Professional Documents
Culture Documents
ukcsts007_iss1am02
ukcsts007_iss1am02
Contents
Paragraph Page
Uncontrolled
1 Introduction 1
1.1 Help Notes 1
Contents (cont’d)
Paragraph Page
6 Environmental Management 23
6.1 Environmental Policy 23
6.2 Environmental Programme 23
Uncontrolled
Figure
1 XXX Operation HSE Programme Structure 4
2 HSE Risk Management Model for Projects 15
Addendum 1 References
Issue Authority
Name: Jon Turnbull
Signature: ________________________________________________
Date: ________________________________________________
Technical Authority
Name: David Aberdeen
Signature: ________________________________________________
Date: ________________________________________________
Amendment Record
AMOSAF.171
Amendment Summary
Distribution List
Virtual Copyholders
Copy Copyholder
Uncontrolled
Preface
Purpose
This Health, Safety and Environment (HSE) Philosophy is for UK operation’s offshore projects,
ranging in size from material changes (as defined in the Safety Case Regulations) to new major
Installations. It provides a framework and the guiding principles for a project HSE Management
System as the basis for compliance with Getting HSE Right (GHSER) and legislation.
The philosophy is given in the form of a template (see below) that can be made project specific.
(Please note that this template is available online only.)
Uncontrolled
Given the foundational nature of the Philosophy, some subjects inevitably relate to the entire
lifecycle of the operation, from concept through to decommissioning and abandonment. This is
particularly true for risk management.
In the case of an existing operation, the completed Philosophy will have been prepared by the
Business Unit and given over to the project who formally accept and comply with it.
In the case of a new project or a ‘Create Asset’, the Philosophy will normally be prepared as a
high-level document and feature initially in the operation’s suite of project manuals.
The Philosophy has equal weighting to the Statement of Requirements and the Operating and
Maintenance Philosophy.
An HSE functional endorsement of the completed Philosophy is required.
Document Status
The basic principles and much of the detail in this document is valid. However, it needs to be
updated to cover developments since it was issued in 1996.
Areas requiring update include:
• Paragraph 4.2 updating based on GHSER instead of Operations Integrity Assurance
System (OIAS)
• Paragraph 4.5 to incorporate the implications of the Capital Value Process (CVP)
• Paragraph 5 to incorporate the new Group Risk Acceptability Criteria when adopted
(expected by the end of 2Q 2001) and the interpretation of the requirements of the Design
and Construction Regulations (DCR)
• Paragraph 6 to include the latest environmental expectations and initiatives
• Updating of references to internal documents and legislation
Responsibility of Copyholders
Uncontrolled
It is the responsibility of the registered copyholder of controlled hard copy versions to
maintain the accuracy of the document by ensuring that all updates are promptly
incorporated and acknowledged.
Furthermore, the registered copyholder of controlled hard copy versions must at all times
maintain custody of this document unless prior approval is given by the relevant
Technical Authority.
The roles and responsibilities of copyholders and ‘virtual’ copyholders are detailed in Section 1
of the Document Control Procedure (UKCS-DCM-001).
List of Abbreviations
1 Introduction
The Health, Safety and Environment (HSE) Philosophy is based on the standard SMS
document UKCS-TS-007, as applied to all BP UK projects and is compliant with BP's
Getting HSE Right (GHSER).
It incorporates only those changes appropriate to making it specific to the
named project.
Although presented in the context of projects, the Philosophy is applicable to the entire
operation. The phases of an operation are:
(1) Concept selection.
(2) Front-end Engineering Design (FEED).
(3) Detailed design.
(4) Construction, inclusive of fabrication, build, load-out, transportation, installation
and hook-up.
(5) Commissioning.
(6) The operating phase.
(7) Decommissioning.
(8) Abandonment.
The Philosophy may be introduced at any stage.
Ideally, for a new project or ‘Create Asset’, the Philosophy would be applied from the
beginning, at the concept selection.
The terms ‘will’ and ‘shall’ have been used in this template Philosophy as though from the
client issuing authority.
