Professional Documents
Culture Documents
CT1_MAY2023_MAF201_Q
CT1_MAY2023_MAF201_Q
CT1_MAY2023_MAF201_Q
INSTRUCTIONS TO CANDIDATES
3. Do not bring any material into the examination room unless permission is given by the invigilator.
QUESTION 1
A. State whether each of the statement below is True (T) or False (F):
ii. All expenses incurred in fulfilling a contract such as material, wages, production
overhead are credited to a Contraction in Progress Account.
iii. Retention money is a sum of money representing an agreed portion of the price
of work completed being withheld by the contractee for a certain period of time.
(4 marks)
B. Garuda Construction Sdn Bhd has been engaged to construct a resort at Perhentian
Island. The contract commenced its operation on 1 July 2022 and is expected to be
completed on 31 December 2023. The estimated contract price that has been agreed
upon is RM5,000,000. The following details of the contract have been extracted from
the company’s book of account for the period ended 31 March 2023:
Particular RM
Material issued to site 1,500,000
Material returned to store 200,000
Plant and machinery at cost (purchased on 1 July 2022) 300,000
Material at site – 31 March 2023 50,000
Wages paid 370,000
Sub-contractor charges paid 255,000
Direct expenses paid 250,500
The company’s accounting period ends on 31 March every year. Depreciation on plant
and machinery is charged on monthly basis at a rate of 12% per annum using reducing
balance method. Overheads is absorbed at 25% of total material used during the
period. As at 31 March 2023, total wages and sub-contractors charges incurred in the
period are RM400,000 and RM230,000 respectively.
Required:
a. Prepare the Construction in Progress Account for the period ended 31 March 2023.
(12 marks)
c. Determine the value of the contract asset or contract liability for Garuda
Construction Sdn Bhd.
(2 marks)
(Total: 20 marks)
QUESTION 2
A. RM4.56
B. RM4.80
C. RM4.59
D. RM4.83
(2 marks)
2. Wowo Bhd manufactures a single product, which passes through two consecutive
processes, which are Cutting and Finishing. The following data was available for
Finishing process.
Units
Transfer from Cutting process 10,000
Additional materials 5,000
Opening work in progress 1,200
Closing work in progress 900
An expected loss of 10% from production unit occurs in Finishing process with no
scrap value. Determine the normal loss in unit for Finishing process.
A. 1,000 units
B. 1,530 units
C. 1,500 units
D. 1,710 units
(2 marks)
© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL
CONFIDENTIAL 4 AC/MAY 2023/MAF201
3. 12,000 kg of material were input to a process in a period. The normal loss is 10%
of input. There is no opening or closing work-in-progress. Output in the period was
10,920 kg. What was the abnormal gain/loss in the period?
B. Mai Jaya Sdn Bhd produces a single product, which passes through two consecutive
processes, namely Process A and Process B. The output from Process A is transferred
to Process B before it becomes finished goods. There is no additional material added
in Process B.
The data below related to the two processes for the month of March 2023.
Process A
The process is started with 60,000 kgs of input materials at a value of RM300,000.
Direct wages cost for the month was RM54,000. Production overhead costs are
absorbed based on 50% of direct wages. Normal loss of Process A is 10% of material
input and can be sold for a scrap at RM0.50 per kg. 55,000 kgs of output will be
transferred to Process B.
Process B
RM
Labour 33,780
Overheads 45,120
Defective units 3,500 kgs
Opening work in progress 5,000 kgs 3,000
Closing work in progress 3,000 kgs
The normal loss is 5% of production. All defective units can be sold at RM1.00 per kg.
Required: