Professional Documents
Culture Documents
Ground Improvement - Technical Proposal_compressed
Ground Improvement - Technical Proposal_compressed
PROJECT:
CONSTRUCTION OF FOUR LANE ROB AND ITS APPROACHES IN LIEU OF EXISTING LEVEL
CROSSING NO. RV-71 AT LM 435 ON NH-217 (NEW -353) AT KHARIAR INCLUDING LAND
ACQUISITION UNDER NH(O) IN ANNUAL PLAN 2021-22 FOR THE STATE OF ODISHA. (BID
REF NO.-09 CE NH OF 2021-22).
EPC CONTRACTOR:
ASHIRBAD ENG & CONSTRUCTION PRIVATE LIMITED
PROJECT SITE OFFICE: UNIT NO. 16, CHALMUNDA P.S. - JONK, KHARIAR ROAD,DIST. - NUAPADA, ODISHA
HEAD OFFICE: PLOT NO. 20/261, MILAN PARADISE, SAILASHREE VIHAR, CHANDRASEKHARPUR,
BHUBANESWAR 751016, ODISHA
AUTHORITY ENGINEER:
Chief Construction Engineer Western NH Circle, Sambalpur
PROOF CONSULTANT:
DESIGN CONSULTANT:
Festal Consulting Engineers Pvt. Ltd.
414, 4th Floor, Orbit Plaza, Crossing Republik, Ghaziabad, UP201016
As mentioned in Schedule B – TCS 5, 5A, 6 of the Contract Agreement for the project ‘Construction of Four lane ROB and its approaches in lieu
of existing Level Crossing No. RV -71 at km 435 on NH-217 (New NH -353) at Khariar Road’ – from chainage 1047 m to 1550 m (in the approach
RE wall section towards Raipur side) – requirement of Ground Improvement using Sand Piles each of 500 mm diameter & 6 meter depth.
As per the Geotechnical Investigations held (Geotech Report attached), the said stretch of around 400-500 meters towards the Raipur side
approach RE Wall portion between chainages 1047 m to 1550 m is found to be heavily water-logged with sandy clay type soil with very low
bearing capacity & excessive settlement.
Hence, for the safety of the RE Wall structure above this stretch there is need for GROUND IMPROVEMENT for increasing the load bearing
capacity of the ground and reduce settlement.
The said provision of Ground Improvement using such Sand Piles is nor feasible & possible due to the below mentioned reasons & hence an
alternative method of Ground Improvement is proposed using Basal Reinforcement with Soil replacement (in which the entire poor soil in the
said stretch shall be replaced with select fill of good bearing capacity meeting all safety requirements along with use of MACCAFERRI High
Strength Uniaxial Geogrid, MACCAFERRI Non Woven Geotextile & Line Drains).
S NO. SAND PILE OF 500 MM DIA & 6 METER DEPTH BASAL REINFORCEMENT WITH SOIL REPLACEMENT USING
GEOGRID & GEOTEXTILE
There is no provision of the Ground improvement technique Basal Reinforcement with Soil replacement provision as per IRC :
using SAND PILES in any IRC/IS codes or MORTH guidelines 113 and IS : 13904 code for ground improvement techniques for
foundations in weak soils.
Sand Pile requirement of depth of 6 meter as given in Sch B Basal Reinforcement with Soil replacement is shallow ground
TCS 5, 5A, 6 is not feasible as the onset of DI rock starts just 2- improvement technique and suggested where this is loose strata of
3 meters below the ground level whereas Sand Piling is a deep natural ground for less than 5 meters.
ground improvement technique and suggested where there is
loose strata of natural ground for more than 7-10 meters
depth.
Depth of Sand Pile can go only up-to the depth of loose Depth of soil replacement depends on the bearing capacity and
stratum irrespective of influence zone of structure & if we rest settlement requirement and maximum depth of replacement goes
the sand piling at the loose stratum than it can punch into till influence zone.
loose stratum.
Sand Piling in the entire effected zone would take at-least 6 Basal Reinforcement with Soil replacement methodology will take
months’ time period and hence could delay the subsequent up-to 3 months and hence reduce.
construction activities of erection of RE Wal earthwork etc. &
eventually would delay the Project timelines.
Sand Piling provision will not be sufficient enough to prevent Basal Reinforcement along-with provision of Line Drains along the
the underground Water percolation inside the RE wall panels entire RE wall section would be required to drain out the
section. underground water percolation.
Compaction in case of Sand Piling is not uniform and area Compaction can be controlled and uniform in case of soil
replacement ratio is also not guaranteed. replacement with Basal reinforcement.
In present case rock is available at shallow depth, in the range Due to presence of rock at shallow depth, replacement of 1.5 m to
of 3 meters, out of which 1 meter is the minimum 3.5 m clay with select fill material and basal reinforcement is the
embedment depth of RE wall structure, hence only around 2- most suitable and safe option to retain the RE Wall Structure above
3 m of clay strata is available after foundation level. the said stretch.
Drilling for sand piles for such shallow depth is not feasible &
not a safe option to retain the RE Wall Structure above the
said stretch.
Technical Proposal
Minor modification
2 R1 29th August 23 Sonal Saurabh Ratnakar
done
Group Profile
Founded in 1879, Officine Maccaferri rapidly became a technical reference in the
design and development of solutions for erosion control and retaining structures.
Maccaferri's scale and experience enables them to be a reliable partner for complex
civil and environmental engineering applications. Furthermore, common to all
Maccaferri's solutions is an aptitude for technological innovation and the goal of
maintaining a sustainable environmental balance.
Technical partnership
Maccaferri is a partner who works alongside clients from the start of the project,
maximizing value for money due to technical expertise and an extensive portfolio of
quality products. Each project is approached with the aim of identifying, addressing
and resolving the specific needs of each customer. This result of this approach is long
term mutual benefits for both client and Maccaferri.
