POINT DISCUSSED ON ZOOM MEETING HELD ON 27.06.

2024
SL.NO. BUILDING NAME BALANCE WORK REMARKS
There is no access to carry out the materials on
terrace for construction work and also no
1 WEIGHT LIFTING HALL Brick coba of approx 25 sqm area . sufficient space for fixing of scaffolding. Hence,
the item may be descope from NBCC's scope of
work.
There is no sufficient space for installation of
Solar Water Heating System in the building
Installation of Solar Water Heating System
premises. Hence, the item may be descope from
NBCC's scope of work.
There is no sufficient space for installation of
Solar Water Heating System in the building
Installation of PVC water Tank
premises. Hence, the item may be descope from
NBCC's scope of work.

As per BoQ specification the existing septic tank


2 REHAB & RECOVERY CENTER should be cleaned and finished with neat cement
punning and to make a platform in that septic
tank over which the pump will be installed and to
execute this item the existing sewer connection
Installation of Submergible sewarage pump in Septic
have to closed for approx One and half months.It
Tank.
was also discussed in the meeting that the
existing sewar connection & septic tank is
functional now a days and need not required to
install the sewarage pump. Hence, the item may
be descope from NBCC's scope of work.

As per BoQ specifications, the item is not


available in the market as per market survey
AC Works
done by NBCC. Hence, the item may be descope
from NBCC's scope of work
The quantity of 100 mm dia pipe required for fire
3 GUEST HOUSE
hydrant connection has not considered in BoQ. If
the same will execute then the full quantity will
Fire Fighting (Fire Hydrant) Works. be deviate. Also it is informed by ED, NSNIS that
not to execute any items which are going to be
deviated. Hence, the item may be descope from
NBCC's scope of work.
The quantity of 100 mm dia pipe required for fire
hydrant connection has not considered in BoQ. If
the same will execute then the full quantity will
4 MILKHA SINGH HOSTEL Fire Fighting (Fire Hydrant) Works. be deviate. Also it is informed by ED, NSNIS that
not to execute any items which are going to be
deviated. Hence, the item may be descope from
NBCC's scope of work.
The quantity of 100 mm dia pipe required for fire
hydrant connection has not considered in BoQ. If
the same will execute then the full quantity will
5 DHYAN CHAND HOSTEL Fire Fighting (Fire Hydrant) Works. be deviate. Also it is informed by ED, NSNIS that
not to execute any items which are going to be
deviated. Hence, the item may be descope from
NBCC's scope of work.
The quantity of 100 mm dia pipe required for fire
hydrant connection has not considered in BoQ. If
the same will execute then the full quantity will
6 P.T. USHA HOSTEL Fire Fighting (Fire Hydrant) Works. be deviate. Also it is informed by ED, NSNIS that
not to execute any items which are going to be
deviated. Hence, the item may be descope from
NBCC's scope of work.