The Philosophy is applicable to an alliance arrangement also. In this respect,
the selection of all the alliance members would be influenced by this Philosophy and
based on their capability of complying with it to ensure consistency and compatibility
across all project areas.
Finally, a point worthy of note is that project HSE budgets, inclusive of study
programmes and loss control effort, historically, have been prone to underestimation.
A sensible guide is to allocate a budget of 1% of the capital cost of the ‘£50M’ project
and about £5M for the larger ‘£1 bn’ project.
Ordinarily the HSE Philosophy is prepared in conjunction with the project.
The project is subject to the HSE Philosophy from which it develops its HSE
management system. A key component of this management system is the HSE plan.
For ‘Create’ and ‘Existing Assets’ the Philosophy would normally be prepared and owned
by the Asset.
In the case of a new project where an Asset is not yet established, the Philosophy may
be prepared on behalf of UK Operations Management for ownership by the
eventual Asset.
In any case, it is important to make the distinction that approval of the HSE Philosophy is
essentially independent of the project and that it is accepted and applied by the project.
Approved by: Name
Manager, XXX Asset Date:
Accepted by: Name
Uncontrolled
Manager, XXX Project Date:
Endorsed by: Name
Management, HSE Function Date:
Endorsement by an HSE function is in accordance with the ‘Asset Manager’s
HSE Obligations’, HSQ 00.02.02.
The overall HSE requirements for the XXX Project are set by BP’s HSE Commitment
(Addendum 1 Ref 1) and by GHSER (Addendum 1 Ref 2).
This HSE Philosophy has been prepared in line with the GHSER (Addendum 1 Ref 2).
It sets out the basic HSE framework and objectives required of XXX Project.
The Philosophy is a companion document of equal standing to the project Statement of
Requirements (SoR) and the Operations and Maintenance (O&M) Philosophy and should
be read in conjunction with them.
Detailed HSE requirements will be addressed in a separate project HSE plan.
A model project HSE plan is available in the Guidelines for Preparing a Project HSE Plan
(UKCS-TS-008).
Uncontrolled
thoroughly understood as it not only presents the 13 elements but lists also the
expectations of all BP senior management for all BP activities in direct response to the
BP’s HSE commitment.
It is imperative, therefore, that the project HSE management system is based on these
elements and the expectations that underpin them, and that nothing is missed.
(1) Leadership and Accountability
• The project management will be required to provide the perspective, establish
and implement a proactive HSE Management System and provide the
resources for success in HSE
• The project will be required to establish the scope, priority and programme of
HSE work for its phase of the operation. It will set the expectations and set the
performance criteria that equates to, or exceeds, current UK Upstream
Region equivalents
• Operations integrity will be assured through visible project management
leadership and commitment, and through accountability at all levels
(2) Risk Assessment and Management
• Risks, in respect of people, facilities and the environment, will require to be
identified and managed throughout the lifecycle of the operation
• The project will be required to establish a system of risk management which
ultimately will be continued by the operating Business Unit
• Risks will require to be minimised and reduced to a level As Low As Reasonably
Practicable (ALARP)
• There will be a process of continued management of HSE risks
• The project will be required to assign responsibilities and accountabilities
particular to risk management for its phase of the operation
• The project will be required to assess, proactively, the implications of all its
activities, set priorities, develop action plans and review progress regularly.
Accordingly, project will be required to:
- Identify sources of HSE risk and hazards
- Assess the consequences and probabilities
- Evaluate and implement a balance of prevention, control and mitigation
measures
• The project will be required to set performance standards against which the
acceptability of the new facilities may be assessed and demonstrated. In this
regard, the project will adopt the UK Operations (UK Ops) criteria and study
methods in its assessment and documentation of HSE risks
(3) People, Training and Behaviours
Uncontrolled
• A system will need to be established by project for the selection and placement
of qualified and competent personnel to meet specific job requirements against
detailed terms of reference
• The operating Business Unit will do likewise and set up systems of training and
performance assessment in readiness for operational input to project and
ultimately for commissioning and operating the facility
(4) Working with Contractors and Others
• Third-party services and performance requirements will require to be specified
by project
• Third parties will be evaluated and selected with due consideration of their HSE
management capabilities, performance and ability to integrate with project
• All Interface requirements will be identified
• The performance of third parties will require to be monitored throughout the
period of service
Note: Strictly, this element must apply to the selection of design contractors,
fabrication contractors, transportation, heavy lift contractors and other
service providers, and also to the selection of all members in an Alliance
arrangement.