Organizational Structure
Maccaferri offers solutions for the construction market in over 100 countries
throughout the world. Our organizational structure has been designed to be global
and local at the same time; it is made up of subsidiary companies who manufacture,
design and install solutions throughout the world. This ensures greater flexibility, a
Major Products:
➢ Gabions
➢ Mattresses
➢ Terramesh& Green Terramesh
➢ Paraweb & ParaLink
➢ ParaGrid & ParaDrain
➢ Geogrids & Geotextiles
➢ Geomembranes & GCLs
➢ Geocomposites
➢ Glass Grids
➢ Erosion Control Mats
➢ Geocells
➢ Fabric Form Mats
➢ Prefabricated Vertical Drains
➢ Geotextile bags & Geotextile tubes
➢ Sack Gabion
➢ Road Mesh
➢ Rockfall Netting
➢ HEA Panels
Major Applications:
➢ Erosion Control
➢ Channel Protection
➢ River Training & Flood Control
➢ Shoreline Protection & Coastal Defense
➢ Reinforced Soil Structures
➢ Ground Improvement
➢ Gravity Retaining Structures
➢ Slope Stabilization
Services Offered:
Our USPs:
The Ministry of Road Transport and highways is developing the four lane ROB and its
approaches in lieu of existing level crossing no. RV 71 at km 435 on NH-217 at Khariar.
Ashirbad Eng & Construction Private Limited is doing the construction of the ROB and
its approaches, and they approach Maccaferri to design the RS wall for the ROB
approaches. While designing the RS wall, Maccaferri envisaged that the ground below
foundation of RS wall is having clay layer ranging from 2 m to 5 m and prone to water
logging. Hence there is need of treatment of soil below RS wall with a suitable ground
improvement solution. Water table is observed at shallow depth. The current proposal
discusses the technical feasibility of ground improvement solutions.
I) Problem Description
As per geotechnical investigation report, the stratum is found to be waterlogged with
sandy clay type of soil which extends up to depth of 4-5m. The stretch is prone to large
amount of settlement, hence required the ground improvement for carrying out the
construction of RS wall embankment.
The major problems associated with the clayey soils are low bearing capacity,
excessive settlement, and deep-seated foundation failure (shown in fig 1). The bearing
capacity observed for the locations is very low. Hence, there is need for ground
improvement for increasing its bearing capacity or in other way for increasing its load
carrying capacity and reducing the consolidation settlement.
The proposed solution includes replacement of clay with selected fill along with high
strength uniaxial geogrid (Paralink/ParaGrid HF), non-woven geotextile (MacTex N).
Details of the solutions & design considerations are presented in design sections.
4. Solution Components
3. Design Considerations
• Load- 24 kPa
BH 20 (CH: 0+750)
BH 18 (A2-CH: 1+040)
Bulk Unit Sat. Unit
Type of Thickness, Cohesion, Friction Specific Void
Weight, Weight,
Strata m (t/m2) Angle, gravity ratio
T/m3 T/m3
Clay 4.5 3 10 1.85 2.05 2.635 0.71
Disintegrated
11.5 0 32 1.952 2.152 2.71
Soft Rock
Hard Rock* 5 0* 32* 1.952 2.152
*Assumed
• Compression Index (Cc) values are not given in the report and the same are taken
as an average of below given correlation given in IS 8009-1
Cc = 0.009 (LL-10)
Cc = 0.3 (e0-0.27)
• The water table is considered at ground level for critical case of design.
Select fill
Angle of Internal Friction (min) 300
Cohesion (min) 0 kPa
Bulk Unit Weight 1.8 T/m3
Sat Unit Weight 2.0 T/m3
• The seismic zone & coefficients (Reference IRC 6: 2010 & IS 1893:2002)
considered for the design are
Seismic Zone III
Seismic Coefficients Ah = 0.08, Av =0.053
• The calculation has been performed as per IS 6403, IS 8009-I, IRC:75-2015 & IRC-
113: 2013.
• Untreated analysis includes a 10.4m and 15.2m high RS wall embankment over
ground level with existing soil strata.
The calculation has been performed as per IRC:75-2015 & IRC-113: 2013.
• With the use of high strength uniaxial geogrid (Paralink/ParaGrid HF) approx. 10%
of reduction in stress is attained.
PARAWEB PARAWEB
DRAINAGE PIPE GRAVEL/AGGREGATE FILTER GRAVEL/AGGREGATE FILTER DRAINAGE PIPE
PARAWEB PARAWEB
OGL/SRL OGL/SRL
REINFORCED BACKFILL REINFORCED BACKFILL
PARAWEB PARAWEB
Location:
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71
AT KM 435 ON NH-217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71 AT KM 435 ON NH-
Project:
217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
Height of wall 10.4m high Reinforced soil wall Based on Boreholes BH-20
excluding 1 m
1) Thickness ( H ) = 4.0 m
embedment
2) Saturated Unit Weight ( gsat ) = 2.030 t/m3
C) ESTIMATION OF SETTLEMENT :
(i) Case I: If the Clayey Soil is not Preconsolidated i.e. Normally Consolidated [ p f > p0 > pc ] --------
(ii) Case II: If the Clayey Soil is Preconsolidated and [ p0 < pc < pf ] ---------
(ii) Case III: If the Clayey Soil is Preconsolidated and [ p0 < pf < pc ] ---------
Dp = 2 * (q * Isz)
1 4.00 4.000 2.000 0.000 1.406 #DIV/0! 2.060 22.154 0.379 N.A. N.A.
Correction Factors --
Location:
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71
AT KM 435 ON NH-217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71 AT KM 435 ON NH-
Project:
217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
Height of wall 10.4m high Reinforced soil wall Based on Boreholes BH-1 (A1)
Excluding 1 m
1) Thickness ( H ) = 2.2 m
embedment
2) Saturated Unit Weight ( gsat ) = 2.068 t/m3
C) ESTIMATION OF SETTLEMENT :
(i) Case I: If the Clayey Soil is not Preconsolidated i.e. Normally Consolidated [ p f > p0 > pc ] --------
(ii) Case II: If the Clayey Soil is Preconsolidated and [ p0 < pc < pf ] ---------
(ii) Case III: If the Clayey Soil is Preconsolidated and [ p0 < pf < pc ] ---------
Dp = 2 * (q * Isz)
1 2.20 2.200 1.100 0.000 1.479 #DIV/0! 1.175 22.948 0.331 N.A. N.A.
Correction Factors --
Location:
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71
AT KM 435 ON NH-217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71 AT KM 435 ON NH-
Project:
217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
Height of wall 15.2m high Reinforced soil wall Based on Boreholes BH-18 (A2)
LAYER 1 : Clay
excluding 1m
1) Thickness ( H ) = 3.5 m
embedment
2) Saturated Unit Weight ( gsat ) = 2.050 t/m3
C) ESTIMATION OF SETTLEMENT :
(i) Case I: If the Clayey Soil is not Preconsolidated i.e. Normally Consolidated [ p f > p0 > pc ] --------
(ii) Case II: If the Clayey Soil is Preconsolidated and [ p0 < pc < pf ] ---------
(ii) Case III: If the Clayey Soil is Preconsolidated and [ p0 < pf < pc ] ---------
Dp = 2 * (q * Isz)
I Clay 0.000
1 3.50 3.500 1.750 0.000 1.426 #DIV/0! 1.838 30.757 0.527 N.A. N.A.
