lightning Protection

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

TITLE

MS –-Lightning Protection System Installations


TITLE
MS –-Lightning Protection System Installations

CONTENTS

1. INTRODUCTION
2. SCOPE OF WORK
3. RESPONSIBILITIES AND INTERFACING
4. INTERFACING REQUIRMENTS
5. SEQUENCING
6. METHODOLOGY
7. REFERENCES
8. EQUIPMENT AND TOOLS
9. HEALTH & SAFETY (ACTIVITY HAZARD ANALYSIS)
10. QUALITY ASSURANCE/QUALITY CONTROL

1- INTRODUCTION:
TITLE
MS –-Lightning Protection System Installations

This method statement is to describe all materials and installation requirements for Lighting Protection
Systems

2- SCOPE OF WORKS:

This method statement details the procedure established for the correct and proper execution of lightning
protection system applicable to the Works, to ensure that the installation conforms to the contract
requirements, specifications, and applicable standards.
This document defines the recognized practices to be adopted to ensure that the works at site are in
compliance with the Project Quality Plan, its associated quality procedures, and the approved Project
Inspection Plan. It applies to the supply, laying, erection, interconnection, testing and commissioning of a
complete lightning protection system.

RESPONSIBILITIES AND INTERFACING


1- site Manager:

a. Assigns areas of responsibilities to Senior Site Engineers.


b. Monitoring and controlling project execution with respect to time, cost and quality.
c. Coordinating between different functions within the project.
d. Expediting areas of concern to best achieve project schedule.

2- Senior Site Engineer:

a. Assigns areas of responsibilities to Site Engineers.


b. Monitoring and controlling project execution with respect to time and quality.
c. Ensures work is performed as per approved method statement.
d. Expediting areas of concern to best achieve project schedule.

3- Site Engineer:

a. Assigns work tasks/ activities to foremen / subcontractors.


b. Ensuring the execution of work activities within the allocated time frame.
c. Monitoring and controlling activity execution with respect to time and quality.
d. Ensures work is performed as per approved method statement.
e. Expediting areas of concern to best achieve work activity time frame.
f. Liaising with QC Engineers regarding work progression and hold point inspections.
g. Liaising with Owner representative regarding any existing underground utilities.

4- Foreman/Subcontractor:

a. Assigns work tasks to technicians / workers.


b. Ensuring the execution of tasks within the allocated time frame.
c. Monitoring and controlling execution with respect to time and quality.
d. Expediting areas of concern to best achieve work activity time frame.
e. Liaising with Site Engineer regarding work progression and readiness for inspection.
TITLE
MS –-Lightning Protection System Installations

5- QC Manager:

a. Assigns areas of responsibilities to QC Engineers.


b. Monitoring and controlling project execution with respect to quality.
c. Ensures completeness of the quality documentation.
d. Ensures the project requirements for quality are fulfilled.
e. Expediting areas of concern to best achieve project quality requirements.

6- QC Engineers:

a. Assigns areas of responsibilities to QC technicians.


b. Ensuring that the Project Inspection Plan (PIP) is briefed to and followed by the construction team.
c. Ensures required quality documentation is fulfilled and approved.
d. Initiating and maintaining check-sheets / records for works.
e. Liaising with Site Engineers regarding work progression and hold point inspections.
f. Performing hold point inspections of finished parts.
g. Expediting areas of concern to best achieve project quality requirements.

7- Safety Team:

a. Ensure that required Personal Protective Equipment (PPE) is worn at all times.
b. Ensure all workers / technicians are briefed about hazards associated with their type of work.
c. Highlight hazards associated to each work activity.
d. Close monitoring of workers and worksite for any safety related issues.

8- Technical Office Manager:

a. Ensure drawings are developed and approved on time.


b. Coordinate all technical and engineering issues with concerned parties.
c. Liaise with construction team to prioritize required drawings / submittals

4- Interfacing Requirements
Details of the requirements for interfacing are defined in the responsibilities of each party involved.