(5) Facilities Design and Construction
• An SoR and an O&M Philosophy will require to be developed for the design,
construction, commissioning and intended operation
• It will be a requirement of project to meet or exceed legislation
• The project will be required to select and apply approved standards and best
practices which ensure inherent safety and ensure health and environmental
risks are minimised in the design, construction and intended operations
• Project systems will be required for the control, authorisation and recording of
deviations from practices and standards
• The operating team will be required to become fully resourced and trained and
the operations HSE Management Systems fully implemented for the
commissioning and transition to the operating phase
• The change over to Business Unit will require to be a seamless and natural
progression of project’s HSE Management System
(7) Management of Change
• Systems will require to be put in place for the express purpose of identification,
management, authorisation and documentation of all temporary and permanent
changes that may be required during each phase of the project
• All proposed changes will be assessed as to the impact on HSE risks and
measures taken to ensure the risks remain acceptable against the UK
operations and legislative criteria, and project performance standards
(8) Information and Documentation
• Project will be required to operate and maintain an HSE information and
document control system that can be handed over and effectively continued by
the operating Business Unit. The system developed will be compatible with the
requirement of the operator
• Responsibility will be assigned for documentation control and systems set up
for safe storage and easy access of all drawings, hazard data files, facility
changes, maintenance and inspection records, HSE reports, correspondence,
codes, legislation and computer files
• Applicable regulations, permits, codes, workplace standards and practices will
be identified and conflicts resolved
• Project and Business Unit requirements will be documented and communicated
to all those affected
• Publication and distribution of HSE information within project will require to be
undertaken to accomplish a sound and positive HSE culture
Uncontrolled
• Equipment, facilities and trained personnel to handle emergencies will be
defined and readily available, and exercises will be performed to ensure
continued preparedness in the event of an accident or incident
(12) Incidents Analysis and Prevention
• All safety and environmental accidents, incidents and significant near misses
will be subject to investigation and analysis
• A central system for reporting, investigation and assessment will need to be
developed by project which ultimately will be carried forward into the operating
phase of the operation
• Findings will be periodically examined to identify common themes which can be
targeted for preventative attention
• All accidents and incidents will be shared openly within the project
and operation and across BP as lessons learned. In this regard, project will
be required to take cognisance of lessons learned from other projects
and operations
Note: For projects involved with existing operations, the addition of a statement
to the effect that project will adopt the operation’s system of incident
investigation and analysis, might be more appropriate.
(13) Assessment Assurance and Improvement
• Measurable goals will require to be developed and performance against them
assessed to facilitate continuous improvement throughout each phase of
the operation
• A process for self assessment of progress toward operations integrity goals will
be developed
• The project and Business Unit alike will be subject to an agreed programme.
