Professional Documents
Culture Documents
ukcsts014_iss1
ukcsts014_iss1
ukcsts014_iss1
Contents
Addendum 1 References
Issue Authority
Name: Jon Turnbull
Signature: ________________________________________________
Date: ________________________________________________
Technical Authority
Name: David Aberdeen
Signature: ________________________________________________
Date: ________________________________________________
Amendment Record
AMOSAF.171
Amendment Summary
Distribution List
Virtual Copyholders
Copy Copyholder
Uncontrolled
Preface
Document Status
The document is reasonably up to date although only exists in draft form.
This document is intended to provide a basis for maintaining some standardisation in the
methods and models used in the Quantified Risk Assessments (QRAs).
QRAs provide the risk data which is quoted in Safety Cases and is used as a basis for assessing
compliance with Risk Acceptability Criteria.
The main areas needing revision include:
Uncontrolled
Responsibility of Copyholders
It is the responsibility of the registered copyholder of controlled hard copy versions to
maintain the accuracy of the document by ensuring that all updates are promptly
incorporated and acknowledged.
Furthermore, the registered copyholder of controlled hard copy versions must at all times
maintain custody of this document unless prior approval is given by the relevant
Technical Authority.
The roles and responsibilities of copyholders and ‘virtual’ copyholders are detailed in Section 1
of the Document Control Procedure (UKCS-DCM-001).
Uncontrolled
List of Abbreviations
Section 1
Methods and Models – BP Best Practice
Paragraph Page
1 Introduction 1
1.1 QRA Technical Alignment – Areas for Comparison 1
1.2 BP Input 2
1.3 Internal Contacts and BP/External Consulting Support 2
1.4 HSQ Controlled Documents 2
Uncontrolled
1 Introduction
During 1993 a consistency review of Safety Case Quality Risk Assessments (QRAs), and
a ‘formal safety assessment’ lessons learned workshop were conducted. These
activities highlighted a number of areas where improvements could be made and led to
the development of a QRA strategy. This strategy addressed three main areas:
• Procurement
• Technical
• Communications
In 1994 a qualification exercise for QRA and other related services was undertaken,
leading to a significantly reduced supplier base.
A QRA Technical Alignment Programme has been set up to improve the consistency and
Uncontrolled
1.2 BP Input
Items underlined in Section 3 indicate where a form has been completed by XEU.
Section 5 contains the completed input forms.
Although a summary of the BP ‘rule set’ is included in each case, there is much more
background detail available in some cases. A reference list is given in Addendum 1.
Copies of all these references are stored in HSQ.
Uncontrolled
In other areas certain external consultants are considered to be market leaders.
A list identifying the contacts is given in Section 4.
Section 2
Areas for Comparison
Uncontrolled
2-1
Areas for Comparison
2-2
Level 1 Level 2 Level 3 Level 4 (Input Forms) Comments/Aspects to be Included
Containment Failure,(Process Gas Dispersion Open Field Initial dilution
Hydrocarbons) (cont d) Modelling
Jet dispersion
UKCS-TS-014
Liquid Drainage Pool size and location Overflow to other areas or to the sea: impact
Modelling of deluge
Dispersion
Ingress into non-hazardous areas Control Room, TR, etc
Explosion Modelling Maximum overpressure
Overpressure distribution How is ignition location, ignition delay,
concentration, cloud size, etc taken into
account?
Structural damage
Equipment damage
External explosion
Explosion mitigation measures
Containment Failure (Others) Utilities Fuel gas
Diesel fuel
Aviation fuel
2-3
Areas for Comparison
2-4
Level 1 Level 2 Level 3 Level 4 (Input Forms) Comments/Aspects to be Included
Containment Failure (Others) Other Hazardous Chemicals
Materials
Radioactive substances
Explosives
UKCS-TS-014
Time effects
Structural collapse modelling
Additional inventory involvement BLEVE
Effect of Installation safety systems ESD, blowdown, firewater etc
Impairment Modelling Temporary Refuge Definitions Structural
Smoke
Decomposition
Systems
Smoke and gas ingress modelling
2-5/6
Areas for Comparison
Best Practice QRA UKCS-TS-014
Section 3
Index System for QRA
Technical Alignment Information
Note: First draft of BP input is included as Section 5 for those items which are underlined.
