Dewobroto Canny 2024 Evaluation of the Indonesian Standard Guidelines for Long Span Pc Girder Erection

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Case Study

Evaluation of the Indonesian Standard Guidelines for


Long-Span PC Girder Erection
Wiryanto Dewobroto 1 and Khairina A. Canny 2

Abstract: Road infrastructure development in Indonesia has increased the use of long-span prestressed concrete I-section (PCI) girders for
bridge structures. However, these girders have instability issues during construction that resulted in multiple failures between 2017 and
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

mid-2018. To address this problem, engineers compiled a standard guideline for erecting long-span PCI girders that includes three recom-
mendations: a lifting point or lifting frame, a dapped-end girder, and artificial stiffeners. In late 2022, despite the initial effectiveness of the
guideline, a video revealed that PCI girders were still vulnerable to failure despite strict adherence to the guidelines. A subsequent study
reviewed the guidelines and revealed that not all the guidance was effective. The study emphasized the importance of standardized bracing at
the supports. Therefore, it is necessary to revise and improve the guidelines to prevent similar failures in the future. DOI: 10.1061/PPSCFX.
SCENG-1424. © 2024 American Society of Civil Engineers.
Practical Applications: The process of erecting long-span prestressed concrete I-section (PCI) girders, which are more than 40 m long, is
risky and can lead to toppling and collapsing. The main cause of this risk is the presence of lateral imperfections, which are limited to length or
span of the girder ðLÞ=500 (maximum) due to construction tolerances and the lateral stiffness being relatively small. Therefore, the process of
erection must be carried out carefully and purposefully. To reduce the risk of accidents, a standard guideline for erection (SGE) was created.
However, although the SGE (2018, 2021) has successfully reduced accidents, failures still happen. There are weaknesses in the SGE that need
to be corrected. There are two critical risk stages during the erection of a PCI girder: the hanging and seated conditions. Using a lifting frame,
according to the SGE (2018, 2021), is correct for the hanging stage. However, the seating procedure in the SGE needs improvement. It is vital
to ensure that the strength of the bracing at the supports is standardized and installed correctly before removing the lifting crane. The reasons
for this recommendation are explained in this paper.
Author keywords: Prestressed concrete I-section (PCI) girder; Guidelines; Erection; Imperfection; Failure; Dapped-end; Lifting frame.

Introduction Bocimi Toll Road, Paspro Toll Road, and Ciputrapinggan Bridge
(SGE 2018). These incidents drew attention to serious concerns in
During President Jokowi’s era (2014–2024), Indonesia focused the erection of long-span PCI girders that required immediate
on developing toll road infrastructure, which led to increased attention. If not addressed effectively, these issues would cause
construction projects across the country. Standardized and repeti- public distrust in the government’s ability to execute infrastructure
tive structural systems were adopted to meet the demands of projects successfully.
fast and cost-effective bridge construction. As a result, long-span
prestressed concrete I-section (PCI) girders (L > 40 m) became a
popular option despite their instability issues during construc- Establishment of a Construction Safety Committee
tion. Unfortunately, between 2017 and 2018, there were several
The Ministry of Public Works and Public Housing took steps to
failures during the erection of PCI girders (Effendi 2017;
ensure the success of construction projects. The Ministry formed
Sepriansyah 2017; Ablehg 2018; Bagus 2018; Haryanto 2018),
a special committee of experts to address any construction-related
which confirmed the challenges they present.
issues that arise. The government established the Construction
Safety Committee (CSC) on January 24, 2018. The CSC monitors
Response to Construction Failures and evaluates high-risk construction projects, investigates accidents,
and provides recommendations to ensure safe construction practices.
Anticipating Public Doubts
It is an honor that the first author, representing academics, was in-
In 2017, there were multiple erection failures on several toll roads vited to join this committee.
and bridge projects, such as the Pemalang-Batang Toll Road, The CSC collaborates with all parties involved in infrastructure
projects to identify risky tasks and anticipate potential hazards. The
1
Professor, Dept. of Civil Engineering, Universitas Pelita Harapan, CSC conducts thorough evaluations to ensure safety by rejecting
Tangerang 15811, Indonesia (corresponding author). ORCID: https://orcid unsafe construction methods. By implementing this strategy, the
.org/0000-0002-9773-0581. Email: wiryanto.dewobroto@uph.edu CSC effectively limits unsafe practices and significantly reduces
2
Lecturer, Dept. of Smart Construction and Civil Engineering, Calvin construction-related incidents.
Institute of Technology, Jakarta 10610, Indonesia. Email: khairina.anindya@
calvin.ac.id
Note. This manuscript was submitted on July 4, 2023; approved on Standard Guidelines for Erection and
January 19, 2024; published online on June 18, 2024. Discussion period Recommendations for Construction Aids
open until November 18, 2024; separate discussions must be submitted
for individual papers. This paper is part of the Practice Periodical on Indonesian construction engineering professionals and experts are
Structural Design and Construction, © ASCE, ISSN 1084-0680. concerned about frequent failures in PCI girder erection. These