Correction Factors --
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71
Location:
AT KM 435 ON NH-217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71 AT KM 435 ON NH-217
Project:
(NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
RS Wall (Roadway
Proposed Structure. Type of Embankment Roadway Embankment
embankment)
Height of wall 10.4m high Reinforced soil wall Based on Boreholes BH-20
2) Thickness ( H ) = 1.0 m
(i) Case I: If the Clayey Soil is not Preconsolidated i.e. Normally Consolidated [ pf > p0 > pc ] --------
(ii) Case II: If the Clayey Soil is Preconsolidated and [ p0 < pc < pf ] ---------
(ii) Case III: If the Clayey Soil is Preconsolidated and [ p0 < pf < pc ] ---------
Dp = 2 * (q * Isz)
1 3.00 3.000 1.500 0.000 1.446 #DIV/0! 1.500 22.588 0.000 N.A. N.A.
2 1.00 1.000 3.500 0.000 1.287 #DIV/0! 3.515 18.581 0.071 N.A. N.A.
Location:
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71
AT KM 435 ON NH-217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71 AT KM 435 ON NH-217
Project:
(NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
RS Wall (Roadway
Proposed Structure. Type of Embankment Roadway Embankment
embankment)
Height of wall 10.4m high Reinforced soil wall Based on Boreholes BH-1 (A1)
Below
1) Thickness ( H ) = 1.5 m
Foundation
2) Saturated Unit Weight ( gsat ) = 2.000 t/m3
2) Thickness ( H ) = 0.7 m
(i) Case I: If the Clayey Soil is not Preconsolidated i.e. Normally Consolidated [ pf > p0 > pc ] --------
(ii) Case II: If the Clayey Soil is Preconsolidated and [ p0 < pc < pf ] ---------
(ii) Case III: If the Clayey Soil is Preconsolidated and [ p0 < pf < pc ] ---------
Dp = 2 * (q * Isz)
1 1.50 1.500 0.750 0.000 1.508 #DIV/0! 0.750 23.273 0.000 N.A. N.A.
2 0.70 0.700 1.850 0.000 1.418 #DIV/0! 1.874 20.794 0.087 N.A. N.A.
Location:
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71
AT KM 435 ON NH-217 (NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
GROUND IMPROVEMENT SOLUTION FOR FOUR LANING OF EXISTING LEVEL CROSSING NO. RV-71 AT KM 435 ON NH-217
Project:
(NEW NH 353) AT KHARIAR IN THE DIST. OF NUAPADA
RS Wall (Roadway
Proposed Structure. Type of Embankment Roadway Embankment
embankment)
Height of wall 15.2 m high Reinforced soil wall Based on Boreholes BH-18 (A2)
Below
1) Thickness ( H ) = 3.0 m
Foundation
2) Saturated Unit Weight ( gsat ) = 2.000 t/m3
LAYER 2 : Clay
2) Thickness ( H ) = 0.5 m
(i) Case I: If the Clayey Soil is not Preconsolidated i.e. Normally Consolidated [ pf > p0 > pc ] --------
(ii) Case II: If the Clayey Soil is Preconsolidated and [ p0 < pc < pf ] ---------
(ii) Case III: If the Clayey Soil is Preconsolidated and [ p0 < pf < pc ] ---------
Dp = 2 * (q * Isz)
II Clay 0.000
1 3.00 3.000 1.500 0.000 1.446 #DIV/0! 1.500 31.059 0.000 N.A. N.A.
PARAPRODUCTS
(Basal Reinforcement)
RAILWAYS APPLICATIONS
1
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
CONTENTS
PREFACE 3
1. INTRODUCTION 3
2. IMPORTANT INFORMATION 4
2.1 RESPONSIBILITIES 4
2.2 CONSTRUCTION DESIGN 5
2.3 PARTS OF THE STRUCTURE 5
2.4 SERVICES PROVIDED BY OFFICINE MACCAFERRI S.p.A. 5
2.5 MATERIALS PROVIDED BY OFFICINE MACCAFERRI S.p.A. 6
3. ORGANISATION OF INSTALLATION SITE 7
3.1 PLANT AND MACHINERY NEEDED BY THE CONTACTOR 7
3.1 EQUIPMENT NEEDED BY THE CONTACTOR 7
3.3 ESTIMATED PERSONNEL REQUIRED FOR INSTALLATION 8
3.4 WORKS TO BE CARRIED OUT BY THE CONTRACTOR 8
3.5 INSTALLATION RATE 8
3.6 EMBANKMENT MATERIAL 9
4. UNLOADING AND STORAGE OF PREFABRICATED ELEMENTS 9
4.1 PREFABRICATED CONCRETE PANELS 9
4.2 ParawebTM REINFORCEMENT AND ACCESSORIES 11
5. INSTALLATION 13
5.1 PROCEDURES FOR POSITIONING PANELS 13
5.2 INSTALLATION SEQUENCE 15
5.3 INSTALLATION OPERATIONS 16
OP 1) SITE PREPARATION 16
OP 2) POURING BLINDING LAYER AND SETTING OUT OF FACING 17
OP 3) POSITIONING AND STRUTTING OF THE FIRST ROW OF PANELS 17
OP 4) PLACING OF WEDGES AND CLAMPS 19
OP 10) REPETITION OF OPERATIONS 4),5),6),7),8),9) AND 10) UNTIL THE TOP LEVEL OF
THE FACING REQUIRED IN THE DESIGN IS REACHED 24
6. CAUSE-EFFECT RELATIONS 25
7. REGISTERED TRADE-MARK 27
2
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
PREFACE
MACCAFERRI Group owns 100% of Linear Composites Ltd based in U.K. who manufactures the Paragrid and
Paralink geogrids.
Paralink geogrids are planar structures consisiting of a monoaxial array
of composite Geosynthetic strips. Each longitudinal strip has a core of
high modulus, low creep polyester yarn tendons encased in a tough, du-
rable polyethylene sheath.
The single strips are connected by low strength cross laid polyethylene
elements which give a grid like shape to the composite. Paralink has su-
perior unidirectional strength and is available as a custom-made product
in a range of strengths between 100 kN/m ultimate up to 1350 kN/m.