1.0 Hazard Identification
1.1 Tools used
1.2 Generic hazard checklist
2.0 Process Hydrocarbon Containment Failure
Uncontrolled
2.2.2 Module
2.2.2.1 Ventilation rate estimation
2.2.2.2 Mixing model
2.2.2.3 Gas ingress into non-hazardous areas
2.3 Liquid drainage modelling
2.3.1 Pool size and location
2.4 Toxic gas dispersion
2.4.1 Open field
2.4.1.1 Toxic gas dispersion and effect modelling
2.4.2 Module
Uncontrolled
2.4.2.1 Toxic gas dispersion and effect modelling
2.5 Ignition modelling
2.5.1 Open field
2.5.1.1 Ignition probability
2.5.1.2 Fire/explosion split
2.5.2 Module
2.5.2.1 Ignition probability
2.5.2.2 Fire/explosion split
2.6 Fire modelling
2.6.1 Open field
2.6.1.1 Flash fire
2.6.1.2 Jet fire
2.6.1.3 Pool fire
2.6.1.4 Liquid spray fire
2.6.1.5 Sea pool fire
2.6.2 Module
2.6.2.1 Flash fire
2.6.2.2 Jet fire
2.6.2.3 Pool fire
2.6.2.4 Liquid spray fire
Uncontrolled
4.5.1 Accommodation fires
4.5.2 Non-ignition of flare
4.5.3 Flare carryover
4.5.4 Scaffold collapse
4.5.5 Turbine fires
5.0 Escalation
5.1 Escalation modelling
5.1.1 How is escalation handled?
5.1.2 How are events grouped into escalation categories?
5.1.3 Time effects
5.1.4 Structural collapse modelling
5.1.5 Additional inventory involvement
5.1.6 Effect of Installation safety systems
6.0 Impairment Modelling
6.1 Temporary refuge
6.1.1 Definitions
6.1.2 Smoke and gas ingress modelling
6.1.3 Structural damage/collapse
6.2 Evacuation, Escape and Rescue (EER)
6.2.1 Definitions
6.2.2 Approach
Section 4
BP Contacts/Custodians
Uncontrolled
Text to be supplied.
BP Contacts/Custodians
November 2001 Issue 1 4-1/2
Best Practice QRA UKCS-TS-014
Section 5
Information Input Forms
Paragraph Page
Figure
5.1 Hazard Identification Input Form 3
Uncontrolled
Section 5
Information Input Forms (cont'd)
Figure Page
5.20 Process Loss of Containment Frequency Input Form 23
5.21 Failure Rate Data 24
5.22 Open Field – Jet Dispersion Input Form 25
5.23 Open Field – Heavy Gas Dispersion Input Form 26
5.24 Open Field – Passive Gas Dispersion Input Form 27
Uncontrolled
5.25 Gas Dispersion Modelling – Module Input Form 28
5.26 Liquid Drainage Modelling Input Form 30
5.27 Toxic Gas Dispersion Input Form 31
5.28 Open Field – Ignition Modelling Input Form 32
5.29 Module – Ignition Model Input Form 33
5.30 Open Field Flash Fire Input Form 34
5.31 Open Field Jet Fire Input Form 35
5.32 Open Field Pool Fire Modelling Input Form 36
5.33 Open Field Liquid Spray Fire Input Form 37
5.34 Sea Pool Fire Input Form 38
5.35 Module Flash Fire Input Form 39
5.36 Module Jet Fire Input Form 40
5.37 Module Pool Fire Modelling Input Form 42
5.38 Module Liquid Spray Fire Input Form 43
5.39 Smoke Modelling Input Form 44
5.40 Explosion Modelling – Maximum Overpressure Input Form 45
5.41 Explosion Modelling – Overpressure Distribution Input Form 46
5.42 Explosion Damage to Structures Input Form 47
5.43 Explosion Modelling – Equipment Damage Input Form 48
5.44 Explosion Modelling – External Explosions Input Form 49
5.45 Explosion Modelling – Mitigation Measures Input Form 50
5.46 Utilities Input Form 51
5.47 Other Hazardous Materials Input Form 52
Section 5
Information Input Forms (cont'd)
Figure Page
5.48 Impacts – Helicopter and Aircraft Input Form 53
5.49 Impacts – Dropped Objects Input Form 54
5.50 Impacts – Ship Collisions Input Form 55
5.51 Breakdown of Collision Types 56
5.52 Missiles Input Form 57
Uncontrolled
(16) Where the modelling has recognised weaknesses it would be useful to know if
there are any modifications used in any cases.
(17) Where weaknesses are recognised are there any plans to modify the rule set to
improve it? If so an attached sheet detailing the planned modifications should
be included.
(18) If there is anything else which should be noted please add it here.
Uncontrolled
HAZOPs, HAZIDs, Safety Reviews and Checklists are all used, as appropriate, to identify the hazards.
Uncontrolled
Note: E&P Forum have prepared a HAZID guideline for seismic operations.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at al
(14) How has it been verified/validated (ref)?
Guidelines have been successfully applied on numerous occasions.
(18) Other:
UKCSTS014_006.ai
Guidance from well engineering and reservoir specialists for the particular well under consideration
would be sought and used.
For early screening, would assume that an ignited blowout would be catastrophic irrespective of location.
Feasibility studies would use typical information based on appraisal and exploration well results.
Uncontrolled
(5) Applicable to QRA Type:
All
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
Multiphase flow models used by the specialists will have been validated.
Details not available at present.
(18) Other:
Phase III of the Joint Industry Project to develop a blowout risk model (refer to Addendum 1 Ref 1) is
looking at defining release area more accurately. Phase II gave some limited historical information on
release size and fluid.
UKCSTS014_007.ai
That the well under consideration is comparable with the wells covered by the blowout risk model.
Phase I and II of a Joint Industry Project to develop a blowout risk model [1].
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at al
(14) How has it been verified/validated (ref)?
Review by safety and drilling professionals sponsoring the project. More formal validation may be
undertaken during 1995.
(17) Are any modifications planned? Blowout risk model development is ongoing.
(18) Other:
This subject is on the agenda of the Health and Safety Executive/UKOOA Joint Working Party on Failure
Rate Data. BP is one of the UKOOA representatives.