Systems will be put in place for the resolution of findings and for measuring the
effectiveness of the assessments
Uncontrolled
• Commitment to GHSER throughout all areas
• Demonstration of:
- Compliance with GHSER
- Alignment with GHSER for third parties and contractors
- Compliance with the legislation
• The development of the design, construction, commissioning and intended operation
are HSE risk driven
• The selection of appropriate alliance members, third-party services and vendors are
compatible with the project’s HSE management system
• The HSE Philosophy and Plans are understood by all parties and project personnel
• Sufficient and competent resources are employed to meet the project’s HSE policy
• Responsibilities, accountabilities and lines of communication are clearly defined
• The project’s schedule of deliverables includes programmes of HSE-related
study work
• Safety Cases and notifications are prepared to the standard BP format and submitted
according to an agreed programme for Health and Safety Executive acceptance and
comment as appropriate
• Procurement of material, equipment and supplies includes consideration of HSE
requirements
• All necessary HSE information is made available to the appropriate personnel;
eg legislation, standards and codes of practice both internal and external to BP
• All HSE issues, recommendations and concerns are formally recorded and monitored,
and are satisfactorily addressed and closed out
• All decisions with HSE implications are recorded and the appropriate personnel are
made aware of them
• Quality and integrity of HSE study work is kept to an acceptable high standard
• All changes (design, construction etc), are subject to authorisation and the HSE
implications are assessed and recorded
• Deviations from accepted codes and standards are formally registered and authorised
• The project is subject to self-regulation
• Contractors are audited by the project against agreed performance criteria
• The project is subject to a formalised programme of external UK Operations audits,
inclusive of Quality Assurance (QA), technical safety, medical and environmental
• The HSE management system is robust to potential audit by Internal Audit Unit (IAU)
and/or the Health and Safety Executive
The project will be required to develop and implement an HSE plan, or plans covering:
(1) Concept selection.
(2) FEED.
(3) Detail design.
(4) Construction, inclusive of fabrication, build, site testing and site commissioning,
load-out, transportation and offshore hook-up.
(5) Offshore commissioning, inclusive of handover to the Operator.
Refer to Figure 1.
Paragraph 4.5 may be tailored to suit the size and type of project and the relationship
with existing operations. The model plan, HSQ 01.05.24, provides a basis for the
development of HSE plans.
The plan(s) will contain a statement on the Project Manager’s commitment to GHSER.
It (they) will give a detailed account of the project HSE management system for
achieving GHSER and legislative objectives.
The principal components of the plan(s) will be the project HSE management system,
risk management (refer to Paragraph 5), environmental management (Paragraph 6) and
Safety Case management (Paragraph 7). The plan(s) will detail also the HSE programme
of safety-related work and deliverables.
The HSE programme will be linked to the project schedule to ensure that all
safety-related work is performed proactively and in a timely manner to meet project
milestones and ensure that HSE activities are risk driven.
Uncontrolled
Manager and project line management. Accountability will be assigned and
demonstrated throughout the entire line management chain to ensure that there is
individual commitment for HSE at every level of the organisation.
The Project Manager will be formally responsible for identification and utilisation of the
necessary resources to ensure that legislation, GHSER objectives and the corresponding
project HSE policy can be met. He will ensure that at all times he has the necessary
competencies in his team to assure the efficient and safe discharge of his
responsibilities. In addition the Project Manager will be responsible for ensuring that
third parties, contractors and service providers employed by project have the capability
of an effective equivalent competency standard.
Where project activities take place within areas under the operational control of others,
the Project Manager will be directly responsible to the operational management for
these activities. In such circumstances, the project will ensure that its activities conform
to the requirements of the operational HSE management system.
An individual will be nominated with responsibility for co-ordinating and monitoring
implementation of the HSE plan(s) and will report direct to the Project Manager.
Responsibilities will also be assigned for the each of the HSE deliverables.
4.10 Procurement
The model contract clauses (Addendum 1 Ref 5) will be used in the procurement of
services and equipment.
Uncontrolled
(5) Commissioning.
(6) The operating phase.
(7) Decommissioning.
(8) Abandonment.
Risk management for the operation will be based on the ‘Risk Management Model’ as
indicated in Figure 2, and will be developed integral to the HSE plan(s).
Risk management will ensure that all HSE risks appropriate to the operation are
satisfactorily addressed. It will provide compliance with GHSER (Addendum 1 Ref 2) and
the Safety Case Regulations (Addendum 1 Ref 8) and the PFEER Regulations
(Addendum 1 Ref 9).
For a material change to an existing operation the above paragraph could be: The Project
shall comply with the XXX Operation Risk Management to ensure that all HSE matters
are satisfactorily addressed in compliance with the requirements of GHSER,
and the Safety Case and PFEER Regulations (Addendum 1 Refs 8 and 9).
UK Operations’ definition for a material change can be found in Change Management
and Material Change Criteria (UKCS-TS-005).
