107 SOUTH EAST

PHASE-02
MONTHLY REPORT

SHRIRAM PROPERTIES LIMITED


PROJECT DETAILS

NO OF UNITS COMPOSITION NO OF TOWERS

708 2B+G+14 6

PROJECT STATUS

SUB-STRUCTURE SUPER-STRUCTURE FINISHING

Completed Completed In Progress


PROJECT DETAILS:

Project
Towers Height No of Units
Name

107 SE-2 6 2B+G+14 708

PROJECT STATUS:

No of Scheduled Completion External Present


S.no Tower
Floors Structure Finishing Completion Status
Terrace floor
1 T-7 2B+G+14 Completed In progress completed.

Terrace floor
2 T-8 2B+G+14 Completed In progress completed.
Terrace floor
3 T-9 2B+G+14 Completed In progress completed.
In progress
Terrace floor
4 T-10 2B+G+14 Completed In progress completed.
5 Terrace floor
T-11 2B+G+14 Completed In progress completed.
Terrace floor
6 T-12 2B+G+14 Completed In progress completed.
STRUCTURE PROGRESS

14 14 14 14 14 14 14
14 14 14 14 14 14
12

10

-2
T-7 T-8 T-9 T-10 T-11 T-12

Floors Completed Sub-Structure End

FINISHING PROGRESS

120%

100%

80%

60%
46%
40%
40%

20% 13%
6%
0% 0%
0%
T-7 T-8 T-9 T-10 T-11 T-12

Work Completed
MIVAN MOVEMENT PLAN

Set Status 1st Repetition 2nd Repetition 3rd Repetition 4th Repetition

Set-1 Available T-7 T-9 T-12 T-14


Set-2 Available T-8 T-10 T-5
Set-3 Available T-16 T-11 T-13

PROCUREMENT
Sl Package Status
1 Excavation Awarded
2 Shell & Core Awarded
3 Structural & Lightning Arrestor Earthing Awarded
4 Internal Electrical Awarded
5 Aluminium Formwork Awarded
6 Water proofing Awarded
7 Tile Supply Awarded
8 Tile installation Awarded
9 Granite Awarded
10 Structural steel work Awarded
11 Grills Awarded
12 Painting Awarded
13 False Ceiling Awarded
14 Wooden Doors Awarded
15 Fire /Shaft doors YTA
16 Iron Mongaries / Hardware’s YTA
17 UPVC Windows & Doors Awarded
18 Expansion joint treatment Awarded
19 Duct closure YTA
20 Temporary Grills/Doors Awarded
21 Curtain Wall YTA
22 Civil Infra YTA
23 Electrical fitting / Fixture Awarded
24 Fire Fighting Awarded
25 Lift Awarded
26 Basement/STP Ventilation YTA
27 PHE - CP & Sanitary Awarded
28 PHE - Internal Awarded
29 Pumps YTA
30 Electrical Infra YTA
31 Solar water Heater YTA
Progress Details with Description and brief writeup:

Tower-07
**External Grinding &Hole Packing Work completed&
ExternalPutty work commenced.
** Internal Water proofing,Tiling &MS work completed .
** Doors&windows installation work started
Tower-08
**External Grinding &Hole Packing pending & External Painting
Preparatory work in progress.
Tower-09
Structure Work completed.
Tower-10
Structure Work completed
Tower-11
Structure Work completed
Tower-12
Structure Work completed.
Club House
** Structural Work in Progress.
THANK YOU