UKCSTS014_008.ai
Uncontrolled
(6.3%) DRILLSTRING/TUBING
DRILL FLOOR
MARINE
PARTED RISER
DIVERTER LINE
(9.4%)
UNDERGROUND
BLOWOUT (3.1%)
UKCSTS014_009.ai
Figure 5.4 Schematic Presentation of the Blowout Release Points with Percentage
Distributions during Drilling from a Floater
BELL NIPPLE
DIVERTER LINE FROM DIVERTER
DIVERTED DIVERTER (3.2%)
(24%)
C/K FLEX LINES
(1.6%)
PARTED BOP
DIVERTER LINE
(6.4%) FROM WELLHEAD
(19%)
WELLHEAD
RISER
OUTSIDE
CASING
(21%)
CRATER
ANNULUS AT MUD
LINE LEVEL (1.6%)
UNDERGROUND
BLOWOUT (1.6%)
UKCSTS014_010.ai
Figure 5.5 Schematic Presentation of the Blowout Release Points with Percentage
Distributions during Drilling from a Fixed Installation
Uncontrolled
BELL NIPPLE
TOP OF DRILLSTRING/TUBING (50%)
THROUGH DRILL FLOOR
(50%) DRILLSTRING/TUBING
BELL NIPPLE
BOP
WELLHEAD
RISER
UKCSTS014_011.ai
Figure 5.6 Schematic Presentation of the Blowout Release Points with Percentage
Distribution during Completions
NEEDLE VALVE
ON FLOWLINE (7%)
RISER
OUTSIDE CASING
(7%)
CASING VALVE ON
(SUBSEA) XMAS
TREE (7%)
UNDERGROUND
BLOWOUT (7%)
UKCSTS014_012.ai
Figure 5.7 Schematic Presentation of the Blowout Release Points with Percentage
Distribution during Regular Production
Uncontrolled
THROUGH DRILL FLOOR TOP OF DRILLSTRING/TUBING (38%)
(38%)
DRILLSTRING/TUBING
FROM WORKOVER
UNIT (4.8%)
WORKOVER UNIT
C/K FLEX LINES
(4.8%)
BOP/XMAS TREE
FLOWLINE FROM XMAS TREE
(9.6%)
FROM WELLHEAD
(4.8%)
WELLHEAD
RISER
UKCSTS014_013.ai
Figure 5.8 Schematic Presentation of the Blowout Release Points with Percentage
Distribution during Workover
BP is a sponsor of a JIP to develop a model for predicting blowout risk. The blowout frequency for the
average well was calculated as exploration well 45 x 10-4 per well drilled and development well
18 x 10-4 per well drilled, completion 9.9 x 10-4 per operation, production 0.53 x 10-4 per well year
markover 1.63 x 10-4 per well year and wireline 0.34 x 10-4 per well year. Average total ignition probability
was 0.017.
HP/HT wells have a significantly higher risk.
Interviews with drilling professionals in all the sponsoring companies identified parameters (nearly 400)
that could influence the likelihood of a blowout. These parameters were then given a weighting to
reflect their criticality in terms of blowout risks. A customised assessment of blowout risks can be made
Uncontrolled
by using a scoring system with default scores being established for a standard well.
Average blowout frequency can be used during concept selection and design. Parameteric model can
be applied during detailed design. BP has worldwide licence. Any consultant can be used on a BP job.
Typically employ Scandpower.
Model for predicting risk of a blowout during offshore operations (Addendum 1 Ref 1).
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Model has not been well validated to date, still very much a prototype. Hopefully there will be some
further development validation in 1995. Still judged to be the best available.
(17) Are any modifications planned? Blowout risk model development is ongoing.
(18) Other:
This subject is on the agenda of the Health and Safety Executive/UKOOA Joint Working Party on Failure
Rate Data.
BP is one of the UKOOA representatives.
UKCSTS014_014.ai
Hole size – 0 to 20mm; 20 to 80mm; >80mm; rupture. Use representative hole size for each range –
not fixed, depends on objective of the study.
Outflow – simple model – CIRRUS. For gas and non-volatile liquid release probably no need for more
detailed modelling. Detailed model for volatile liquids and multiphase is PLAC, unless the cost turns
out to be prohibitive.
The range of hole sizes in each category (small, medium or large) may be chosen by relating the
flame length with target distances.
Uncontrolled
(5) Applicable to QRA Type:
Use CIRRUS for simple studies. PLAC is only suitable for detailed studies.
The Update of Loss Containment Data for Offshore Pipelines (Addendum 1 Ref 2)
CIRRUS (Addendum 1 Ref 3)
PLAC (Addendum 1 Ref 4)
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Refer to CIRRUS manuals for validation.
PLAC validation?
(18) Other:
PLAC can be run by BP Group Research and Engineering. It may be possible to obtain a PC version and
devise how this could be made available to consultants.
UKCSTS014_015.ai
For standard steel jacket Installations, three locations considered, above at and below splash zone.
More exact location is not usually critical – worst place is usually assumed.
For small hole assume release is tangential to riser. Use judgement to determine how many
directions should be used in the analysis, usually the percentage of the circle containing target areas.
Assume full bore release is vertically upwards.
For floating and other types of Installation, locations need to be determined on a case by case basis.
Uncontrolled
All.
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
In some very detailed analysis the sensitivity of the assumptions that the release is tangential to the
riser has been reviewed to consider probability of release reaching topside ignition points.
UKCSTS014_016.ai
UK industry standard database is given in Addendum 1 Ref 2. This can be interpreted in different ways.
A BP interpretation is given in Addendum 1 Ref 5, and the results are given in Figures 7.13 and 7.14.
Flexible risers are anticipated to be covered in more detail in future revisions of Addendum 1 Ref 2.
Work done by one of the manufacturers Coflexip may also be useful (Addendum 1 Ref 6).
Uncontrolled
(5) Applicable to QRA Type:
All.
Riser under consideration is suitably represented by the population in the AME database.
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
An additional frequency due to ship collision could be added where it is likely to be significant, also
engineering studies (Addendum 1 Ref 7) can be used to argue a reduction in failure frequency due to
protective inspection etc measures in place.
