Professional Documents
Culture Documents
Proforma Spec_Rainwater Recycling System_29_09_2010
Proforma Spec_Rainwater Recycling System_29_09_2010
PARTICULAR SPECIFICATION
FOR
FOR
[PROJECT TITLE]
[PROGRAMME NO. ]
FOR
CONTRACT NO. /
DOMESTIC SUB-CONTRACT TO CONTRACT NO.*
[Note: This proforma particular specification only specifies the general contractual
requirements and technical specification for the supply and installation of
rainwater recycling installation. The works may be incorporated under the
specialist sub-contract works for air-conditioning installation or as appropriate with
due considerations on project scale and nature. Project officer should address the
particular contractual requirements such as design responsibilities in the particular
specification for air-conditioning installation or as appropriate to incorporate the
scope of rainwater recycling installation works.]
1.1.3 The works shall also include the provisions of operation and
maintenance manuals, trainings and analysis of water
samples.
1.2.7 First flush device shall be designed and provided for first
stage filtering of rainwater before entering into the rainwater
collection tank.
1.3.3 Others
(d) Local motor control panel for the rainwater pump shall
comply with Clause C5.26 of the EEGS.
(d) Each filter tank shall be equipped with inlet and outlet
pressure gauges and differential pressure sensor (for
auto-control backwash) for filtering and automatic
backwashing operations. The automatic backwashing
operations shall also be controlled by timer in the
control system.
(e) The filter vessel shall have suitably sized inlet and outlet
connections, drain connection, access ports and vent
fittings if required. The vessel shall be equipped with
automatic air vent, manual air vent, manual drain valve
and pressure gauge mounted on tank for accurate
reading.
(e) All plant room valves and circuit control valves shall be
provided with approved plastic labels. A circuit control
diagram of appropriate size showing the location of
each isolating, regulating and control valve shall be
provided and fixed in a glazed hardwood frame in a
position indicated by the *Architect /Supervising
Officer.
(b) The control system shall interface with the water level
sensors in the rainwater collection tank, mixing tanks
and UV disinfection system such that the UV lamp will
only be operated a certain period before the operation of
the filtration and treatment plant. A minimum of 2
minutes warm-up time for the UV lamp is required
before the operation of rainwater treatment plant.
(b) The interfacing points shall include, but not limited to,
the following:
The following conditions shall be complied with in the execution of the work:
[Note: Project Engineer should list out special items not being
covered by existing Testing and Commissioning Procedures for
which the relevant applicable particular testing and commissioning
requirements shall be specified under this sub-section. In case this
sub-section is not applicable, "Not Used” shall be inserted instead of
deleting this sub-section. Examples are as shown below:-]
- E-coli (number/100mL)
- Legionella (number/litre)
- Total coliforms (number/100mL)
- Suspended solids (mg/litre)
- Turbidity (NTU)
- 5 days biochemical oxygen demand, BOD5 (mg/litre)
- Residual chlorine (mg/litre)
- pH value
(c) Water samples shall be taken from the mixing tank and the
far end points of the distribution pipeworks or water draw-
off points. It is preferable to collect water samples just
before the recycled rain water enters the mixing tank.
Sampling tap, if provided, shall be run for at least 10
seconds with the recycled rain water discharged to the
drainage system prior to sampling. The sampling tap shall
be flushed at least once a month.
3.4 Others
4.1.4 At the end of the defects liability period complete inspection and
tests shall be carried out on the plant by the *Contractor /Sub-
contractor with the presence of the *Architect’s representative
/Supervising Officer’s Representative, any defects found shall be
rectified by the *Contractor /Sub-contractor without charge to
the Employer.
4.1.5 A log book shall be provided and kept in the plant room to
record all faults, rectification works and services carried out by
the *Contractor /Sub-contractor during the maintenance period.
4.3 Others
[Note: This schematic diagram should be deleted if particular system design drawings
are provided by the Project Engineer and to be incorporated into the tender
drawings.]