Bidirectional strength can be obtained by installing two paralink Layers
at right angles to each other.
Paralink conforms to CE marking for reinforcement applications, and is
certified by the British Board of Agreement for applications in soil rein-
forcement.
1. INTRODUCTION
Paraproducts have been used many years in soil reinforcement applications in many different countries in a variety
of different applications such as:
• Steep slope construction
• Basal reinforcement of railway and road embankments
• Foundation reinforcement of piled embankments
• Geosynthetic foundations on weak soils
All these applications have been deeply investigated and their design is fully detailed in the first edition of BS 8006.
This is the first European Code dedicated to Reinforcement Application. In order to comply with this Code of Prac-
tice the Paragrid and Paralink range of materials have been tested and certified by the British Board of Agrement
since the early 1990’s and the base strip material Paraweb since 1978 (actually we have the third edition of these
certifications)
3
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
• Piled foundations
• Areas prone to subsidence”
2. RAILWAY APPLICATIONS
The products have been widely used in railway applications mainly as basal reinforcement; the first applications
have been done in UK while the most extensive and documented applications are in Italy where both Paragrid and
Paralink have been used in the construction of a new high speed railway lines.
Hereafter is reported the list of the main application and for some projects pictures, certifications and more detailed
information.
UK References
1. Piled Embankment reinforced with Paralink geogrids in the construction of the railway link from the
British rail main line (London-Cambridge) to the new airport terminal buildings of Stansted (London
Airport 3)
Designer/client: British railway board
Contractor: Peter Birse Ltd.
Notes: Paper presented to the International Conference on Geotextiles, geomembranes and related pro
ducts - The Hague (NL) - 1990
4
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
5
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
6
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
7
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
23
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
24
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
The tensile strengths required are very high especially if we take into consideration the elongation limits
imposed; the maximum elongation acceptable at the working stress have in fact not to exceed the 5%.
These working conditions have driven the choice of the reinforcement geogrid (see following paragraph).
To be emphasized that the high resistance are a logical result of the BS8006 assumption of not taking
into account the positive contribution of the confined soil so that the embankment is fully sustained by the
reinforcement element only.
This supposition can be, at first impact, considered excessively cautious but the working difficulty in
compacting the soil around the pile caps has as a
result that the real contribution of the soil is prac-
tically negligible.
REINFORCEMENT MATERIAL
CONCLUSION
Many other embankments, following the path opened by this first applications (in the same area have been
built five piled embaments: RI83, RI84, RI87, RI89 and RI90 where “RI” ins the Italian shortening for em-
bankment), have been done in Italy on railways and highway embankments.
The interest for these first embankments is anyway still very high because these are the only one where
the contractor and the designer decided to squeeze at top level the geosynthetics performances in order not
to build additional caps to the piles. It is still under discussion if it is the best solution from the economical
point of view (but this was the point of view of the contractor) but most important fat is that the solution
works perfectly and the results are as estimated during the design phase; for sure this is the most welcomed
solution by the railways authority side.
ACKNOWLEDGEMENTS
The authors wish to extend special thanks to: the Consorzio CEPAV UNO, the EUROVIE S.c.a.r.l., Dott.
Eng. A. Boschi.
REFERENCES
26
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
Hewlett W.J. & Randolph M.F. (1988). “Analisis of piled embankments”, Ground Engineering, Vol.22, No.3, April 1988, pp.
12-18.
“Code of practice for Strengthened/reinforced soils and other fills” – British Standard 8006/95.
Rehnman S-E, Eriksonn U.B., Jendeby L. (1999). “Embankment on soft soil, interaction between embankment, reinforced and
piles. Long term measurement at Urvalla, Sweden”, Geothecnical engineering for transportation infrastructure, pp. 1867-
1872.
8. Piled Embankement reinforced with Paralink geogrids in the construction of the railway high
speed train track from Bologna to Milano - Italain Railway identification of the Embankment RI 84
Designer/client: Italferr Spa/TAV Spa
Contractor: Eurovie scarl (Parma)
Materials used: Paralink 600 m2 7.800
Paralink 800 m2 4.000
Paralink 1050 m2 1.800
Paralink 1150 m2 4.700
G E O G R IG LIE TR AS V E R S A LI
tipo lung h ezza largh ezza n°
da a mq
pa ralink rotolo ro to lo roto lo
1 26 11 50 40 4.5 26 4 680
27 36 10 50 38 4.5 10 17 10
37 39 8 50 36 4.5 3 48 6
40 44 8 50 38 4.5 5 85 5
45 60 8 50 36 4.5 16 2 59 2
61 66 600 88 4.5 6 2 3 76
with an identification number. This identification code is shown on an in- 67 67 600 88 3.0 1 264
68 68 600 68 *2 4.5 1 306
stallation sketch (see following page) and on a summary table (see aside) 69
70
69
71
600
600
86
88
4.5
4.5
1
2
387
792
to enable correct installation and positioning of each roll. 72
74
73
74
600
600
90
68 *3
4.5
3.0
2
1
810
204
75 75 600 44 *1 3.0 1 132
76 77 600 44 *2 4.5 2 396
78 78 600 42 *3 4.5 1 189
With these tools the installation team will make a quick and easy job wi- 79 79 600 44 3.0 1 132
80 83 600 86 4.5 4 15 48
thout any possibility of mistakes and with assurance of no wastage of ma- 84 84 600 88 3.0 1 264
Installation sketch of RI84 - Installation documents given from Maccaferri tech. Dpt to the contractor installation team
28
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
29
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
16
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
17
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
18
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
19
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
20
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
7. Piled Embankement reinforced with Paralink geogrids in the construction of the railway railway
high speed train track from Bologna to Milano - Italain Railway identification of the Embankment
RI 83
Designer/client: Italferr Spa/TAV Spa
Contractor: Eurovie scarl (Parma)
Notes: Paper presented to the International Conference on Geotextiles, geomembranes and related
products - Yokoama (J) - 2006 (hereafter attached)
INTRODUCTION
In the construction of the new Italian high speed railway line (“Treno Alta Velocità”) connecting the cities
of Napoli and Milano some piled embankments have been build in the area of Parma (on the portion of line
connecting Bologna to Milano) in place of the traditional consolidation system based on drainage systems.
The choice of a “non traditional solution” was due to the need to solve in a very short time the settle-
ment problem; this in order to satisfy the construction time requirements and to minimize the local and dif-
ferential settlements on the embankments.