UKCSTS014_017.ai
RISER SECTION ABOVE SPLASH ZONE 0.056 1.52E-05 7.58E-06 0.00E-00 2.27E-05 4.55E-05
SPLASH ZONE 0.556 1.52E-04 7.58E-05 0.00E-00 2.27E-04 4.55E-04
Uncontrolled
RISER SECTION ABOVE SPLASH ZONE 0.067 1.82E-05 9.08E-06 0.00E-00 1.82E-05 4.54E-05
SPLASH ZONE 0.467 1.27E-04 6.36E-05 0.00E-00 1.27E-04 3.18E-04
BELOW SPLASH ZONE 0.467 1.27E-04 6.36E-05 0.00E-00 1.27E-04 3.18E-04
SAFETY ZONE NEAR <100m 0.600 3.92E-04 1.57E-04 2.35E-04 7.84E-05 8.62E-04
FAR 100-500m 0.400 2.61E-04 1.04E-04 1.57E-04 5.22E-05 5.75E-04
MID LINE Frequency per km/year 1.000 4.85E-05 2.42E-05 0.00E-00 1.62E-05 8.89E-05
SUBSEA WELL Frequency per year 1.000 3.22E-03 0.00E-00 0.00E-00 0.00E-00 3.22E-03
UKCSTS014_018.ai
Uncontrolled
TOTAL 1.65E-03 3.56E-04 4.45E-05 0.00E+00 2.05E-03
RISER ABOVE SPLASH ZONE 0.400 3.51E-04 7.59E-05 9.49E-06 0.00E-00 4.36E-04
SPLASH ZONE 0.200 1.76E-04 3.80E-05 4.74E-06 0.00E-00 2.18E-04
BELOW SPLASH ZONE 0.400 3.51E-04 7.59E-05 9.49E-06 0.00E-00 4.36E-04
SEAFETY ZONE NEAR <100m 0.667 5.60E-04 1.21E-04 1.51E-05 0.00E-00 6.97E-04
FAR 100-500m 0.333 2.80E-04 6.06E-05 7.57E-06 0.00E-00 3.48E-04
UKCSTS014_019.ai
Use CIRRUS for simple studies. PLAC only for more detailed studies.
The Update of Loss Containment Data for Offshore Pipelines (Addendum 1 Ref 2).
CIRRUS (Addendum 1 Ref 3).
PLAC (Addendum 1 Ref 4).
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
(10) Can a consultant's model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Refer to CIRRUS manuals for validation.
PLAC validation?
(18) Other:
UKCSTS014_020.ai
Depends on objective of study. Exact location and orientation is not usually very important for
mid-line failures.
Within the safety zone around an Installation, failure locations every 50 or 100m may be considered.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_021.ai
UK industry standard database is given in Addendum 1 Ref 2. This can be interpreted in different ways.
A BP interpretation is given in Addendum 1 Ref 5.
The results are given in Figures 7.13 and 7.14.
Note that a frequency is given for the safety zone and for mid-line failures.
Uncontrolled
All.
Pipeline under consideration is suitably represented by the population in the AME database.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Site-specific studies may be undertaken to assess the likelihood of trawl damage, dropped objects
damage, anchor damage. Influence of inspection and repair regimes may also be used to modify
failure rates.
UKCSTS014_022.ai
Uncontrolled
(5) Applicable to QRA Type:
All – increasing level of complexity can be introduced for more detailed design.
ESD valves are leak tight that can be modified if it proves to be a critical assumption.
Liquid level assumed to be normal operating level.
Normal operating temperature and pressure assumed.
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
This task is fundamental to the complexity of the overall analysis. If scenarios are being generated
manually then it is important that a simple conservative approach is taken. A computerised system is
needed for more rigorous handling.
UKCSTS014_023.ai
Define a minimum hole size that has the potential to cause a major hazard – typically a couple of
millimetres depending on fluid and pressure. Assume all hole sizes are possible between minimum and
full bore rupture. For pre-ESD release cases use 10mm, 50mm and full bore to conservatively represent
the ranges min to 10mm, 10mm to 50mm and 50mm to full bore. For post-ESD case use hazard analysis
to define threshold hole sizes on a case by case basis – fire damage is a function of both size and
duration. Outflow rate – use simple orifice calculations, CIRRUS or HARP. Pre-ESD assume pressure is
constant. Post-ESD take account of blowdown, liquid head etc.
Uncontrolled
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Difficult to validate. Being able to run sensitivities rapidly and effectively would help a lot.
(18) Other:
Where a particular component dominates the frequency of a certain hole size range, eg small bore
fittings dominate the 10 to 50mm category, it may be possible to argue that based on engineering
judgement the probability of leak size is not uniform but is biased towards a certain hole size.
UKCSTS014_024.ai
For stabilised oil releases, oil pool is assumed to form. Pool is circular around the release point unless
dictated otherwise by bunding (refer to Figure 7.26). Number of release locations selected for each
isolatable system depends on specific circumstances and objective of study.
For gas and multiphase releases, selection of release location/orientation will be driven by escalation
routes, damage criteria and impairment criteria.
Objective is to drive realistic probabilistic values for use in event trees.
Uncontrolled
(5) Applicable to QRA Type:
All.
A large number of assumptions need to be made which may change for each Installation.
Need to be clearly recorded.
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
Very difficult to validate – heavily reliant on judgement.
(18) Other:
A computerised system may be of benefit.
UKCSTS014_025.ai
Equipment count is based on as-built drawings, site survey, or average for system type depending on
design state. Numbers of flanges are assumed unless a site survey is carried out.