5- Sequencing

Work shall be performed generally in accordance with the Works Programme (or “Schedule”), which
details the durations and relationships with other types of works.
TITLE
MS –-Lightning Protection System Installations

6- Methodology
a. Pre-Work
a. Check that the design and shop drawings for the lightning protection system are in “approved for
construction” status.
b. Check that access to the work site area for installation is clear, unobstructed and safe. Ensure that
required means of material / personnel transportation, and temporary services / provisions are available.
c. It is to be noted that lightning system components are of a valuable nature and that they should be
properly stored in a secure location as per manufacturer’s recommendations and Project specifications,
and that access to these materials should be controlled in accordance with the Project's Storage Process
procedure.
d. Check that the system components (conductors, earth rods, air terminals, etc) have been ordered,
fabricated, assembled and factory tested and inspected, as applicable, before being delivered to Site.
Upon delivery to Site, system components and associated accessories shall be checked as per the relevant
Project Inspection Plan, to ensure that they are in accordance with the site requirement, the approved
design and material submittals and that they are free from any damage caused during delivery.
e. During installation, structural building members (e.g. I-beams, concrete columns, and walls) shall not be
cut or drilled without prior approval by the civil construction team.
ii. Works
Installation of Lightning Protection System:
a. We use down conductor bare copper cable to connect the roof termination by earthing termination of
lightning protection system
b. (Earthing Pits).
c. The procedures of installations will start after finishing of all civil works at roof.
d. Specify the location of Early Streamer base by using of approved shop drawings.
e. Specify the location of insulated copper conductor routes by using of approved shop drawings.
f. Start to fix the metallic cable clips at the defined raceways by using drill machine.
g. Insert the Early Streamer base to the specified locations and fixing it by using the drill machine.
h. Finalize all the roof lightning termination.
i. Finally, fasten the Early Streamer at its base.
j. For the down conductors, the procedures of installations will start after finishing of all civil works at
facades.
k. Define the location of the down conductor by using of approved shop drawings.
l. Install the test link at height level as detailed at the drawing starting.
m. Excavate the rote from the location of the down conductor till the lightning Earthing
n. For the lightning outdoor Earthing termination, the procedures of installations will start before finishing
of the civil works at site.
o. Specify the location of all pits by using of approved shop drawings.
p. Install the earthing rods into soil by using the hammer to the required depth (which indicated at drawing).
q. Excavation depth: around 50 cm from area finishing level.
r. Specify the location of cables routes by using of approved shop drawings.
s. Excavate the cables routes according to the approved drawing to up to level -50cm by using the
excavation tools.
t. After excavation completion, lay the cables at the excavations.
u. Start fastening for rod to cable clamp as in drawing.
v. Define the location of the cable to cable py using the bimetallic connectors at the cable raceways
TITLE
MS –-Lightning Protection System Installations

by using of approved shop drawings.


w. Start covering the cable routes by a thin layer of natural site soil.
x. Install the pre cast concrete hand-hole at each pit. The top cover of the hand-hole will be levelled with
the finishing floor.
iii. Post-works

iv. The responsible engineer shall then inspect the complete system to verify adequate and proper system
installation, and order any rectifications required.

a. After installation and until commissioning activities start, any part of the lightning protection system that is
likely to collect dust or sustain damage from subsequent construction activities shall be adequately
protected using dust covers or any other appropriate protective means.
b.After installation, tests on the lightning system shall be performed as per Project Inspection Plan, including
system to earth resistance measurement to ensure the proper installation. Unless otherwise specified,
c. The foreman / lightning Subcontractor shall coordinate with other construction trades to ensure that no part
of the installed system is damaged, including air terminals, down conductors and exothermic connection
points.
d.Ensure that any non-terminated pigtails extending out of concrete foundations / slabs are adequately
protected from physical damage using appropriate means, for example, by sliding a piece of PVC conduit
over the pigtail.
7- REFERENCES:
a. General Specifications for QA/QC Inspection (Project Spec- 26 41 13),
b. IFC Drawings
c. Approved Shop Drawings
d. Approved Technical Submittals
e. Manufacturers Installation Instructions
8- Equipments and Tools
• USED TOOLS:
- Simple Hand Tools: Shovel, Pick-prods, Hammers
- Handle clamp and cleaning accessories
- Personal Electrician’s Tools: Screwdriver sets, cable cutter, cutting pliers, saw for copper tape, meter.
• PERSONAL PROTECTIVE EQUIPMENTS:
- Helmet – gloves – goggles – Safety Shoes – Hi-Vis. Vest

9- HEALTH & SAFETY (ACTIVITY HAZARD ANALYSIS)

10- QUALITY ASSURANCE/QUALITY CONTROL:


TITLE
MS –-Lightning Protection System Installations

You might also like