The process of risk management will be started at the concept selection and be
progressively developed into maturity through the FEED and project phases and
continued in the operating phase. It will also include consideration of future
decommissioning and abandonment as required by the Safety Case Regulations
(Addendum 1 Ref 8).
In compliance with the offshore regulations and GHSER, risk management must be
inherent to the operation from the start, at the concept selection, and be continued
throughout each of the project phases, through the operating phase and onto
decommissioning and abandonment.
HAZARD IDENTIFICATION
PERFORMANCE GOALS
• FIRE/EXPLOSION (GIVEN)
HAZARD PREVENTION
• COLLISION
(FIRST PRIORITY) • CORPORATE HSE POLICIES
• TRANSPORTATION
• OCCUPATIONAL • OPERATIONS INTEGRITY
• OTHERS ASSURANCE SYSTEM
CONCEPT SELECTION • LEGISLATION
DESIGN OPTIMISATION
PERFORMANCE GOALS
(SELECTED)
OPERATIONS OPTIMISATION
• HSE MANAGEMENT SYSTEM
• HSE POLICIES
YES • INDUSTRY STANDARDS
CAN HAZARD BE PREVENTED? • BP CODES AND PRACTICES
• HSE PRACTICES
NO
Uncontrolled
HAZARD CONTROL
(SECOND PRIORITY)
HAZARD MITIGATION
(THIRD PRIORITY)
PERFORMANCE MEASURES
NO
IS ALARP ACHIEVED?
YES
UKCSTS007_002.ai
Uncontrolled
(2) Risk reduction shall follow the priority:
(a) Elimination of the hazards as the preferred solution, and where this is
not possible.
(b) Provision of control measures as a second option only.
(c) Provision of mitigatory measures, as the very last option.
(3) The acceptability of the risks shall be judged against set performance criteria (refer
to Paragraph 5.2), inclusive of UK Operations and legislative criteria.
Note: The Health and Safety Executive has made it clear that it expects
‘new Installations to demonstrate significantly higher standards’; that is
to say, higher standards than those achievable on the older Installations
that existed at the time the Safety Case Regulations were introduced.
(4) The risks shall be reduced to As Low As Reasonably Practicable (ALARP) and
ALARP shall be demonstrated (Addendum 1 Ref 10).
(5) The HSE risks shall be subject to a programme of continual improvement
throughout the lifecycle of the operation.
For modifications and material changes to an operation, an example policy
statement could be:
'The project will adopt a risk policy whereby any potential increase in risk that
might otherwise occur as a result of the new equipment will be offset by
implementation of identified risk reduction measures to existing systems.’
Under this statement, the overall risk picture may either remain unchanged or,
indeed, be reduced. The chances of an increase in risk will be low and, if it does
happen, will probably be marginal and, in any event, must be ALARP.
Uncontrolled
5.2.2 IR Acceptability Criteria
The operation shall comply with the XEU risk acceptability criteria statement
(Addendum 1 Refs 10 and 11) in respect of individual risk. Accordingly, the IR shall be no
greater than 10-3 per annum for those at most risk and the IR shall be subject to the
ALARP principle.
Essentially:
• Performance goals are high-level performance statements, eg an effective emergency
response will be developed
• Performance standards are applied precisely to systems or equipment where analysis
has shown the need for a performance better than the industry standard
• Performance measures are criteria that require to be validated by defined inspection
and testing routines in order to ensure the specified performance continues to be
achieved. Performance measures may be an industry standard or a performance
standard (defined above) or a combination of both
Performance goals will be applied to the operation as a whole and to major systems that
make up the operation.
Examples of high-level performance goals are:
Uncontrolled
• Emergency systems
• Emergency response
Performance standards and performance measures will be applied to the systems and
subsystems of the operation, particularly those that make a measurable contribution to
the protection of life.