Leak frequencies are based on E&P Forum Hydrocarbons Leak and Ignitions Database.
A summary is given as an addendum to this form.
Uncontrolled
E&P Forum Hydrocarbon Leak and Ignition Database (Addendum 1 Ref 10).
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
Difficult to validate. Accepted as an industry standard.?
(18) Other:
Anticipate using results from HSE database (Ammendum 1 Ref 11) in the future, also the equipment
counts prepared for that. BP is involved in Phase 2 of the E&P Forum project (Addendum 1 Ref 12)
which should facilitate the development of BP specific data.
UKCSTS014_026.ai
Uncontrolled
1 1.0000 1.0E-4 3.10E-05
Vessel 1.50E-4 25 0.5400 0.54 8.10E-05
50 0.8900 0.35 5.25E-05
150 0.9600 0.07 1.05E-05
1 1.0000 0.04 6.00E-06
Heat Exchanger (HC in shell) 1.50E-4 25 0.5400 0.54 8.10E-05
50 0.8900 0.35 5.25E-05
150 0.9600 0.07 1.05E-05
1 1.0000 0.04 6.00E-06
Heat Exchanger (HC in tube) 1.30E-5 25 0.5400 0.54 7.02E-06
50 0.8900 0.35 4.55E-06
150 0.9600 0.07 9.10E-07
1 1.0000 0.04 5.20E-07
Heat Exchanger (HC in both) 1.63E-4 25 0.5400 0.54 8.80E-05
50 0.8900 0.35 5.71E-05
150 0.9600 0.07 1.14E-05
1 1.0000 0.04 6.52E-06
Piping <3in diameter 7.00E-5 0.05 0.6000 0.60 4.20E-05
(per metre) 0.22 0.8500 0.25 1.75E-05
0.45 0.9500 0.10 7.00E-06
1 1.0000 0.05 3.50E-06
Piping 4in – 11in diameter 3.60E-5 0.05 0.6000 0.60 2.16E-05
(per metre) 0.22 0.8500 0.25 9.00E-06
0.45 0.9500 0.10 3.60E-06
1 1.0000 0.05 1.80E-06
Piping >12in diameter 2.70E-5 0.05 0.6000 0.60 1.62E-05
(per metre) 0.22 0.8500 0.25 6.75E-06
0.45 0.9500 0.10 2.70E-06
1 1.0000 0.05 1.35E-06
Flange 8.80E-5 0.1 0.9600 0.96 8.45E-05
1 1.0000 0.04 3.52E-06
Valve 2.30E-4 0.05 0.6500 0.65 1.50E-04
0.1 0.8800 0.23 5.29E-05
0.2 0.9400 0.06 1.38E-05
1 1.0000 0.06 1.38E-05
Small Bore Fitting 4.70E-4 0.1 0.1300 0.13 6.11E-05
0.2 0.2000 0.07 3.29E-05
1 1.0000 0.80 3.76E-04
UKCSTS014_027.ai
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Guidelines have been successfully applied on numerous occasions.
(18) Other:
UKCSTS014_028.ai
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Guidelines have been successfully applied on numerous occasions.
(16) Are any modifications used? Yes Customised for specific situations.
(18) Other:
UKCSTS014_029.ai
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
(10) Can a consultant's model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Guidelines have been successfully applied on numerous occasions.
(18)Other:
UKCSTS014_030.ai
Uncontrolled
Further information is given on an Attachment Sheet to this form.
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
By Cambridge University against measurements on Offshore Installations (report not yet published).
(18) Other:
Complexity of input/output data handling and linkage of the parts requires specialist use – this will be
improved so a Safety Engineer can use the composite model on a PC.
JETDISP is being included.
UKCSTS014_031.ai
Although MODVENT is still being developed it has been applied to models where explosion risks are
high and the risk levels are sensitive to explosion size and frequency.
MODVENT is a 3-D integral dispersion model which takes obstacles and boundary effects into
account. MODVENT covers the effect of air flows on the release from the release point so initial
dilution effects are included.
The requirements for the explosion consequence modelling vary depending on the model being run.
MODVENT can be used to calculate equivalent gas cloud volumes of still stoichiometric mix or
whatever is required by the explosion model. It can also calculate the flammable envelope where
that is required for consequence modelling.
Uncontrolled
MODVENT will also be able to cover smoke and gas ingress modelling.
For a first pass to see whether explosions are a significant problem on an Installation, the nearest
dispersion model among plug flow, stirred tank, bubble etc would be applied until MODVENT is able
to be applied simply and locally.
Open field dispersion could use CIRRUS or JETDISP as a first pass. These models are currently the
subject of discussion on their accuracy levels and areas of applicability.
Advice should be sought from HSQ on which one to use in any case. The intention is to add the
open field dispersion equations in JETDISP into MODVENT.
The basic flow field on which MODVENT superimposes a leak is calculated by FLOWPOR, CFD or
wind tunnel testing. BP have a CFD methodology and safety factors which they apply but they do not
recommend specific CFD models providing the validated form of equations is used.
Sunbury should be involved when CFD modelling is proposed.
Forced ventilation cannot be incorporated in MODVENT. At present a CFD model is used for forced
ventilation modelling. This should be discussed with Sunbury.
A modification to MODVENT may be added which will calculate the overall ventilation, air change rate
but that is not available at present.
MODVENT does not include heavy gas. HEGADAS (in CIRRUS) or DEGADIS (stand alone) would be
applied for that. They are similar models which have a similar level of validation.