© ASCE 05024006-1 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


issues could lead to a loss of public trust in the government’s ability The standard guidelines for erection (SGE 2018, 2021) provide
to effectively manage construction projects. If not dealt with guidelines for workers to follow when erecting a long-span PCI
promptly, these issues could also result in a need to rely on foreign girder. One of the changes outlined in the SGE (2018, 2021) when
experts and limit opportunities for local professionals due to politi- lifting with a crane is the use of a lifting point (embedded device) or
cal factors. lifting frame (external device) instead of slings in a single basket
In 2018, the Association of Precast and Prestressed Concrete hitch (Fig. 2).
Companies (APPCC) and the Association of Precast and Pre- The SGE (2018, 2021) goes beyond prescribing a lifting point or
stressed Concrete Experts (APPCE) in Indonesia released a book lifting frame, because it also offers valuable recommendations for
titled, Precast and Prestressed Concrete Beams–PCI Girder specific design modifications to address the risks associated with
Products. The book offers solutions to the challenges of using long-span girders (L > 40 m), thereby minimizing the potential for
PCI girders. It covers various topics, including applications girder rollover incidents. One such recommendation involves incor-
and production of PCI girders and erection procedures for PCI porating a dapped-end girder type (Mattock and Chan 1979).
girders. The book has been well-received and is now the standard The local experts believe that using a dapped-end PCI girder can
guideline for erection (SGE 2018) for contractors and a helpful help reduce the risk of instability during erection. They believe that
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

reference for members of the CSC. the lateral force acting perpendicularly on the top side of a girder is
In 2019, a new publication called SNI 8730:2019 was released. the cause of instability; consequently, making the distance between
This publication provides additional guidelines for occupational the support and the lateral force relatively short will reduce the risk
safety and health in the construction and erection of precast of instability. However, there are no standard guidelines or litera-
concrete girders for bridges (BSN 2019). In 2021, the Ministry of ture to support this recommendation.
Public Works and Housing collaborated with APPCC and APPCE Another new device, artificial stiffeners from steel, has been de-
to release an updated standard guideline for erection (SGE 2021). veloped to make girders more rigid during construction (Fig. 3).
These three publications are a valuable guide for producing and Simple design calculations are used to ensure feasibility (SGE
installing precast and prestressed concrete girders for bridges in 2021). Calculations are made assuming that artificial stiffeners,
Indonesia. Fig. 1 shows the guidebook covers. listed in SGE (2018) and SGE (2021), increase the torsional

Fig. 1. Standard guideline for the erection of PC girders for bridges in Indonesia.

Fig. 2. SGE provisions for lifting PCI girders. (Images courtesy of PT LIMOV Power Structure, Banten, Indonesia.)

© ASCE 05024006-2 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Fig. 3. Application of artificial stiffeners on a PCI girder in Indonesia. (Images courtesy of PT LIMOV Power Structure, Banten, Indonesia.)
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

constant or torsional stiffness (J), or it could be the moment of in- effectiveness of the SGE guidelines in managing risks while install-
ertia of the PC girder in the weak axis (Iy ). Both parameters (J and ing long-span PCI girders.
Iy ) are used in Eq. (6) increase the critical moment, causing lateral
torsional buckling, thereby reducing the risk of instability during
The Reliability of the Standard Guideline Is Questionable
erection. It is important to note that these additional components
also add weight during erection, resulting in unexpected results When the new guidelines were released, the community of construc-
and increasing the risk of failure. tion workers initially experienced a sense of relief, believing that the
SGE (2021) is a valuable guide for installing long-span PCI risk of failures during the installation of long-span PCI girders had
girders thanks to its three innovative features: a lifting point or been solved. However, their confidence was shattered in early 2023
frame, a dapped-end girder, and artificial stiffeners. The SGE with the circulation of a video of an incident in which a long-span
(2018, 2021) has successfully addressed previous concerns PCI girder failed shortly after being placed on its supports (Fig. 4).
regarding construction failures, including the 2017 incident. As The video of the collapse gained widespread attention due to the
a result, construction workers can have greater confidence in the presence of additional compelling evidence. Both the video clip

Fig. 4. Sequence of events from a video showing the erection failure of a PCI girder. (Images courtesy of M. Bimo Septiano.)

© ASCE 05024006-3 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Literature Review on Girder Stability during Erection

Background
There is a lack of comprehensive studies on the stability of PCI
girders during erection in Indonesia. Many practitioners assume
that their stability behavior resembles that of steel I-beams, but this
is not necessarily true. PCI girders have a thicker cross section and
higher torsional stiffness than slender steel I-beams. In order to
make the best decisions, it is crucial to understand the stability
behavior of PCI girders based on existing research.

