Professional Documents
Culture Documents
Original analysis
Original analysis
Analysis
2 Cleaning of reinforcement from rust from the DSR - 2019, CPWD, Vol.-2, Item No.-26.29.1
reinforcing bars to give it a total rust free steel
surface by using alkaline chemical rust
remover of approved make with paint brush
and removing loose particles after 24 hours of
its application with wire brush and thoroughly
washing with water and allowing it to dry
including cost of all labour, materials, tools,
taxes etc. all complete as per direction of
Engineer-In-Charge. (Bars upto 12 mm
diameter.)
Detail of cost for 3.00 sqm (95.54 meter
length of 12mm dia bar) Bars up to 12 mm
diameter (1 litre chemical shall cover 3.00
sqm area of bars)
MATERIALS
Chemical Rust Remover Ltr 1.00 200.00 200.00
LABOUR (Application charges for 3.0 sqm)
Painter Day 0.162 461.00 74.68
collie Day 0.162 311.00 50.38
Putty, brush, sand paper LS 3.162 1.73 5.47
Sundries LS 1.980 1.73 3.43
Total 333.96
Add 1% water Charges 3.34
Total 337.30
Add 15 % Contractor's profit and overheads 50.59
Cost for 3.0 sqm (95.54 m length of 12 mm 387.89
bar)
Rate per meter length of Bar 4.06
Add labour cess @1% 0.04
Total 4.10 / Meter
3 Providing & applying Zinc rich epoxy based DSR - 2019, CPWD, Vol.-2, Item No.-26.29.1
primer coat of approved make in two coats on
reinforcement applied as per manufacturer’s
recommendation including cost of all labour,
materials, tools, taxes, all complete. as per
technical specification and as per the direction of
Engineer-in-Charge,
Detail of cost for 3.00 sqm (95.54 meter
length of upto 20 mm dia bar) Bars upto 12
mm diameter (1 litre chemical shall cover 3.00
sqm area of bars)
MATERIALS
Zinc rich epoxy based primer Ltr 1.00 850.00 850.00
LABOUR (Application charges for 3.0 sqm)
Painter Day 0.32 461.00 149.36
collie Day 0.32 311.00 100.76
Putty, brush, sand paper LS 3.16 1.73 5.47
Sundries LS 1.98 1.73 3.43
Total 1109.02
Add 15 % Contractor's profit and overheads 166.35
Cost for 3.0 sqm (95.54 m length upto 12mm 1275.38
bar)
Rate per 1 Meter 13.35
Add labour cess @1% 0.13
Total 13.48 / Rmt
4 Providing and applying solvent free two Approved
components epoxy resin of minimum compressive analysis of
strength 55MPa at 7 days and tensile strength 20 Sagada Work
MPa at 14 days for better bonding between old
and new concrete @ 0.5kg/sqm on prepared
surface of structure with cost of all materials,
equipments, scaffolding, labour charges etc.
including supervision, dewatering if necessary
with all leads, lifts delifts, taxes, duties, cess,
conveyance, loading, unloading etc complete as
per the direction of the Engineer-in-Charge.
Detail of cost for 10 sqm area (0.5cum) Cum 0.50 4866.78 2433.39
M25 concrete 0.5 cum of concrete@
347 kg/cum
Cost of SBR Polymer (@2% of cement 173.50 Kg 3.47 290.00 1006.30
kg = 173.50X2% = 3.3 kg
TOTAL 3439.69
Add 15 % Contractor's profit and overheads 515.95
Total 1273.94
Rate for 1sqm for internal wall 136.98
Add for outer side add 30% on labour for 19.61
scaffolding
Over Head Charges and Contractor's profit @15% 2.94
on extra labour cost
Rate for external wall for 1 sqm 159.53
b Painting on concrete surface providing and
applying two coats of water based cement paints
to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ 1 ltr for 2 sqm
Unit = SQM
Taking output = 10SQM
a) Material
Sikalastic®-560 @ Rs.455/- per KG
Coverage for 10SQM @ 1.6 KG/sqm KG 16 455 7,280.00
b) Labour
HIGH SKILLED LABOUR day 2 461 922.00
Mazdoor day 2 311 622.00
Total 8,824.00
Add Water/Machinary Charrges 1% 88.24
Sub Total 8,912.24
Add 15 % for over Head & Contractor profit 1,336.84
cost of 10 SQM 10,249.08
Rate per 1 SQM 1,024.91
Cess @1% 10.25
say 1,035.16
14 Removing white or colour wash by scrapping and Ref: DAR 2019 Vol II, p 871 It. 14.43
sand papering and preparing the
surface smooth including necessary repairs to
scratches etc. complete
Labour
Belder day 0.09 401.00 36.09
Coolie day 0.04 311.00 12.44
Bhisti day 0.04 351.00 14.04
Sundries such as sand paper and scrapper LS 2.73 1.73 4.72
Repair to scraches LS 1.82 1.73 3.15
Total 70.44
Add 1% for water charges 0.70
71.14
Add overhead charges @7.5% 5.34
Add contractor's Profit @7.5% 5.34
81.82
Add for Cess 1% 0.82
Total for 10sqm 82.64
Total for 1 SQM 8.26