More than this, new consolidation solutions – as far as concern the Italian market – were easily accepted
in areas characterized by the presence of a prevalent water table able – in time - to reduce to zero the bene-
fits of any consolidation done with drainage systems. The drainage solutions option have been studied but
it was not possible to guarantee either the reduction of the constructions time or to obtain gradients of set-
21
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
tlements acceptable for the ordinary work of the railway line (the main contractor’s need was a maximum
gradient of settlement equal to 5 cm/10 years in standard working conditions).
The piled embankments area is located south of the city of Parma parallel to the motorway A1 (Milano-
Bologna). This area is well known as rising spring-water area in the province of Parma and this could have
caused an increase of the speed of the settlement without guarantee of the functional work of the embank-
ment.
In order to solve the problem, in place of a solution based on drainage systems, it has been decided to
design a solution based on a wide-spread use of piles with a top foundation layer of the embankment done
with a crossed layer of mono directional high resistance geogrids.
Because of the lack of a relevant national standard the BS8006 Code of Practice has been used to design
the geogrid foundation layer; this was also a specific request of the Italian railways authority in order to
have no risk in the design of this innovative application.
This paper will give some information on the geotechnical background of the surrounding area, details
of the final solution and the design key elements calculated according to the indication of the chapter 8 of
the mentioned BS8006; finally the results will be compared with a modified design calculation based again
on the BS8006.
Gotechnical informations
The full piled embankment area has been geotechnically investigated with “in situ” and laboratory tests.
The stratigraphic profile is detailed in figure 1.
In the following table 1 are reported the thickness of the different soil stratum intersected by the piles and
the most relevant soil parameters of the area of the piled embankment.
Settlement calculation
The evaluation of the settlements has been done with the elastic method according to the geotechnical pa-
rameters obtained by the analysis tests. The consolidation method, according to the model of Broms
(1987), has been supposed to be as an improvement of the elastic parameters of the soil interested by the
pile injection.
The most relevant results of the settlement analysis is reported in table 2, where H is equal to the height
of the analysed embankment and η is the settlement measured at 3 and 13 years from the beginning of the
construction of the embankment.
22
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
8
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
9
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
Italy references
2. Piled Embankement reinforced with Paralink geogrids in the costruction of the railway link from the
main line (Roma-Neaple) to the new facilities of the Rome terminal of the High Speed Train (TAV) -
Italain Raiway identification of the Embankment RI 01
Designer/client: Italferr Spa/TAV Spa
Contractor: Condotte Spa (Rome)
Materials used: Paragrid 200/05 m2 11.500
Paralink 400 m2 9.000
Paralink 800 m2 4.500
10
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
3. Piled Embankement reinforced with Paralink geogrids in the costruction of the railway
link from the main line (Roma-Neaple) to the new facilities of the Rome terminal of the
High Speed Train (TAV) - Italain Raiway identification of the Embankement RI 02
Designer/client: Italferr Spa/TAV Spa
Contractor: Condotte Spa (Rome)
11
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
4. Piled Embankement reinforced with Paralink geogrids in the costruction of the railway link from
the main line (Roma-Neaple) to the new facilities of the Rome terminal of the High Speed Train (TAV)
- Italain Railway identification of the Embankment RI 04
Designer/client: Italferr Spa/TAV Spa
Contractor: Condotte Spa (Rome)
5. Reinforced Foundation Embankement on soft soils with Paralink geogrids in the costruction of the
railway high speed train track from Bologna to Milano - Italain Railway identification of the Emban-
kment RI 61
Designer/client: Italferr Spa/TAV Spa
Contractor: CMB scrl
Notes: Paper presented to the National Conference on Geotextiles, geomembranes and related pro-
ducts - Bologna (IT) - 1997
6. Reinforced Foundation Embankement on soft soils with Paragrid geogrids in the costruction of the
railway high speed train track from Roma to Neaple - Italain Railway identification of the Embank-
ment RI 44
Designer/client: Italferr Spa/IRICAV 1 Spa
Contractor: Pegaso scarl (Rome)
Notes: Paper presented to the National Conference on Geotextiles, geomembranes and related pro
ducts - Bologna (IT) - 1997
12
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
Hereafter attached the approval certificate iussued to Paragrid 110/15S iussed by IRICAV 1
13
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
(committent of the contractor Pegaso scarl) and transmitted as approved to Italferr (Italian Railway’s
enginnering company working as supervisor). Certificate was issued in October 95 to Terram Ltd (at
that time LCL’s property) and to Maccaferri Italy and Maccaferri France (France Gabion)
14
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
15
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
30
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
31
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
32
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
9. Piled Embankment reinforced with Paralink geogrids in the construction of the railway railway high
speed train track from Bologna to Milano - Italain Raiway identification of the Embankement RI87
Designer/client: Italferr Spa/TAV Spa
Contractor: Eurovie scarl (Parma)
Materials used: Paralink 600 m2 7.00
Paralink 850 m2 800
Paralink 900 m2 1.600
33
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
11. Piled Embankment reinforced with Paralink geogrids in the construction of the railway high speed
train track from Bologna to Milano - Italain Raiway identification of the Embankment RI 90
Designer/client: Italferr Spa/TAV Spa
Contractor: Eurovie scarl (Parma)
34
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
12. Piled Embankment reinforced with Paralink geogrids in the costruction of the railway high speed
train track from Bologna to Milano - Italian Railway identification of the Embankment RI 08 (Bologna
area)
Designer/client: Italferr Spa/TAV Spa
Contractor: Baldassini-Tognozzi-Pontello Spa (Firenze)
Materials used: Paralink 400 (cross direction) Paragrid 150/05 (main direction)
35
Maccaferri reserves the right to amend product specifications without notice and specifiers are
requested to check as to the validity of the specifications they are using.