UKCSTS014_032.ai
Bunding/gullies can control pool size and burn rate. If deluge is operating pool covers entire module
or up to intermediate divisions. Drains will be examined for design and preferential drainage of water,
oil or both.
Worst case design for the module may minimise sea pool fire effects.
Without bund and deluge the pool will still fill the floor area and overflow unless the release rate
< drain capacity + burn rate.
Grating can encourage combustion if liquid sprays onto it: 50% combustion on grating, 50% falling
through up to 100m2 grating.
Uncontrolled
(5) Applicable to QRA Type:
Drainage can only really start to be taken into account during detained design. For earlier stages
assume oil pool fills module and then overflows (size of oil pool based on release rate and burn rate
only – ie no allowance for drainage).
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Need to agree some simple rules to minimise subjectivity.
UKCSTS014_033.ai
MODVENT (Addendum 1 Ref 14) would be used for dispersion in modules. CIRRUS (Addendum 1
Ref 2) and JETDISP (Addendum 1 Ref 13) could be used for the first pass open field modelling –
refer to details on Sheet 2.2.
Uncontrolled
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Toxic gas dispersion within modules not usually required. Onshore as well has limited inventories of
acutely toxic material.
UKCSTS014_034.ai
Uncontrolled
(5) Applicable to QRA Type:
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Not well validated. Should be treated as a key sensitivity.
(18) Other:
Needs standardising and improving.
UKCSTS014_035.ai
P ignition = exp (0.3921n (m) - 4.333) for oil release } m = release rate in kg/s
P ignition = exp (0.6421n (m) - 4.16) for gas release } logic?
Given ignition P explosion = exp (0.381n (m) - 2.995) , m = gas release rate in kg/s, for liquid streams
consider vapour flash fraction.
Design implications?
Uncontrolled
All.
Classification of Hazardous Areas – Con, Lees Ang IChemE 1992 (Addendum 1 Ref 16).
Comments: 1 2 3 4
(9) Does BP impose its preferance? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Not well validated. Should be treated as a key sensitivity.
(18) Other:
Key area for R&D, better model required.
UKCSTS014_036.ai
Flash fires are treated as explosions with zero overpressure. LFL boundary is taken to be the
extent of damage.
Uncontrolled
(5) Applicable to QRA Type:
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
The effects on individuals should be covered but requires more work to be done.
UKCSTS014_037.ai
First pass use CIRRUS as BPFLARE is on VAX and therefore not easily accessed. FIREX is similar to
forthcoming BPFLARE PC version. CFD can be used to model the fire though in most situations is
too expensive to be justifiable. Burn rate is taken to be the leak rate. Heat flux 300kW/m2 max,
250 average (methane 200 average). PFP effect is in 01.05.07 where durations for existing specific wall
types are given, new PFP would be based on proven manufacturer's test data.
SCI interim guidance is used for structural and equipment effects. No particular structural collapse
models are recommended. Feedback into hole size selection – based on hole size/release rate
required to do damage. Deluge/foam effects – none.
Uncontrolled
All – the variation will be in the number of events modelled and calculated.
Semi-empirical models used, wind speed restriction of 50m/s, jet deflection model ignores
buoyancy effects.
Input is directly from the hole size/release rate modelling with additional inputs on wind speed
direction etc.
CIRRUS (Addendum 1 Ref 3).
BP FLARE (Addendum 1 Ref 17).
Impairment Criterias HSQ Guidance 01.05.07 (Section 5)
SCI Interim Guidance (Addendum 1 Ref 18).
FIREX P (Addendum 1 Ref 21).
(8) Is much interpretation required? Yes.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref CIRRUS Validation Manual for model F2, 3/93)?
Peer review by Dr R Britter, Dept of Engineering, University of Cambridge. PFP tests proven by
manufacturers. Structural collapse modelling mechanisms are not specified.
(18) Other:
Conversion of BP FLARE to a PC base is a possible R&D item. Current SCI Phase II work/experiments
are likely to help. British Gas are doing experiments including obstacles.
CFD can show deluge effect.
UKCSTS014_038.ai
Flame height, burn rate, shape, radiation etc - BPPOOL (in CIRRUS and standalone PC model which
includes obstacles). Heat flux 200, 150 ave (cond) 50 less for crude. BPPOOL divides the flame into two
with different emmisivities for the upper and lower sections. PFP effect is in 01.05.07 where
durations for existing specific wall types are given, new PFP would be based on proven manufacturer's
test data. SCI interim guidance is used for structural and equipment effects. No particular structural
collapse models are recommended. Feedback into hole size selection based on hole size/release rate
required to do damage. Deluge – general area, 50% reduction in burn rate (heavy crude) 25% for
condensate: foam – 75% reduction in burn rate of pool area while foam lasts. Fuel flowing into fire,
10% probability of foam extinguishing, 75% probability of extinguishing if no flow into the pool.
Uncontrolled
(5) Applicable to QRA Type:
All – the variation will be in the number of events modelled and calculated.
Comments: 1 2 3 4
(9) Does BP impose its preference?
,
Always x Never
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref CIRRUS Validation Manual for model F2, 3/93)?
BPPOOL validation exercise is in Addendum 1 Ref 19.
(18) Other:
SCI Phase II includes experiments with deluge on pool fires.
UKCSTS014_039.ai
Criteria for a spray fire – > 7bar heavy crude, 4bar light crude, 2bar condensate.
For heavy crude all release would form an oil pool < 2bar and quantities prorated in between.
CIRRUS, BPFLARE, FIREX may underestimate radiation but no alternative other than hand calculations.