Examples of performance standards and measures are:
• TR endurance time
• Fire and gas detection
• Process trips
• Human impairment, heat and smoke
• Firewall endurance times and performance
• Fire pump availability
• Air breathability in TR
In addition, the following references will require to be used in the development of the
criteria:
• Impairment criteria for personnel and Installation hardware (refer to UKCS-TI-012)
• Guidance on the Design of Instrumented Protective Systems (refer to UKCS-TI-022)
• Assessing smoke and gas ingress (Addendum 1 Ref 20)
• Ship collision risks (Addendum 1 Ref 21)
• Loss potent matrix (Addendum 1 Ref 22)
A list of actual performance criteria must be produced, perhaps as early as the concept
phase. If it does not make this document too cumbersome, then the list can be
produced here or as an appendix, otherwise it would be developed for the statement of
requirements or the basis of design and the HSE plan. The list can be altered at any time
but, be careful, such a move could severely impact concept selection or the design or
the intended operation.
For modifications and material change type projects, the performance criteria already
established for the operations would probably be applicable, especially those quoted in
the operations Safety Case.
In some cases, however, the operation may impose additional performance criteria such as:
• Environmental, emission are not to exceed (some factor); or
• Environmental emissions are to be reduced by (some factor)
Uncontrolled
5.3 The Formal Safety Assessment Programme
The scope and timing of the individual studies that make up the Formal Safety
Assessment (FSA) programme will be sufficient to enable informed and confident
decision-making in the development of the operation and to enable the demonstration of
acceptable risk and acceptable risk reduction.
From an HSE standpoint, the development of the operation is risk-driven. It follows that
the FSA programme is crucial to ensuring that HSE issues are addressed in a timely
manner so as to:
(1) Avoid delays.
(2) Avoid unplanned corrective expenditure.
(3) To ensure that CAPEX and OPEX is not wasted but is directed to areas that give
measurable effective risk reduction benefit.
The FSA programme as a discrete function within the HSE plan formalises the distinction
between the technical safety engineering work required of the risk management and the
general prevention and loss control type engineering.
Note: Steps (1) to (5) below may be edited corresponding to the scope and phase of
the project.
(1) Concept Selection
Risk management will be a major contributor to concept selection, equal to
technical and commercial needs. It will provide a generic view of the operation and
the hazards likely to be involved for each of the options under consideration.
Risk ranking will be performed to help in the selection process. It will include
consideration of construction, commissioning, operating, decommissioning and
abandonment.
It is likely that BP corporate high-level performance goals need only apply at this phase
unless the project is concerned with a material change to an existing operation.
At this stage, industry standards and generic data only may be used to provide the
appropriate level of accuracy required of the HSE studies.
Limiting the concept selection to industry standards and making use of generic
data is likely to be more than adequate at this stage. It simplifies the HSE study
work and, hence, saves on time and costs.
By using national and international codes, Company codes and lessons learnt, the
concept finally selected will be at least as good as the industry standard.
An HSE report will be required of concept selection. It will present the rationale
behind the option finally selected and give an account, specifically, that risks and
environmental issues have been addressed satisfactorily. It will give justification for
proceeding to FEED. The report will ultimately provide input to the Design
Safety Case.
Uncontrolled
(2) FEED
At this stage risk management becomes less generic and more specific to the
selected option.
A Concept Safety Evaluation (CSE) will be required of FEED. This will provide a
good indicator of the overall risk picture likely to be achieved and the major risk
drivers particular to the operation. In addition, it will provide demonstration of risk
minimisation and the potential for ALARP.
The CSE will include, but not be limited to:
• Fire and explosion
• Emergency response
• Smoke and gas ingress
• Emergency systems
• Quantified Risk Assessment (QRA)
Specifically, the IR and the TR impairment will be quantified to a degree sufficient
to confirm and demonstrate that the risks will be acceptable for the operation and
that there exists potential for further risk reduction.
Performance criteria specific to the operation will be established.
Assurances will be given that these performance criteria have been, or can be, met.
The CSE, together with the concept selection report, will provide the basis for the
preparation of the Design Safety Case.
The CSE is sometimes referred to as the CSA (Concept Safety Assessment).