Girder Modeling for Stability Analysis


Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

PCI girders in all work stages can be modeled under two primary
support conditions: (1) hanging; and (2) seated girders (Fig. 6).
The hanging condition is selected when a girder is lifted from the
top using a wire rope sling attached to the web or flange at its ends.
Fig. 5. Girder collapse seen from the top of the support pier. (Image The seated condition is selected when a girder is supported from
courtesy of J. I. Rastandi.) underneath; this occurs during transportation, storage, or when the
girder is installed and seated on its supports (Mast 1989, 1993;
Stratford and Burgoyne 1999; Venkata 2019).
(Fig. 4) and additional photos (Fig. 5) confirmed that there was In both the hanging and seated cases, stability analysis of a PCI
indeed a problem with installing the PCI girder, leading to the girder focuses on identifying the balanced position. This position
failure. ensures that the forces acting on the roll axis, an imaginary axis
The installation of PCI girders follows the latest standard enabling the girder to rotate as a rigid body, are kept in equilibrium.
guidelines, but failures still occur. The SGE (2018, 2021) recom- By carefully examining and calculating the forces and moments
mendations were followed, including the use of a dapped-end exerted on the girders, engineers can evaluate their stability and
girder type and artificial stiffeners, as seen in the photo of the make well-informed decisions regarding the installation and sup-
collapsed PCI girder. An important finding is that failures still port processes.
occur when carefully following the SGE (2018, 2021). However,
a lifting point, another recommendation in SGE (2018, 2021),
The Equilibrium of a Hanging Girder
can ensure that a girder is successfully lifted and placed on its
supports. The support is flexible when a girder is suspended from a lifting
The collapse is thought to have been due to eccentricity at the point or loop. It is free to roll, because there is no restraint against
support, which caused the girder to rotate along the roll axis parallel girder rotation. In this configuration, a girder can rotate freely due
to the centroid axis of the girder section; the temporary bracing to the absence of restraints. Stratford and Burgoyne (1999) stated
installed was of inadequate strength. Furthermore, it is essential this is the most dangerous condition or stage. The center of rotation,
to evaluate SGE (2021) comprehensively to identify deficiencies which is typically situated on the upper surface of a girder, serves as
and seek improvements. This evaluation is critical in order to pre- a pivotal point where it can rotate as a rigid body. This center point
vent similar incidents in the future so that construction safety can be and the axis passing through it, known as the roll axis, are shown in
ensured. Fig. 6(a).

Fig. 6. Two girder modeling conditions for stability analysis: (a) hanging girder; and (b) seated girder. (Reproduced from Mast 1989, 1993, with
permission.)

© ASCE 05024006-4 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

Fig. 7. Force equilibrium condition in a hanging girder. (Reproduced from Mast 1989, with permission.)

When a PCI girder is in an ideal state, it tends to curve only in state. By analyzing these parameters, engineers can gain a deeper
the vertical plane while in a hanging position. In this condition, the understanding of the factors that influence the stability of a girder
neutral axis of a PCI girder aligns perfectly with the roll axis. On a during the lifting process.
practical level, it is essential to acknowledge that no PCI girder is Mast (1989) proposed various methods for enhancing the
perfect. During production, tolerances for lateral imperfections or stability of a girder in the lifted (hanging) condition, as shown in
sweep must be considered. According to production guidelines Eqs. (1) and (2). These methods encompass the following strategies:
provided by APPCC and APPCE, the maximum allowable sweep 1. The most effective method is shortening the lifting point dis-
tolerance is divide the length of the girder by 500 (L=500). In ad- tance. This strategy can be applied by ensuring appropriate
dition, there is a possibility of eccentricity at the lifting point. Both stress distribution on the upper side of a PCI girder.
sweep and eccentricity contribute to a shift in the centroid of the 2. Additional devices can shift the roll axis upward, further
cross section, causing it to deviate from perfect alignment with the improving stability.
roll axis, as shown in Fig. 7. 3. Increasing the compressive strength of the concrete can
pffiffiffiffiffienhance
Even a minor deviation (represented by the angle θ) from the roll parameter E (elastic modulus), where Ec ¼ 4,700 fc , which
axis tends to give rise to a lateral force component (W sin θ) acting indicates normal concrete [ACI 318M (ACI 2008)].
on the weak axis of the girder. Due to its relatively lower stiffness, 4. Modifying the girder section to increase the stiffness along the
the girder undergoes deformation. This deformation causes the weak axis (Iy ) is another effective method. For a PCI girder, the
angle with the roll axis to increase until equilibrium is established influence of the stiffness of the lower flange component along
progressively. the weak axis is as effective as the influence of the stiffness of
the upper flange. Increasing the size of the lower flange com-
Factor of Safety of a Hanging Girder against Instability ponent is particularly advantageous, because it shifts the cent-
roid of the girder lower, simultaneously increasing both Iy and
According to Mast (1989), the factor of safety (FS) of a hanging
yr . Moreover, the presence of prestressing forces in the lower
girder with regard to rolling stability is directly proportional to the
flange component ensures crack prevention.
distance (yr ) between the centroid of its cross section and the roll
axis, as shown in Fig. 7. The FS is inversely proportional to the
magnitude of the distance between the centroid of the girder cross The Equilibrium of a Seated Girder
section at the support point and that in the middle of the curved
span resulting from deformation along the weak axis. These rela- Fig. 8 illustrates slender beams balanced on elastic supports.
tionships can be expressed using the following equations: The magnitude of the moment arm, represented as ca , is deter-
mined by the self-weight of a girder, which generates moments
yr about its roll axis (Mast 1993); it is obtained using the following
FS ¼ ð1Þ
z̄0 equation:

1 wl4 ca ¼ z̄ cos θ þ ei cos θ þ y sin θ ð3Þ


z̄0 ¼ ð2Þ
120 EI y
where θ = roll angle of the major axis of the girder with respect to
where yr = height of the roll axis above the center of gravity of the vertical; z̄ = lateral deflection of the center of gravity of the curved
beam; z̄0 = theoretical lateral deflection of the center of gravity of arc of the deflected girder; ei = initial eccentricity of the center of
the beam, computed with the full dead weight applied laterally; gravity of the girder; and y = height of center of gravity of girder
E = elastic modulus of the concrete material; Iy = moment of inertia above roll axis.
of the beam in the weak axis; w = component of girder weight In order to ensure stability, it is essential to ascertain that the roll
causing lateral deformation, w ¼ W sin θ; and l = distance from axis of a girder, as shown in Fig. 8, is positioned beneath its center
the lifting point of the hanging girder. of gravity. Stability is achieved by ensuring that a girder supports
The aforementioned equations are considered fundamental and resist the rolling moment, denoted by the parameter K θ. When
do not incorporate the effects of imperfections. However, they play considering M r , the moment about the roll axis due to the elastic
a crucial role in providing information about the key parameters support, the magnitude of the moment arm for resisting the rolling
that determine the stability of a hanging girder when it is in a lifted moment, represented as cr , must be determined. This rolling

© ASCE 05024006-5 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


The critical moment causing LTB can be predicted using the
following formula:

π pffiffiffiffiffiffiffiffiffiffiffiffiffiffi
M cr ¼ EI y GJ ð6Þ
L

where E = elastic modulus of the material; I y = moment of inertia of


the beam in the weak axis; G = shear modulus of elasticity of the
material; J = torsional constant or torsional stiffness of the section;
and L = span of an unbraced section of the beam.
A steel I-beam’s torsional constant or torsional stiffness, J,
depends on the flange’s thickness and web. Compared to a steel
I-beam, a PCI girder typically has thicker dimensions. The in-
creased thickness of a PCI girder leads to significantly higher
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

torsional stiffness, often 100 to 1,000 times greater than that of


Fig. 8. Force equilibrium condition in a seated girder. (Reproduced a steel I-beam. Due to these fundamental differences in torsional
from Mast 1993, with permission.) stiffness, classical LTB theory, which primarily applies to steel
I-beam, has limited applicability to PCI girders. In analyzing and
designing a PCI girder, it is essential to consider other appropriate
theories and design approaches specific to concrete structures.
moment is caused by W, the self-weight of the girder (Mast 1993),
and is obtained using the following equation:
Lateral Torsional Resistance of PCI Girders

cr ¼ ðθ − αÞ ¼ rðθ − αÞ ð4Þ In the seated girder condition, two factors introduce risks to the
W
behavior of PCI girders. The first factor is the presence of lateral
where K θ = stiffness, or rotational spring constant of the elastic imperfections or sweeps in the beam. The second factor is the sup-
support, and is obtained by applying a known rolling moment port rotates, such as eccentricity and soft rubber bearing pads,
and measuring the resulting rotation angle (K θ = the applied rolling which contribute to the deformation of the girder. Consequently,
moment divided by the resulting rotation angle); α = slope angle of the cross section of a PCI girder undergoes deformation at the mid-
the bearing support; and r K θ =W, called the stability radius, is the span, similar to the behavior observed in slender beam sections
height from the center point of the girder due to its self-weight, of LTB.
which tends to achieve a balanced condition with the stiffness When a slender steel I-beam experiences LTB, failure is usually
of the support. initiated from the midspan unbraced section of the I-beam. This
The self-weight of the girder creates a moment arm, ca , that in- section undergoes lateral distortion, indicating its susceptibility
duces a rolling moment about the roll axis. The stability of a girder to LTB. Consequently, engineers try to determine adequate dimen-
against the rolling moment is determined by the factor of safety, sions for the section and location of the bracing when designing the
which depends on the stability radius calculated using the follow- steel I-beam.
ing equation (Mast 1993): In a steel I-beam, the distorted section is commonly observed at
the midspan, while the support section remains unaffected and does
cr rðθ − αÞ K θ ðθ − αÞ not experience rotation. This indicates that the influence of LTB has
FS ¼ ¼ ¼ ð5Þ
ca z̄θ þ ei þ yθ Wðz̄θ þ ei þ yθÞ not reached the support section, because the damage occurred in the
cross section beforehand. In order to address this structural configu-
Eq. (5) indicates that a girder’s stability in the seated girder con- ration and prevent collapse due to LTB, it is advisable to install
dition is directly influenced by the rotational stiffness of the elastic bracing along the span of a steel I-beam in addition to the bracing
support, represented as K θ . Consequently, the factor of safety at the supports. This comprehensive bracing system helps enhance
against the rolling moment increases if the support has a higher the overall stability of a steel I-beam and mitigate the risk of LTB
rotational stiffness. Therefore, stiffer rotational support provides failure.
a greater factor of safety against rolling moments. Due to imperfections and support rotation, a PCI girder may
display deformations that resemble those seen in LTB, as shown
in Fig. 6. However, it is important to note that local distortion
Theory of Lateral Torsional Buckling in Slender Beams
behavior, such as that seen in a steel I-beam, usually does not occur.
The classical study of lateral buckling in beams assumes that the This distinction can be attributed to the significantly higher flexural
supports are restrained against rotation. Buckling occurs when stiffness (Iy ) and torsional stiffness (J) exhibited by PCI cross sec-
the midspan section of the top beam deforms laterally due to tions compared to steel I-beam sections. The flexural and torsional
compressive stress, resulting in a twisting deformation of the stiffnesses of a PCI girder are approximately a hundred times
cross section. This type of buckling is known as lateral torsional greater, rendering them considerably more rigid. As a result, when
buckling (LTB). subjected to slight support rotation, a PCI girder can withstand the
LTB is a phenomenon that results in the outward curvature of deformations associated with rotating support conditions. These
the top side of a beam. This buckling condition has significant im- conclusions have been validated through empirical tests, providing
plications for the stability analysis of a slender steel I-beam, which substantial evidence for the remarkable stiffness and performance
possesses relatively low torsional (J) and flexural stiffness in the of PCI girders in such conditions (Mast 1993, 1994).
weak axis (Iy ). Understanding and accounting for LTB are crucial In tests conducted by Mast (1993, 1994), a PCI girder with a
in ensuring the overall stability and performance of steel I-beams in 45.6-m (146-ft) span was installed on special supports, adhering
various structural applications. to the bracing criteria. It is important to note that the lower support