General area deluge will not extinguish and will have little effect. Monitors may be able to extinguish.
Heat flux: stab crude, 200kW/m2 max and 150 average: condensate 300 and 250.
Uncontrolled
All – the variation will be in the number of events modelled and calculated.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
(10) Can a consultant's model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated?
Nothing at present, by next year will have more information through the JIP on fire and blast.
British Gas experiments appear to support the 7bar pressure.
(18) Other:
,
The Steel Construction Institute s Joint Industry Project on Fire and Blast is still ongoing.
UKCSTS014_040.ai
No self-sustained sea pool fire if wind speed > 3m/s or wave height > 2.5m probability of suitable
weather for sustained fire < 0.07. Note: The 3m/s (and therefore the 0.07) is now questioned.
Oil slick direction is vector addition of 3% wind velocity + 100% surface current.
Sustained combustion is likely if fuel temperature > 40°C above its flash point. If < 20°C above its
flash point it will self extinguish. Where fuel thickness < 0.8mm combustion is unlikely.
Additional information on ignition probabilities, how oil reaches the sea and pool size are included in
the reference. The constraints on ignition are not well understood at this stage.
Uncontrolled
Note: Source of oil, eg topsides, riser etc is an important consideration.
All.
n/a.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
n/a.
(18) Other:
SINTEF experiments looking at the characteristics of crude fires on the sea will be available this year.
Ease of burning may be considered next year.
UKCSTS014_041.ai
Module flash fires are treated as explosions with zero overpressure and form part of the
distribution of explosion overpressures.
Uncontrolled
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
The effects on individuals should be covered but requires more work to be done.
UKCSTS014_042.ai
4) Summary Description:
Flame has to be long enough to reach equipment and engulf 1/2 diameter to damage or wall +1m spread.
Burn rate is taken to be the leak rate, rarely ventilation controlled, fuel often runs out before air.
If ventilation controlled unburned gas burns as diffusion gas flame externally outside upper module.
Heat flux = 300kW/m2/250kW/m2average. Structural response and PFP effect is in 01.05.07 where
durations for existing specific wall types are given, new PFP based on proven manufacturer's test data.
SCI interim guidance used for structural and equipment effects. No particular structural models are
recommended. Feedback into hole size selection based on hole size/release rate required to give
specified damage levels. Deluge/foam effects – none. Further information is on an attachment to
Uncontrolled
this form.
All – the variation will be in the number of events modelled and calculated.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated?
(18) Other:
Guidance on when to stop using directional model is required. CFD may be used to produce
databases. This area will invariably be critical and an agreed rule set is essential.
UKCSTS014_043.ai
There will be a cut-off size of jet fire above which the fire effectively fills the module and cannot be
modelled as a directional flame. At that stage all critical structure and equipment within the module
should be considered to be exposed to a heat flux of 300kW/m2.
The cut-off will relate flame length to module size but it has not yet been defined.
Note: Guidance on this is required.
The switch over to ventilation controlled is calculated quite simply depending on the area of the vent.
HARP will be able to calculate whether fires are or are not ventilation controlled.
The effect of the external fire can be calculated using FIREX for a ventilation controlled fire.
Where the internal fire is ventilation controlled it is unclear what software is used. (HARP may be
Uncontrolled
able to be used for this and CFD can be used to build up databases to be used as references.)
Where the fire is not ventilation controlled and is relatively small and unobstructed, open field models
can be used.
UKCSTS014_044.ai
Flame height, shape, radiation, hot gas layer depth can be calculated using the FIREX model.
SCANDPOWER handbook criteria used to calculate the spread if it reaches the roof.
External flaming is as for jet fires. For ventilation controlled fires the burn rate is set by the air supply.
Heat flux approx 50kW/m2 higher than open field.
Deluge – general area, 50% reduction in burn rate (heavy crude) 25% for condensate.
Foam – 75% probability of extinguishing fire if no flow into pool.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
(10) Can a consultant's model be substituted? Easily No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
Check in manual.
(18) Other:
UKCSTS014_045.ai
2) Consultant: 3) Date:
BP September 1994
4) Summary Description:
Criteria for a spray fire – > 7bar heavy crude, 4bar light crude, 2bar condensate. For heavy crude all
pool < 2bar and quantities prorated in between.
Models may underestimate radiation but no alternative other than hand calculations.
General area deluge will not extinguish and will have little effect. Monitors may be able to extinguish.
Liquid jets will lose energy and rise on leaving the module. Flame volume as for equivalent pool fire.
If flame vol < 1/2 module volume then no significant external flaming otherwise external flame = total
volume – 1/2 module volume (if fire is freely ventilated). If ventilation controlled use FIREX
Uncontrolled
(SCANDPOWER Handbook).
All – the variation will be in the number of events modelled and calculated.
6) Key Assumptions:
FIREX (21)
Scandpower Handbook (Addendum 1 Ref 22).
Comments: 1 2 3 4
9) Does BP impose its preference? Always Never
,
10) Can a consultant s model be substituted? Easily No
11) How sensitive are models to this rule set? Very x Not at all
12) How subjective is its application? Very x Not at all
13) How auditable is it? Easily x Not at all
14) How has it been verified/validated (ref)?
Nothing at present, by next year will have more information through the JIP on fire and blast.
18) Other:
The Steel Construction Institute Joint Industry Project on fire and blast is still ongoing.