For the smaller project, producing a distinct CSE(A) and then incorporating the
findings in the Design Safety Case may not be an efficient way of working. In such
cases it is in order to complete the CSE(A) study work for direct input to the
Design Safety Case rather than produce a separate CSE(A) report. The Design
Safety Case becomes, in effect, the CSE(A).
Uncontrolled
during FEED. Risk-sensitive systems and equipment will be identified that may
require more detailed scrutiny and possible changes in order to meet the stipulated
performance standards.
HSE assumptions will either be validated or reworked to ensure that, in reality,
the performance criteria can actually be met.
The FSA programme, will provide the basis for the preparation of Safety Cases and
notifications required of the Safety Case Regulations (Addendum 1 Ref 8).
(4) Construction Phase
The minimisation of construction risks will be fundamental to construction.
Potential major accident events and occupational hazards will be addressed.
Construction tasks will be subject to Task Risk Assessments (TRAs) (Addendum 1
Ref 23) and in some cases may be subject to QRA.
(5) Offshore Commissioning and the Operating Phase
The risk management developed by the project will be taken over by the Operator
and integrated seamlessly into the Operations HSE Management System. It will be
maintained throughout the life of the operation until decommissioning.
The policy of reducing risk will be continued. For Installation alterations and
material changes, risk reduction will be a key factor to ensuring that the overall IR
and TR impairment risk levels and the standards of performance achieved continue
to be acceptable in compliance with GHSER and legislation.
6 Environmental Management
The project will set up and implement an environmental management process which will
aim to ensure that all environmental risks, regulatory and BP policy requirements have
been identified and addressed and appropriate measures have been taken.
reduction of emissions, waste and the use of energy in the design construction,
commissioning and intended operation of the new facilities.
(3) The new facilities will apply the best available pollution control techniques that are
commercially viable.
Uncontrolled
The Safety Case programme will be integral to the project HSE plan. It will be aligned to
the FSA programme and the project schedule to ensure that the project complies with
the legislative timing of the submissions and to ensure the ‘risk-driven’ objective of the
operation is not hindered in any way.
Addendum 1
References
(1) HSE Commitment: BP’s Commitment to Health, Safety and the Environment.
(2) BP ‘Getting HSE Right’ (GHSER), January 1999.
(3) Technical Integrity Performance Standards (UKCS-TI-001)
(4) Standard Contract HSE Clauses; HSQ 01.02.06, Rev 0a.
(5) Standard for Technical Safety Audits, HSQ 01.02.09, Rev 0.
(6) Offshore Installations (Safety Case) Regulations 1992, SI 1992/No 2885.
Uncontrolled
(7) The Offshore Installations (Prevention of Fire and Explosion, and Emergency Response)
Regulations 1995 (PFEER), SI 1995/No 743.
(8) XEU UK Operations HSE Management System, Risk Acceptability Criteria, XEU
Statement of Policy; HSQ 01.01.01 Rev 0; November 1992.
(9) XEU UK Operations HSE Management System, Risk Acceptability Criteria, Application in
Offshore Safety Cases, Guidance Note; HSQ 01.06.01, Rev 0; November 1992.
(10) A Guide to the Offshore Installations (Safety Case) Regulations 1992, SI 1992/No 2885.
(11) Guidance on PFEER (UKCS-TI-003)
(12) Emergency System Goals (UKCS-TS-006)
(13) Impairment Criteria (UKCS-TS-012)
(14) Guidance on the Design of Instrumented Protective System (UKCS-TI-022)
(15) Emergency Response Goals (UKCS-TS-017).
(16) Methodology for Assessing Smoke and Gas Ingress to Accommodation and TR Volumes,
HSQ 01.03.01, Rev 0.
(17) Ship Collision Risk Assessment, HSQ 01.05.08, Rev 0.
(18) Guidance on the Loss Potential Matrix, HSQ 01.05.05, Rev 4.
(19) XEU HSE Practices; HSQ 00.04.01.
(20) HSE Policy Implementation & Environment, HSQ 03.01.01, Rev 0.
(21) Offshore Safety Case Overview and General Guidance (UKCS-TS-004)
References
June 2002 Issue 1/AM02 Add 1-1