LABOR:
1 Construction Foreman for 20 day at P 799.80 /day ….. P 15,996.00
10 Laborer for 20 day at P 533.20 /day ….. 106,640.00
LABOR COST ….. P 122,636.00
LABOR:
1 Construction Foreman for 20 day at P 799.80 /day ….. P 15,996.00
3 Skilled Workers for 20 day at P 666.50 /day ….. 39,990.00
6 Laborer for 20 day at P 533.20 /day ….. 63,984.00
LABOR COST ….. P 119,970.00
SUB-TOTAL COST ….. P 1,229,721.83
III.SECONDARY TREATMENT
MATERIALS:
6 pcs Aero Grids at P 41,989.50 /pcs ….. 251,937.00
Colorite Plastic and HDPE
Size of Grid: 1m x 1.2m
66ft. Of Aerotube
2 pcs S/s Foot Valve 1" at P 11,655.75 /pcs ….. 23,311.50
6 pcs S/s Ball Valve 1" at P 3,285.54 /pcs ….. 19,713.23
6 pcs S/s Gate Valve 1" at P 4,067.81 /pcs ….. 24,406.86
6 pcs S/s Check Valve 1" at P 3,129.08 /pcs ….. 18,774.51
6 pcs S/s Bushing 1x1/4" at P 139.30 /pcs ….. 835.79
12 pcs S/s Coupling 1" at P 217.75 /pcs ….. 2,612.95
12 pcs PPR Pipe1" at P 1,173.41 /pcs ….. 14,080.96
15 pcs PPR Coupling 1" at P 72.94 /pcs ….. 1,094.13
12 pcs PPR Pipe 1" at P 1,173.41 /pcs ….. 14,080.88
30 pcs PPR Elbow 1" at P 482.34 /pcs ….. 14,470.18
30 pcs PPR Union Patente 1" at P 117.91 /pcs ….. 3,537.16
24 pcs PPR Tee 1" at P 179.48 /pcs ….. 4,307.40
4 pcs PPR Coupling Reducer 1¼ x 1" at P 131.97 /pcs ….. 527.87
55 pcs PPR Male Adaptor 1" at P 540.18 /pcs ….. 29,710.17
2 pcs PPR Male Adaptor 1¼" at P 806.47 /pcs ….. 1,612.93
5 pcs S blue Elbow 2" at P 431.89 /pcs ….. 2,159.46
1 pcs S blue Tee 2" at P 647.84 /pcs ….. 647.84
2 pcs S blue Ball Valve 2" at P 3,285.54 /pcs ….. 6,571.08
5 pcs S blue Male Adaptor 2" at P 431.89 /pcs ….. 2,159.46
2 pcs S blue Union Patente 2" at P 2,231.44 /pcs ….. 4,462.88
4 pcs S blue Pipe 2" at P 3,959.01 /pcs ….. 15,836.04
2 pcs S blue Flange 2" at P 7,198.20 /pcs ….. 14,396.40
3 pcs UPVC Pipe Black 2" at P 7,414.15 /pcs ….. 22,242.44
6 pcs UPVC Pipe Black 11/4" at P 677.16 /pcs ….. 4,062.98
6 pcs UPVC Pipe Black ¾" at P 557.19 /pcs ….. 3,343.16
5 pcs UPVC Union Patente Black 2" at P 871.78 /pcs ….. 4,358.91
4 pcs UPVC Tee Black 2" at P 393.24 /pcs ….. 1,572.94
8 pcs UPVC Inside reducer 1-1/2 at P 533.87 /pcs 4,270.93
8 pcs UPVC Inside reducer 1-1/4 at P 119.97 /pcs 959.76
8 pcs UPVC Inside reducer 1 at P 119.97 /pcs 959.76
8 pcs UPVC Inside reducer 3/4 at P 179.96 /pcs 1,439.64
8 pcs UPVC Inside reducer 1/2 at P 299.93 /pcs 2,399.40
8 pcs UPVC Inside reducer 1/4 at P 359.91 /pcs ….. 2,879.28
1 pcs Epoxy A&B Non-sag 4Liters at P 4,662.83 /pcs ….. 4,662.83
1 lot FRP Pipe & Fittings at P 36,657.50 /lot ….. 36,657.50
2 pcs B/s Check Valve 3" at P 21,701.24 /pcs ….. 43,402.48
MATERIAL COST P 604,458.69
LABOR:
5 Skilled Workers for 20 day at P 666.50 /day ….. P 66,650.00
5 Laborer for 20 day at P 533.20 /day ….. 53,320.00
LABOR COST ….. P 119,970.00
LABOR:
VI.VENTILATION SYSTEM
MATERIALS:
1 pcs Exaust Fan 16" (Indutrial) at P 17,595.60 /pcs ….. 17,595.60
KDK Reversible Wall
Mounted Air Fan
10 pcs PVC Orange Pipe 4" 1000 series at P 7,129.22 /pcs ….. 71,292.17
8 pcs PVC Orange Elbow 4" at P 691.03 /pcs ….. 5,528.22
5 pcs Pvc Orange Wye 4" at P 1,073.73 /pcs 5,368.66
5 pcs PVC Orange Tee 4" at P 1,655.59 /pcs ….. 8,277.93
VIII. CONSUMABLES
MATERIALS:
20 pail Chlorine 70% Calcium Hypochlorite at P 11,330.50 /set ….. P 226,610.00
Weight: 45kls
2 sack Poly Aluminum Chloride at P 3,199.20 /sack ….. P 6,398.40
4 gal F-100 Coagulant 20Liters at P 15,996.00 /gal ….. 63,984.00
1 bag Manganese at P 6,665.00 /bag ….. 6,665.00
8 bag Activated Carbon at P 7,998.00 /bag ….. 63,984.00
6 bag Pebble #10 at P 1,199.70 /bag ….. 7,198.20
6 bag Pebble #15 at P 1,199.70 /bag ….. 7,198.20
MATERIAL COST P 382,037.80
LABOR:
4 Skilled Workers for 12 day at P 666.50 /day ….. P 31,992.00
4 Laborer for 12 day at P 533.20 /day ….. 25,593.60
LABOR COST ….. P 57,585.60
X. BACTERIAL MEDIA
MATERIALS:
1 lot Biocleaner Inocula at P 1,599,600.00 /set ….. P 1,599,600.00
SUMMARY
I. PREPARATION AND HAULING WORKS P 1,379,655.00
II. SECONDARY EQUIPMENT 1,229,721.83
III.SECONDARY TREATMENT 724,428.69
IV.AIR ACCESS SYSTEM PIPING WORKS 378,585.36
V. JOINTS, BRACKETS AND CLAMP 521,433.61
VI.VENTILATION SYSTEM 345,336.58
VII. TERTIARY TREATMENT 277,773.21
VIII. CONSUMABLES 439,623.40
IX. ELECTRICAL WORKS 247,920.67
X. BACTERIAL MEDIA 1,599,600.00
XI. CONCRETING AND PAINTING WORKS 1,905,690.13
DIRECT COST …….. P 9,049,768.46
8% PROFIT …….. 723,981.48
12% OCM …….. 1,085,972.22
5% VAT …….. 542,986.11
ENG'G. SUP. …….. 597,291.74
ESTIMATED TOTAL COST P 12,000,000.00