© ASCE 05024006-6 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


can tilt. The girder was tested and was proven to withstand support Effect of a Lifting Frame on Hanging Girder
rotation along the axis up to an angle of 32 degrees from the vertical Stability
line without experiencing failure. However, this is possible when The stability of a girder can be improved by a device that can
the reference is at an angle of 0 degrees relative to the vertical line shift the roll axis upward (Imper and Laszlo 1987; Mast
under the nonrotated condition. A PCI girder will fail when the 1989). In the US, this technique is already a standard part of erec-
support rotation along the axis reaches 90 degrees from the vertical tion procedures and involves using a lifting loop as a unique lift-
line. ing point. By implementing this method, the roll axis can be
The capability of a PCI girder cross section to rotate along the shifted above the neutral axis or centroid of the girder, as illus-
axis up to 32 degrees shows its considerable strength and stiffness trated in Fig. 9.
against torsion and flexure along the weak axis, surpassing that A lifting frame is a useful and innovative method for enhancing
of a steel I-beam. The stability of a girder against the occurrence stability during the hanging girder stage, as shown in Figs. 2
of support rotation along the axis up to 32 degrees only relies on the and 10. Although it differs slightly from the lifting loop shown in
resistance torsional moment of the support. Additional bracing Fig. 9, its purpose is the same—shifting the roll axis upward. This
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

along the girder span is not necessary. This behavior is notably approach is backed by research conducted by Imper and Laszlo
distinct from that of a steel I-beam. (1987), Mast (1989), and PCI (2016). The differences between
the two figures (Figs. 9 and 10) mainly focus on improving ease
of installation and field speed, which are crucial for driving inno-
Evaluation of the Effectiveness of the Standard vation, improving safety, and increasing work efficiency.
Guideline In Indonesia, the lifting frame (Fig. 10) is a unique device that
has become popular in infrastructure projects, especially during
PCI girder erection. It is designed for use when lifting a PCI girder
Introduction
with a crane. It has been proven to increase stability, making it a
In late 2022, there was a PCI girder erection failure when the SGE valuable solution for safe and efficient PCI girder installation in
was being followed. This raised concerns about the reliability of the various construction projects in Indonesia.
standard. To solve this issue, we review and evaluate three recom- Once a PCI girder is placed on its supports and the lifting frame
mended improvements in the SGE (2018, 2021): the lifting point or is detached from the lifting wire rope slings, the lifting frame no
frame, dapped-end girders, and artificial stiffeners. longer contributes to its stability.

Fig. 9. Unique device to shift the roll axis of a girder upward in the US. (Reproduced from Imper and Laszlo 1987; PCI 2016, with permission.)

Fig. 10. Unique device to shift the roll axis of a girder upward in Indonesia. (Images courtesy of PT LIMOV Power Structure, Banten, Indonesia.)