high speed train track from Bologna to Milano - Italain Railway identification of the Embankement RI 05
and TR 05 (Bologna area)
Designer/client: Italferr Spa/TAV Spa
Contractor: Baldassini-Tognozzi-Pontello Spa (Firenze)
Materials used: Paragrid 150/05
14. Reinforced Foundation Embankement-Trench on soft soils with Paragrid 150/05 geogrid in the con-
struction of the railway high speed train track from Bologna to Verona - Italian Railway identification
of the Embankment RI 04 and TR 03 (Bologna area)
Designer/client: Italferr Spa/TAV Spa
Contractor: Baldassini-Tognozzi-Pontello Spa (FI)
Materials used: Paragrid 150/05
36
Case Studies- Ground Improvement using
ParaLink as Basal Reinforcement
YEAR: 1985
PARALINK: 200S
YEAR: 1986
PARALINK: 300S
YEAR: 1988
YEAR: 1988
LOCATION: UK - Wales
PARALINK: 300S
YEAR: 1989
PARALINK: 600S
YEAR: 1991
YEAR: 1992
PARALINK: 200S
CLIENT: Barmac
APPLICATION: Hybrid reinforced Earth Structure with Terramesh System facing units
PARALINK: 300
JOB: Rehabilitation of the road connecting Cagliari and Perdaxius
YEAR: 1998
CLIENT: COESA
YEAR: 2001
LOCATION: UK - Rochdale
YEAR: 2001-2005
YEAR: 2003
LOCATION: Venezuela
CLIENT:
JOB: High Speed railway track from Rome to Neaples; embankments N° 1,2
&4
YEAR: 2003-2004
LOCATION: ITALY—Rome
LOCATION: PORTUGAL
CLIENT:
YEAR: 2002-2003
PARALINK: 100, 200, 300, 400, 450, 500, 550, 600, 650,700, 950 - 81.000m2 (Total)
YEAR: 2003-2004
100, 150, 200, 250, 300, 350, 400, 450, 500, 550, 600, 900 - 164.900m2
PARALINK:
(Total)
YEAR: 2004
JOB: Expansion of the third lane of the Rome ring road at the Aurelia exit
YEAR: 2004
50, 100, 150; 200, 250, 300, 350, 450, 500, 550, 650, 750, 800, 850, 950 -
PARALINK:
109.800m2 (Total)
LOCATION: PORTUGAL
YEAR: 2006
YEAR: 2007
APPLICATION: Main reinforcement in reinforced earth structure with Terramesh facing units
JOB: Alphaville
YEAR: 2007
APPLICATION: Main reinforcement in reinforced earth structure with Terramesh facing units
YEAR: 2007
YEAR: 2008
YEAR: 2008
LOCATION: ROMANIA
LOCATION: SLOVAKIA
JOB: Triumphal Presidential Flagpole Park on the shore of the Caspian Sea
YEAR: 2008-2009
CLIENT: Azenco
CLIENT: Inter-Lider
LOCATION: UK – London
YEAR: 2009
YEAR: 2009
JOB: Agriport
YEAR: 2009
LOCATION: SA - Durban
YEAR: 2009-2010
CLIENT: Zapoge
YEAR: 2009-2010
YEAR: 2010
CLIENT: Rosinzhiniring
Main reinforcement in reinforced retaining structure with Terramesh System
APPLICATION:
units as facing and secondary reinforcement
PARALINK: 500 - 77.000m2
YEAR: 2010
YEAR: 2008-2010
GROUND IMPROVEMENT
Technique: Stone Columns + ParaLink
Problem:
Mundra Special Economic Zone is located in Kutch District, Gu-
jarat and is one of the largest SEZ in India. An ROB was pro-
posed over the railway line that cuts across the connectivity road
between Mundra and NH8A. The approaches of ROB were pro-
posed to be retained by ParaWeb Reinforced Soil wall system
However, foundation soil comprising primarily of sandy silt with
clay was found to have inadequate load bearing capacity to
bear the load of retaining walls.
Keeping in mind the high water table and high consolidation set-
tlements, such a ground improvement technique was to be pro-
posed which would improve bearing capacity of soil, reduce
post– construction settlement and also facilitate process of im- Fig. 1 Project Location
plementation. Thus, considering all these factors, stone column
technique with a geosynthetic raft was adopted.
Wall Height in m Settlement in mm
Solution: 200
8.8
The stone column technique, also known as vibro-replacement 180
or vibro-displacement, is a ground improvement process 8.0
where vertical columns of compacted aggregate are formed 160
through the soils to be improved (Refer Photo 1) 7.2
120
Primary purpose of soil improvement by stone column technique 6.4
is mainly to increase the bearing capacity of foundation soil and
also to reduce post construction settlement. 100
5.6
Stone column derives its support from lateral resistance provided
by the surrounding soil caused by
Table 1 Estimated settlements at different wall
• bulging of the uncemented stone column under the load
• the resistance due to surcharge effect
• the bearing support offered by intervening soil.
Client name:
M/s Mundra Port & Special Economic Zone Ltd
Consultant name:
M/s. Multimedia Consultant Pvt. Ltd
Contractor
M/s. Chetan Engineers
Technique used:
Stone Column + ParaLink™
Construction info: Photo 1 During Construction — Installing stone
Construction Start: April 2009
Construction end: June 2010
The geosynthetic raft is ParaLink™, which are monoaxial array of geosynthetic strips having uni-
directional strength ranging from 100 to 1350 kN/m. The purpose of providing ParaLink™ as basal rein-
forcement is to ensure proper distribution of the load from the superstructure to the stone columns and
reduce differential settlements.
Photo 2 During Construction— Installing drainage layer Fig. 2 Stone column layout (South side)
The area is recommended to be excavated till the founding level where the stone columns are
installed.
Stone columns :
• South side - entire zone including the reinforced and unreinforced section was im-
proved by stone column technique.
• North side - owing to relatively better quality of soil, stone columns were provided only
under reinforced soil.
ParaLink™ was laid throughout the entire zone both in the North and South side of the struc-
ture. The surface of the stone column was covered with a free draining granular fill compacted
to 95% of Modified Proctor density.
Present Status : Project is completed in June 2010 and serving its purpose.
R S Wall Details:
Maximum Height of Wall: 6 m
Client name:
Northeast Frontier Railway
Main contractor name:
M/s Raitani Engineering Works Pvt. Ltd.
Consultant:
Products used:
PARALINK AND PARAGRID
Construction info:
Construction Start: Photo 3. Compaction of material over geotextile
Construction end:
Photo 3. Installed ParaGrid Photo 5. Installed ParaGrid
Soluzioni
per l’ambiente
S. Marco Argentano (CS) Case History
Figura 7
Figura 4
Figura 5 Figura 8
Figura 9
Figura 6
Garanzia di Qualità
La produzione, il sistema di gestione interna e l’assistenza
tecnica sono certificati in conformità alle norme ISO 9002
Problem
A 12 000m² warehouse for storage of thousands of tons of
soya had to be built on of low bearing, silty, fine hydraulic fills
which are up to 4m in depth at the Durban Harbour area.
