Visitors

NIL

Signatures

T5C Name: HEI Name: Other Name (if any):


Sign: Sig: Sign: Org:

PICTURES (Mechanical works)


Figure 1: showing the installation of spiral case dewatering pipe at U-20

Figure 2: showing the installation of draft tube elbow at U-18