© ASCE 05024006-7 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Effect of Dapped-End Girder on the Stability of a 2. Dapped-end girder with a hard bearing pad (H60, E ¼
Seated Girder 4.55 MPa), and
3. Full-end girder with a soft bearing pad (H45, E ¼ 1.8 MPa).
The rotational stiffness of the support influences the stability of the
As part of the study, three FEM models were constructed, each
seated girder condition precisely when its axis direction of rotation
with the same span length. These models aided in calculating the
is aligned parallel to the neutral axis of a PC girder. The material
magnitude of the torsional or rolling moment reaction at the sup-
used for the bearing pad plays a critical role in determining this
port. Furthermore, the analysis was conducted for various span
stiffness. When the material is too soft, it can increase the rolling
lengths (25, 30, 35, 40, 45, and 50 m) to examine the effects across
moment at the support (Mast 1993).
different spans.
Rolling moments at the support emerge due to lateral imperfec-
In order to maintain consistency and simplify the analysis, all
tions (such as sweep) and support eccentricity. Their magnitudes
models were based on the same girder cross section, that is, the
tends to vary from one project to another, depending on the quality
one used for the longest span, 50 m. The data provided corre-
of work in the field and something that triggers it.
spond to the PCI girder utilized in the Cibitung-Cilincing toll
The distance between the midspan center of gravity of a girder
road project, which had a length and depth of 50.8 and 2.3 m,
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

and the roll axis directly influences the magnitude of the rolling
respectively. The details shown in Fig. 11 serve as a reference
moment. Opting for a dapped-end support configuration allows
for the analysis.
for a reduction of this distance, leading to improved stability. How-
The PCI girder for the FEM analysis was modeled using two
ever, even with a dapped-end PCI girder, some degree of rotation
elements, namely the rubber bearing pad (solid C3D8I) and girder
along the roll axis can still occur in the seated condition.
Previous studies on dapped-end PC girders have predominantly (solid C3D8R). Both had a mesh size of 0.1 m. The contact be-
concentrated on strength design (Mattock and Chan 1979; Klein tween these two elements was simulated as hard contact along
et al. 2017; Yuen 2020). There is currently a lack of research on the the normal axis, with an allowable separation afterward. In addi-
stability of dapped-end PC girders in the seated condition. In order tion, friction was considered along the tangential axis between
to gain insight into the impact of using dapped-end girders on the rubber and concrete interface (with the coefficient of friction,
girder stability, a parametric study involving nonlinear structural μ, set to 0.6). This modeling approach accounted for the interaction
analysis was conducted with FEM using the ABAQUS/EXPLICIT between the girder and the rubber bearing pad, addressing potential
(2012). In this study, we employed nonlinear geometric analysis instability issues. The entire model assumed elastic behavior,
to address contact problems. Three different parameters were because failure only occurs during erection, when the acting load
considered for each girder model, allowing for a comprehensive is solely the self-weight of the structure. Therefore, the PC girder
comparison, as follows: was modeled as solid concrete only, without considering the pres-
1. Full-end girder with a hard bearing pad (H60, E ¼ 4.55 MPa) ence of steel reinforcements or prestressing strands. The Abaqus
as baseline, model for the PCI girder is shown in Fig. 12.

Fig. 11. Specifications of the reference PCI girder for FEM modeling: (a) side elevation of PC girder span 50.8; (b) cross section of PC girder; and
(c) Abaqus modeling input.

© ASCE 05024006-8 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Fig. 12. Detailed FEM model for PCI girder: (a) full-end PCI girder; (b) dapped-end PCI girder; and (c) detail of the end section.
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

Fig. 13. Lateral imperfection in the form of a sweep equal to L=500 in FEM modeling.

In Abaqus, it is possible to define and incorporate lateral imper- magnitude of the torsional moment reaction and its potential impact
fections or sweep, which serve as triggers for torsional moments on girder stability, torsional restraints parallel to the axial axis of the
reaction at the support. Imperfection in the geometry were modeled PCI girder were applied to the girder supports attached to the rubber
as lateral deviations of the girder along the span. There was a maxi- bearing pad. The larger the torsional or rolling moment reaction,
mum value of 1=500 deviation at the midspan of the girder, as the greater the risk of girder instability.
shown in Fig. 13. FEM models generated in Abaqus are usually nonlinear. Many
The FEM analysis was designed to be able to accommodate of the problems to which Abaqus is applied are history-dependent,
large deformations and the occurrence of contact interactions be- so solutions must be developed in a series of small increments.
tween the girder and the rubber bearing pad. In addition, the explicit The time incrementation scheme in ABAQUS/EXPLICIT (2012)
dynamic calculation method was selected in Abaqus. This method is fully automatic and requires no user intervention. The final con-
was deemed the most suitable for the analysis. During the initial figuration of the analysis can be observed by examining the mag-
stage of the analysis, a thorough check was performed to ensure nitude of the deformation of the girder, as shown in Fig. 15.
that the contact interaction could be appropriately simulated on Meanwhile, to evaluate their effects, analysis was conducted on
the rubber bearing pad. three distinct parameters for various girder spans (25, 30, 35, 40,
Fig. 14 shows that the contact between the girder and the rubber 45, and 50 m). By examining the analysis results under different
bearing pad was predominantly compression, without any tensile span conditions and parameters, the influence of these variables
conditions observed. It was anticipated that as the girder tilted, sep- on the magnitude of the torsional or rolling moment reaction at
aration or some form of detachment would tend to occur between the support was observed. A comparison curve was generated,
its contact surfaces and the bearing pad. In order to monitor the as shown in Fig. 16.
The FEM analysis conducted with Abaqus provided supporting
evidence for the hypothesis that a dapped-end girder has the poten-
tial to reduce the torsional or rolling moment reaction at the sup-
port. It is important to note that the stiffness of the rubber bearing
pad can significantly influence the final results, because this param-
eter contributes to an increase in the torsional or rolling moment
reaction. Therefore, even with a dapped-end girder (as shown in
Fig. 4), there is still a possibility of experiencing a rotation about
the roll axis due to a rolling moment when a girder is installed or
seated on the support without any additional temporary bracing.
Rotation at the support triggers PCI girder instability, causing
failure.