These hydraulic fills are underlain by silty sand horizons which
are interspersed by sandy clay and sandy clayey silts, which
vary from 2m to about 20m in thickness. Calcareous
sandstone, soft shale and siltstones were also found at depths
of between 25-27m below ground. The water table was at 1.6m
below natural ground. The client needed the structure to be
finished as quickly as possible. The challenge was to provide a
suitable foundation to carry such huge loads, on such poor
founding conditions, in the quickest time.
Solution The top 1.5m of in situ material was removed in readiness of the
A raft foundation of Paralink ™ basal reinforcement was found contraction of a reinforced soil raft.
to be the most cost-effective solution for this problem. Piled
foundations would have served this purpose from a structural
view point, but construction was going to take much longer
than the client was willing to tolerate. Paralink ™reinforcement
did not only offer a fast and sound engineering solution, but a
cost analysis showed that this alternative provided a huge cost
saving as well.
Client name:
TRANSNET PORT TERMINALS
Main contractor name:
LIVIERO
Consultant:
MOORE SPENCE JONES
Product used:
PARALINK™ 600 and 1000
Construction info:
A compacted layer of decomposed granite was placed on top of
Construction date: 09 MAY 2009 the geotextile followed by the first layer of GeoGrids of
Completion date: 17 JUNE 2009 ParaLink™600 and ParaLink ™1000
Page 1 of 2
CASE HISTORY
ZAF / CH / 058 Eng - Rev. 00 , Aug 2009
VALLEY TERMINAL
RICHARDS BAY, KZN
GEOTECHNICAL ENGINEERING/ EMBANKMENTS ON SOFT SOIL
Product: Paralink ™, ParaWeb™
Problem
Two 5000 m² warehouses for storage of thousands of
tons of sulphate had to be built on of low bearing, silty,
estuarine area. The ground was unable to carry the high
loads and engineering solution was needed to provide a
suitable foundation to carry the large loads as
economically and possible and with the fast construction
programme.
Solution
A piling solution to meet the loading requirements was
ruled out as to slow and to expensive. A raft foundation
The ground was too wet and too soft even for pedestrian access
of ParaLink™ 300 basal reinforcement laid on a pre- necessitating in pioneer paths being laid to provide access for
consolidated base using the dynamic compaction and soil sampling.
replacement method was found to be the best solution
for this problem. ParaLink™ 300 reinforcement did not
only offer a fast and sound engineering solution, but a
cost analysis showed that this alternative provided a
huge cost saving as well.
Design Features
Knowledge of the geology of the area and very specific
soil details are necessary for any basal reinforcement
design. In this project the Dutch Probe tests, DCP,
boreholes, inspection pits, etc were all carried out to
determine the site conditions. The level of the
groundwater table was also determined.
The rolls of ParaLink™ 300 were unrolled into position and then
covered with structural fill.
Client name:
RICHARDS BAY MINERALS VALLEY TERMINALS
Main contractor name:
LEO MAT
Consultant:
GEOTECH MOORE SPENCE JONES
Product used:
PARALINK™ 300, PARAWEB
Construction info:
Construction date: November 2007 The limiting factor was the availability to provide a structural
Completion date: December 2007 cover at the same rate that the ParaLink™ 300 was laid.
Page 1 of 2
Maccaferri SA (Pty) Ltd reserves the right to amend product specifications
without notice and specifiers are requested to check as to the validity of the
specifications they are using.
Benefits
The laying of ParaLink™ 300 is easy and simply entails
unrolling the roll of ParaLink™ 300 onto well prepared
ground and then cover with a selected granular fill,
compacted as per specification. The rate of construction
was therefore very quick, the contractor was able to lay
an average of 1000m² of ParaLink™ 300 per day and
completed the 11 000 sq metres raft foundation in six
weeks on time and on budget.
www.maccaferri.co.za
Page 2 of 2
MACDRAIN REFERENCES
SELECTED MACDRAIN PROJECTS - Flat applications under embankments
YEAR: 1999
LOCATION: UK
COMMITTENT: -
CONTRACTOR: -
APPLICATION: -
MACDRAIN: N 1051– 300,000 m2
YEAR: 2004-2005
LOCATION: KAZAKHSTAN
APPLICATION: Anticapillarrity and drainage layer at the base of the road embankments
YEAR: 2004-2006
LOCATION: ITALY
APPLICATION: Anticapillarrity and drainage layer at the base of the road embankments
YEAR: 2004-2006
LOCATION: ITALY
Drainage layer at the base of the enlarged embankments (type N 1081) and
APPLICATION:
vertical drainage behind concrete structures (N 1050)
YEAR: 2004-2006
LOCATION: ITALY
APPLICATION: Anticapillarrity and drainage layer at the base of the railway embankments
LOCATION: ITALY
APPLICATION: Anticapillarrity and drainage layer at the base of the railway embankments
LOCATION: ITALY
CANAL LINING
HARYANA,INDIA
CANAL LINING
Product:Mac Drain N - 105 M
Problem:
Haryana Irrigation department has taken up construction work of canal
with concrete lining. The canal section has a cross sectional length of
about 16m and the total length of the canal is about 65 km.
A major portion of the canal, around 30 km, exists in cut section where
high level of pore water pressure is expected to act on the proposed
concrete lining.
The expected uplift pressure on concrete lining necessitates provision
of elaborate drainage arrangement underneath the lining and as a safe-
guard an additional thickness for the lining.
Haryana Irrigation department was looking for alternatives solutions
which will be technically better and cost effective to overcome from
problem.
Product Used:
- Maccaferri Drainage Composites reduce pore water pressures. Photo 2. MacDrain N - 105M
- This enables threatening saturated ground conditions to be avoided.
- Simple and fast to install, this system cuts the cost of conventional
drainage systems and gives superior performance.
Client name:
Haryana Irrigation Department
Main contractor name:
Mehta Construction company
Consultant:
Products used:
MacDrain N - 105M - 3,49,000 Sq.m
Construction info:
Construction Start: February 2009
Photo 3. Leveling of surface before laying Drainage
Construction end: 2010 composite
Drainage composite
Mac Drain N - 105 M
Photo 4.Unrolling of Drainage Composite Photo 5. Laying of Drainage Composite using Machine
Drainage composite
Concreting
Advantages :
Other Details:
Permeability of soil is approximately 2x10-4 cm/sec.
