Professional Documents
Culture Documents
Proforma Spec - LVSB (Draft 6)
Proforma Spec - LVSB (Draft 6)
Proforma Spec - LVSB (Draft 6)
PARTICULAR SPECIFICATION
FOR
(Brief title description of work in brackets to be inserted, if necessary, to better reflect the scope of
installation in addition to the above description of work category.)
FOR
[PROJECT TITLE]
[PROGRAMME NO. ]
FOR
CONTRACT NO. /
NOMINATED SUB-CONTRACT TO CONTRACT NO.**
[Project Title ]
(Brief title description of work in brackets to be inserted, if necessary)
1.1 Installations/Systems
All equipment, materials and workmanship shall fully comply with the
specifications as stated in the Preliminaries and all current amendments
thereto, unless otherwise specified on the Drawings or in this Particular
Specification.
This Low Voltage Cubicle Switchboard Installation shall include the design,
supply, installation, testing, commissioning and maintain of the low voltage
cubicle switchboard (hereafter called the “Switchboard”), as shown on the
Drawings.
[Note: The 2 systems listed below are core items and if any item is not
applicable in this contract, its heading of such item shall be retained with
"Not Used” to be remarked under the heading. Include material
specification as Section 1, 2, 3, etc as per the standard format. This
proforma specification is a general guidance and is not exhaustive, the
project engineer/officer should exercise their expertise professional
judgement to specify the requirements to meet the project specific needs.]
[Note: Project Engineer shall check with PQS on the list of drawings to be
included in the Preliminaries or to include the drawing list in this
Particular Specification]
*Not Used
*Not Used
[Note: Project Engineer shall list out specific items which require
Contractor’s/Sub-contractor’s design input. The Project Engineer should
discuss with Project Quantity Surveyor in the drafting of this section as
there is a Clause relating to the Design Responsibility of the
Contractor/Sub-contractor in the Special Conditions of Contract, and refer
to the Preliminaries Section of Condition of Contract Clause 23 - Design
Responsibilities.]
1.4 Others
[Note: This is a section allowed for the addition of any particular project
information or supplementary technical requirements, etc., which may
not be covered in either section 1.1 to 1.2.]
For example:
1.4.2 The data received from the digital power analyzers, digital
multifunction meters, digital protection relays and switchgears as per
the requirements in this Particular Specification shall be received by
the CCMS for recording and monitoring. The Contractor/Sub-
contractor** shall be responsible for the integration of the data with
the CCMS including all necessary equipment and tools to ensure the
requirements in this Particular Specification are satisfied. [This
clause is applicable for the works with CCMS that has included in
the other parts of the Contract. Provide the point schedule such as
the open/close, trip/normal, current, kWH, kVA, voltage, etc of main
ACB, outgoing circuits, etc. as an appendix to this Specification]
1.4.3 *In addition to the requirements as per clause C5.24 in the EEGS,
digital power analyzer shall also be able to record and store the data
of the maximum kVA and cumulative kWH of each month at the
interval as per *HKE or *CLP Power tariff requirements. These data
shall be stored in the digital network analyzer for a minimum period
of at least 2 months. A data port shall be located on the fascia of the
analyzer to retrieve the stored data by manually downloading the
[Note: Project Engineer shall list out particular constraints to this installation
work. In case this section is not applicable, “Not Used” shall be inserted instead
of deleting this section. Examples are: -]
*Not Used
*The following conditions shall be complied with in the execution of the work:
*Not Used
For example:
For example:
3.4 Others
*Not Used
*Not Used
(Specify training requirements for special equipment that are not covered in
the EEGS)
4.3 Others
[Note: Project Engineer shall refer to Clause 7(5) of the Special Condition of
Contract for 1999 GCC and BSB Circular 14 of 2003 and BSB Circular No. 40
of 2003 on the detailed requirements for submission of technical information of
the equipment/material for the Approval of the Architect.]
EQUIPMENT/MATERIAL SPECIFIED
Air-circuit Breaker G.S. Clause C5.4
Manufacturer
Fuse Switches/Switchfuse G.S. Clause C5.2
Manufacturer
Moulded-case Circuit Breakers G.S. Clause C5.5
Manufacturer
Automatic Changeover switch G.S. Clause C5.15
Manufacturer
*Annex - 1
[Note: This Annex is supplementary only. Incorporation of this Annex in the
particular specification is at the discretion of the Project Engineer. ]
Notes:
+ Details of load nature i.e. inductive or resistive, motor type, starting method of motor
and starting current.
++ Duty cycle of connected load may include load start/stop point, minimum on/off
time, beginning/ending time of duty cycle periods etc.