Professional Documents
Culture Documents
DPR 25-6-2024 E&M (HEI) - Copy
DPR 25-6-2024 E&M (HEI) - Copy
DPR 25-6-2024 E&M (HEI) - Copy
WAPDA: Tarbela
5th Extension Project HEI-HMC JV
Time Temp. (oC) Sun (Yes/No) Rainfall (Heavy, Moderate, Light) Wind (Strong, Medium, Light)
24:00h 25 °C No No Light
General Conditions:
A
Start/ stop
Plant, Eqpt, Labour Hr
time (hrs)
(Idle)
Unit-18: 8:00
1. 18 seats
Welding of draft tube segment 7 remained in progress. 8:00-12:00 minibus=1
2. Pick up= 0
Welding of vertical ribs on draft tube remained in progress.
13:00-17:00 3. 30 seats Coaster
Installation of draft tube segment 5 has been completed. bus=1
Installation of draft tube segment 4 has been started and 4. 25t mobile crane=0
remained in progress. 5. 60t trailer=0
6. SMAW welding
Unit-18 MIV: plants=10
7. GTAW plants=2
No activity. 8. Electrode oven=1
Unit- 19: 9. Grinder=4
10. Measuring
No activity. instruments
Unit-19 MIV: 11. Total station=1
12. Manpower= 45
No activity. Including,
Unit- 20: Labours=23 (Pak.)
Supervisor=7 (Ch.)
Installation of spiral case dewatering pipe from EL:324.3m to Electrician =1 (Ch)
EL:326.5m remained in progress. Driver/operator=2
(Pak)
Unit-20 MIV: HSE=1
Welders=9 (Pak)
No activity.
Surveyor=2
Sump pit:
No activity.
Erection bay:
No activity.
Loading bay:
No activity.
Downstream:
No activity.
Intake:
No activity.
HEI workshop
B 8:00
8:00-12:00
1. 18 seats
Prefabrication of cooling water system, drainage and minibus=0
13:00-17:00 2. 60t trailer=1
dewatering pipes remained in progress (site support work).
3. 10t overhead
Fit up of U-18’s draft tube cone lower segment remained in
crane=1
progress. 4. 25 t mobile
NDT (100% DPT and UT) inspection of U-20’s draft tube cone crane=1
upper segment, carried out jointly by T5C and Contractor’s 5. 4.4t truck crane=1
representative. 6. Pickup=0
7. SMAW welding
plant=3
8. GTAW welding
machine=1
9. Electrode oven=1
10. Grinders=5
11. Measuring tape.
12. Air compressor=1
13. Hydraulic jacks
14. Manpower= 26
Including:
Labours=15 (Pak.)
Supervisor=2 (Ch.)
Electricians =2
(1Ch.+1Pak.)
Driver/operator=3
(Pak)
HSE=0 (Pak.)
Welders=2 (Pak)
Storekeeper=2
(Pak.)
Remarks:
Chinese (Office /
09 6 15
Administrative Staff)
Local (Site + Workshop
0 71 71
Staff)
Local (Office /
06 6 12
Administrative Staff)
Total: 117
Stoppages in work
No No No No
No
Drawings
Site Instruction
Visitors
NIL
Signatures