Effect of Artificial Stiffener on Seated Girder Stability


The design calculation for artificial stiffeners (web and flange) is
published in the appendix of SGE (2021). The artificial stiffener is
expected to increase the torsional constant (J), thereby increasing
girder performance. Interestingly, parameter Iy, which represents
Fig. 14. Contact modeling at the support.
the stiffness of the PCI girder about the weak axis, is not considered

© ASCE 05024006-9 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

Fig. 15. Maximum lateral deformation of a girder with full-end support.

PCI girder is seated indicates that an artificial stiffener is not


working.

Causes of Failure and the Role of Standard Guidelines


As shown in Fig. 17, the PCI girder installation failed after the
hanging girder stage was complete and the seated girder stage
had been entered. This means that the lifting point or lifting frame
aids had proven worthwhile, but the artificial stiffeners were not
beneficial.
The FEM analysis showed that a dapped-end girder can effec-
tively reduce the rolling moment at the support, but its success de-
pends on the stiffness of the bearing pad. It may not be wise to rely
entirely on dapped-end girders, because other factors can affect its
performance. In the seated condition, rolling or torsional moments
tend to occur due to lateral imperfections (sweep) and variations of
the support circumstances. The magnitude of the rolling moments
varies between projects and is influenced by the quality of on-site
Fig. 16. Curve diagram of span versus torsional moment at the support. work. In order to ensure construction safety, sufficient temporary
bracing at the support is required to effectively prevent rolling
failure.
Therefore, in the seated girder condition, failure only occurs
in the design calculation, although the references used were also when the existing temporary bracing at the support is not strong
from Mast (1989); see Eqs. (1) and (2). enough to withstand the rolling moment. The collapse of a girder,
This calculation design suggests that artificial stiffeners may be as shown in Fig. 17 through a series of detailed videos, can be
intended for something other than the hanging girder stage. It attributed to a significant rotation along the axis at the support,
means for the seated girder condition. However, failure when a exceeding the maximum limit of 32 degrees.

Fig. 17. Recorded images moments before the collapse. (Images courtesy of M. Bimo Septiano.)

© ASCE 05024006-10 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

Fig. 18. Recommended bracing configuration according to SGE (2021).

