1 SHUTTERING WORKS 18 18 36 2 STEEL WORKS 5 2 7 3 MASONRY 13 7 20 4 GENERAL WORKS 16 26 42 5 OPERATORS 6 6 6 TRUSS WORK 19 19 7 CARPENTER 4 4 8 FIRE 2 2 9 EXPANSION JOINT 2 2 10 ELECTRICAL 8 8 11 TILE CLADDING 1 1 2 12 WOOD POLISH 6 6 . 100 54 154 TOTAL 154 Tuesday TODAYS WORK PLANNING 01-7-24 1 ZONE A- Truss work, handrail work 2 ZONE A-Carpenter work 3 ZONE A- Expansion joint work 5 ZONE B- plastering below handrail 6 ZONE B- plumbing work 7 ZONE B- Handrail work 8 ZONE B-Block work SF 9 ZONE B-Electrical work 10 ZONE C- Plastering at SF 11 ZONE C- Truss work 12 ZONE C- Electrical works 13 ZONE C- Lintel work SF 14 ZONE C- Block work at FF, GF,SF 15 ZONE C-Painting 16 MANUSCRIPT- column shuttering work 17 MANUSCRIPT- sunshade shuttering and steel work 18 MANUSCRIPT- porch slab shuttering 19 MANUSCRIPT- outer area plastering 20 COMPOUND WALL-Foundation Drilling work 21 PORCH-Steel work and shuttering work 22 NURSERY-Truss work 23 Spetic tank shuttering work PREVIOUS DAY WORK DONE 30-6-24 1 ZONE A- Truss work, handrail work 2 ZONE A-Carpenter work 3 ZONE A- Expansion joint work 4 ZONE B- painting work 5 ZONE B- staircase plastering 6 ZONE B- plumbing work 7 ZONE B- Handrail work 8 ZONE B-Block work SF 9 ZONE B-Electrical work 10 ZONE C- Plastering at SF 11 ZONE C- Truss work 12 ZONE C- Electrical works 13 ZONE C- Lintel work SF 14 ZONE C- Block work at FF, GF,SF 15 MANUSCRIPT- column shuttering work 16 MANUSCRIPT- sunshade shuttering and steel work 17 MANUSCRIPT- porch slab shuttering 18 COMPOUND WALL-Foundation Drilling work 19 PORCH-Steel work and shuttering work 20 NURSERY-Truss work 21 NURSERY-Laterite block work 22 SEPTIC TANK - shuttering work