FLOW RATE OF GEOCOMPOSITE:
Considering Hydraulic gradient = 1
Flow rate = 100 lit/Sq.m./sec @ 100kPa.
Photo 10 : Finished Lining
Problem
Client: NHAI
The Gurgaon-Kotputli-Jaipur on NH-8 is a high traffic corridor Designer / Consultant: Maccaferri (Designer) / CEG
(km 42.7 to km 273.0) connecting Haryana and Rajasthan. and SNC Lavlin
The corridor was four laned as part of NHAI’s Golden Contractor: M/s. NKC Projects Ltd.
Quadrilateral project. Due to high traffic congestion, this
Products used (Qty.)
four laned road was proposed to be developed into six lane.
- MacDrain N 34,800 sqm
It was decided to construct a masonry wall along the Date of construction: 12/2009 - 02/2010
highway to retain the embankment. As per MORTH
requirements, 600mm thick gravel filter shall be provided
behind retaining wall as a drainage media to quickly drain
off excess pore water which may develop behind the wall.
Weep holes were provided throughout the length of the wall
to drain out the seepage from the backfill.
Solution
Advantages of MacDrain:
- Effective solution compared to gravel drain.
- Non-biodegradable.
- Being factory made, high quality is ensured.
- Convenient to install.
- Economical.
- Eco-friendly.
Photo 5: Seepage noted from weep holes Photo 6: MacDrain® retrieved after test
.
CASE HISTORY
Rev: 1, Issue Data 08.10.2020
Problem
Client: Road & Buildings Department, Bhavnagar
Bhavnagar is a city in the state of Gujarat situated 198 km Designer / Consultant: Road & Buildings Design
away from the state capital Gandhinagar. This proposed Circle
Creek Kalatalav Sanesh road is the approach road to Contractor: Kalathiya Engineering & Construction
Bhavnagar District and for the nearby Salt Industries as well.
Ltd
The proposed road is formed between the creeks, where the Products used (Qty.)
ground water table is high and flood level is also high during - MacGrid EG 90,888 sqm
the monsoons. Also, sub grade strength was found to be of - Road Mesh 1,41,775 sqm
CBR less than 2 percent with poor soil properties. The road - ParaLink 91,789 sqm
used to demand high maintenance and repairs cost. - Gabion 38,329 cum
- MacDrain N 27,817 sqm
Solution
- MacTex N 1,55,779 sqm
R & B department referred the problem to Maccaferri for the Date of construction: 07/2011 - 06/2012
improvement of 14 km length proposed road. Ease and
speed of construction was a key element in the design
selection process. Considering the site conditions and poor
soil properties, Maccaferri suggested a composite that will
offer the design strength for road pavement construction
necessary for this project.
.
7. Technical Specifications
Table 1
Mechanical:
Hydraulic:
2. Method of measurement
Quantity of filter geotextile shall be determined from cross sections and the linear distance and
paid for under the appropriate bid items.
3. Basis of Payment
Accepted filter geotextile shall be paid for at the unit price (per square metre area) for each pay
item included in the contract.
4. Method of Testing
The supplier has to submit a Certificate of conformity for the parameters indicated in Table 1 for
every lot/shipment.
Providing and laying of high strength uniaxial flexible BBA Certified geogrids
with polyethylene coating with minimum long-term strength for 120 years
1) Scope of work
This specification covers the use of high strength uniaxial geogrids for Basal
reinforcement (as per IRC 113) including the scope of furnishing and installation as
per the special provisions mentioned in the specifications, instructions from the
manufacturer/supplier and as directed by the Engineer-In-Charge.
All high strength uniaxial geogrids shall be new and undamaged. Materials which are
not new or damaged will not be accepted. These shall follow the design as shown and
mentioned in the manufacturers set of drawings for the pavement application.
• The company providing the materials must demonstrate the High strength
Geogrid products have been used and proven in Embankment structures.
• The company must have proven ability to manufacture the required shapes of
the high strength uniaxial geogrids.
The manufacturing facility shall operate under a management system that is 3 rd party
certified to ISO 9001:2015 standards. The high strength geogrids shall be
manufactured in such a way so as to ensure an efficient and durable reinforcement
system suitable for pavement applications.
Prior to the supply of the material the supplier or manufacturer should ensure that the
ParaLink shall meet the requirements as specified in the Tables 1&2. Conformance
testing shall be performed on random samples by the manufacturer or supplier in
accordance with approved quality control practices and form accredited test
laboratories.
After the finalization of the supplier, ParaLinks shall be provided for the testing. The
tests that are to be carried out are Tensile strength (MD), Elongation (MD), Puncture
Resistance, Apparent Opening size and permittivity and the tests should meet the
requirement as per Tables 1& 2.
III) Material
The geogrid for basal reinforcement shall be high strength flexible geogrid with a high-
quality coating like LDPE or equivalent. Latex or PVC or modified bitumen coating or
geotextile shall not be permitted. The geogrid shall be manufactured from polymeric
strips comprising of tendons made from high tenacity polyester fibers concentrated in
separated bundles and encased in a durable polyethylene sheath. The polyester yarns
are placed in tension and polyethylene is then co-extruded on to the polyester to form
polymeric strip. The polyethylene sheath used on geogrid shall act as a chemical
barrier and also provide protection against any form of installation damage. The
selection of the geogrid needs to be strictly based on the long-term design strength
values for a design life of 120 years at 30°C.
The long-term design strength shall be derived as per guidelines given in ISO TR
20432 for design life of 120 years and design temperature of 30C considering
following factors
Tallow = TUTS / RF
RF = RFCR x RFID x RFW x RFCH x FS
Tallow = Allowable tensile strength
TUTS = Ultimate tensile strength
RF = Reduction factor
RFCR = Reduction factor for creep
RFID = Reduction factor for the effect of installation damage
RFW = Reduction factor for weathering
RFCH = Reduction factor environmental degradation (chemical and biological) at the
service temperature
FS = Reduction factor related to the mass of information available and to the production
quality.
The adoption of reduction factors should be strictly based on reliable test data and
performance data available with the manufacturer from accredited independent
agency or the manufacturer should provide a valid third-party accredited certification
like BBA (British Board of Agreement) certifying the Reduction Factor (RF) value for
their geogrid for design temperature of 30°C and design life of 120 years. Manufacturer
should have creep test data from independent accredited laboratory for period over 10
years at design temperature of 30°C.
Table (1) Minimum RF for up to 120 years design life, 30°C temperature
applications
Sr.
Parameter Unit Geogrid grade
No.