Collapse occurs when a girder undergoes a significant rotation include Mr. Indera Sadikin, Director of Perseroan Terbatas (PT)
along the axis (>32 degrees) that prevents it from being supported Limov Power Structure; Dr. Ing. Josia I. Rastandi, Structures and
by its weight along the weak axis. Excessive rotation due to insuf- Materials Laboratory, Civil Engineering Department, Faculty of
ficient bracing at the support is the main cause of failure. Engineering, Universitas Indonesia, and Director of PT Risen En-
When the bracing at the support in the seated girder condition gineering Consultant; and Mr. Junison and Mr. M. Bimo Septiano
does not function properly, this can lead to significant rotation from PT PP (Persero) Tbk. Their valuable data on the PC girder
along the axis. The requirements for installing bracing at the sup- collapse has been thoroughly examined and processed to make this
ports have been explicitly specified in SGE (2021), as shown in paper possible. The first author would also like to express gratitude
Fig. 18, which depicts various types of bracing. to Mr. Kimron Manik, Director of Construction Sustainability and
The existing standard guideline for erection (SGE 2021) does Secretary of the CSC for his invitation to participate in the CSC’s
not offer detailed provisions for installing bracing components. meetings. The existence of meetings related to construction issues
Consequently, variations in how the guidelines are interpreted in projects under the Ministry of Public Works and Public Housing
and implemented on each project may lead to inadequate bracing is beneficial in gathering ideas for writing papers like this one.
performance and strength. In order to address this issue and ensure
reliable prevention of rolling, it is imperative to conduct a critical
study aimed at standardizing bracing practices for the support References
immediately after the completion of the girder lifting phase.
ABAQUS/EXPLICIT. 2012. Theory manual. Pawtucket, Rhode Island:
Hibbitt, Karlsson, & Sorensen, Inc.
Conclusion Ablehg, F. 2018. “Girder collapsed during toll road construction in Batang,
central Java.” Accessed April 21, 2024. https://www.youtube.com
After the failure of a PCI girder erection in late 2022, an evaluation /watch?v=nfWrfXIcGYg.
study was conducted to assess the effectiveness of SGE (2021). ACI (American Concrete Institute). 2008. Building code requirements for
The study found that (1) the lifting point or lifting frame system structural concrete and commentary. ACI 318M-08. Farmington Hills,
is suitable for hanging girders; (2) dapped-end girders do not guar- MI: ACI.
antee stability when seated on a rubber bearing pad at the support; Bagus, M. 2018. “Launcher girder collapses, Solo-Kertosono toll bridge
and (3) unfortunately, artificial stiffeners do not function properly. project delayed.” Accessed April 21, 2024. https://jatim.inews.id/berita
Therefore, immediate bracing installation at the support is neces- /launcher-girder-roboh-proyek-jembatan-tol-solo-kertosono-molor.
sary to withstand the rolling moment. The current versions of SGE BSN (Badan Standardisasi Nasional). 2019. Occupational safety and
(2018, 2021) mention bracing, but a detailed procedure is needed to health in the construction and erection of precast concrete bridge gird-
ers. SNI 8730:2019. Jakarta, Indonesia: BSN.
ensure the strength of the bracing to withstand the rolling moment.
Effendi, M. 2017. “Police are investigating the cause of the collapse of a
Overall, this evaluation significantly improved the guidelines for
support pole on the Pasuruan-Probolinggo toll road.” Accessed April
PCI girder installation and provided valuable insights for enhancing
21, 2024. https://www.bbc.com/indonesia/indonesia-41793202.
current practices. Haryanto, R. 2018. “Photos of the collapsed concrete girder at the Antasari
toll interchange.” Accessed April 21, 2024. https://news.detik.com/foto
-news/d-3795604/foto-foto-beton-girder-di-simpang-susun-tol-antasari
Data Availability Statement -yang-ambruk.
Imper, R. R., and G. Laszlo. 1987. “Handling and shipping of long span
All data, models, and code generated or used during the study bridge beams.” PCI J. 32 (6): 86–101. https://doi.org/10.15554/pcij
appear in the published article. .11011987.86.101.
Klein, G., A. Botros, B. Andrews, and K. Holloway. 2017. “Dapped ends of
prestressed concrete thin-stemmed members: Part 2, design.” PCI J.
Acknowledgments 62 (2): 83–100. https://doi.org/10.15554/pcij62.2-02.
Mast, R. F. 1989. “Lateral stability of long prestressed concrete beams–
The first author of this paper would like to express gratitude to sev- Part 1.” PCI J. 34 (Jan): 34–53. https://doi.org/10.15554/pcij.010119
eral individuals for their valuable contributions. These individuals 89.34.53.

© ASCE 05024006-11 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006


Mast, R. F. 1993. “Lateral stability of long prestressed concrete beams— SGE (Standard Guideline for Erection). 2018. Precast and prestressed con-
Part 2.” PCI J. 38 (Jan): 70–88. https://doi.org/10.15554/pcij.01011993 crete beams—PC girder beam product. Jakarta, Indonesia: APPCC and
.70.88. APPCE.
Mast, R. F. 1994. “Lateral bending test to destruction of a 149 ft prestressed SGE (Standard Guideline for Erection). 2021. “Standard operating
concrete I-Beam.” PCI J. 39 (4): 54–62. https://doi.org/10.15554/pcij procedure—PC girder beam products.” In Technical guidance for pre-
.07011994.54.62. stressed precast concrete for highway construction. Jakarta, Indonesia:
Mattock, A. H., and T. C. Chan. 1979. “Design and behavior of dapped-end APPCC, APPCE, and Ministry of Public Works and Public Housing.
Stratford, T. J., and C. J. Burgoyne. 1999. “Lateral stability of long precast
beams.” PCI J. 24 (6): 28–45. https://doi.org/10.15554/pcij.11011979
concrete beams.” In Proc., Institution of Civil Engineers-Structures and
.28.45.
Buildings, 169–180. London: Institution of Civil Engineers.
PCI (Precast/Prestressed Concrete Institute). 2016. Recommended practice Venkata, S. P. 2019. “Lateral stability analysis of precast prestressed bridge
for lateral stability of precast, PC bridge girders. 1st ed. Chicago: PCI. girders during all phases of construction.” Doctoral dissertation, Dept.
https://doi.org/10.15554/CB-02-16. of Civil and Architectural Engineering and Construction Management
Sepriansyah, D. 2017. “Video: Toll road construction collapses, a worker of College of Engineering and Applied Science, Univ. of Cincinnati.
dies horribly when crushed by a concrete girder.” Accessed April 21, Yuen, K. W. C. 2020. “Finite element analysis of dapped-ended concrete
Downloaded from ascelibrary.org by Wiryanto Dewobroto on 06/18/24. Copyright ASCE. For personal use only; all rights reserved.

2024. https://palembang.tribunnews.com/2017/10/30/video-konstruksi girders reinforced with steel headed studs.” Master’s thesis, Graduate
-tol-roboh-seorang-pekerja-tewas-mengenaskan-tertimpa-beton-girder. Program in Civil Engineering, Univ. of Calgary.

© ASCE 05024006-12 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2024, 29(4): 05024006

You might also like