UKCSTS014_046.ai
A composite model will shortly be available covering smoke composition, ventilation, contamination
rate and personnel effects. The model consists of four main components:
1. Quantities of toxic components – see (Addendum 1 Ref 23).
2. Dispersion as gas dispersion – MODVENT etc.
3. Ingress into sensitive areas – see (Addendum 1 Ref 23).
4. Computer software SGICALC – see (Addendum 1 Ref 23).
Uncontrolled
(5) Applicable to QRA Type:
FEA, site geometry, TR layout, manning, weather (generic data is available for concept use).
HSQ Guidance on Smoke Modelling (Addendum 1 Ref 23).
MODVENT (Addendum 1 Ref 14).
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily x No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
By using validated and industry standard methods/references. Calculations were validated by
external consultants against sources.
(18) Other:
n/a.
UKCSTS014_047.ai
All. Build up a simple model for screening/concept design and then add detail as available.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
BP has had bad experiences changing explosion models part-way through a development.
The preffered route is for Sunbury to carry out all explosion modelling.
UKCSTS014_048.ai
In principle some form of probabilistic assessment of ignition location, cloud size, cloud
concentration would be carried out.
Preffered approach not yet determined.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Another important area for R&D. Key step is to finalise approach in modelling gas accumulations.
UKCSTS014_049.ai
Walls with steel plates fully welded to the support structure may start to buckle at overpressures of
0.2 – 0.3 barg, and bending of the wall support diagonals and secondary structure may take place at
0.3 – 0.5 barg. Walls with steel cladding may collapse and fall off at pressures of 0.1 – 0.2 barg.
The primary columns and horizontal beams at main truss lines are usually very strong.
Initially simple static hand type calculations would be used. If there was a problem then ABACUS (or
similar) non-linear finite element analysis would be used.
As a final resort sections may be tested. SCI Guidance would be used.
Uncontrolled
All. Detail of modelling required would depend on the level of information available, criticality and
objective of the study.
Large numbers of simplifying assumptions are required – important to involve Structural Engineers.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_050.ai
Process equipment with its piping is expected to shake and possibly deform during the explosion.
This type of influence may lead to possible new leakage of hydrocarbons if the equipment is
subjected to a drag force created by an explosion exceeding 0.3 barg.
The drag forces are strongest near the largest explosion venting areas.
Uncontrolled
(5) Applicable to QRA Type:
Information used in escalation modelling – analysis of drag forces would only be considered in
detail design.
6( ) Key Assumptions:
Comments: 1 2 3 4
(9) Does impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Guidelines have been successfully applied on numerous occasions.
(16) Are any modifications used? Yes Customised for specific situations.
(18) Other:
UKCSTS014_051.ai
No firm approach.
Historically there has been a difference of opinion between experts on the significance of this
phenomenon.
Could be significant.
Need to develop a firm position.
Uncontrolled
Comments: 1 2 3 4
9) Does BP impose its preference? Always Never
,
10) Can a consultant s model be substituted? Easily No
11) How sensitive are models to this rule set? Very Not at all
12) How subjective is its application? Very Not at all
13) How auditable is it? Easily Not at all
14) How has it been verified/validated (ref)?
18) Other:
UKCSTS014_052.ai
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
BP is sponsoring research into active and passive explosion mitigation measures.
UKCSTS014_053.ai
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_054.ai
Ensure these are all identified and assessed using a systematic HAZID process.
Detailed frequency and consequence analysis work not usually required.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_055.ai
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_056.ai
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
(10) Can a consultant's model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_057.ai
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
Currently the subject is of much concern as high risk levels are predicted in the North Sea.
UKOOA Marine Committee is sponsoring Safetec to update traffic data which is at the heart of the
COLLIDE model.
(18) Other:
Subject of inter-governmental department debate in the UK.
UKCSTS014_058.ai
External (Passing) Merchant Small Powered/Drifting Frequency assessment using COLLIDE + structural damage
assessment + fatalities assessment
Medium "
Large
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_060.ai
Risk in North Sea is low therefore use a simplistic conservative method to give an indication of risk.
Reference compares likely earthquake loads with the design storm loading and derives risk levels
of between 5 x 10 -6 to 6.2 x 10-8.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_061.ai
Subsidence risk is considered to be negligible for conventional jackets. The height of the Installation
at sealevel (LAT) is monitored. Also the relative height of the well conductors and the topside can be
used as a guide.
The subsidence risk for unconventional jackets or Installations may need to be assessed but if a
potential problem was identified it would be controlled by implementing a system for increased
monitoring of the Installation position and as long as the appropriate system was implemented as part
of the Installation operation the risks from subsidence would be considered negligible.
Uncontrolled
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_062.ai
Scour is treated in a similar way to subsidence. If a potential problem is identified, as may be the case
in the Southern North Sea, it is monitored and controlled as part of the Safety Management System.
The residual risk is considered to be negligible.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_063.ai
From Reference 31 – risk of failure of a structural component is 1 x 10-5, with addition of redundancy and
overall structural system failure that reduces to approx 1 x 10-6.
Effect on topside is covered in Reference 32. Conservatively the overall risk that the actual
applied load will exceed the resistance is less than 1 x 10-5.
Uncontrolled
Reference 23 – designed to 100 year storm, DoE Offshore Installations: Guidance on Design and
Construction, June 1990 and API RP2A August 1991.
Risk of Structural Failure due to Extreme Environmental Events (Addendum 1 Ref 31).
Risk of Structural Failure of Topsides due to Extreme Environmental Events (Addendum 1 Ref 32).
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_064.ai
The risk of structural failure of primary components of Installation jackets, sufficient to cause Installation
collapse and affect the TR, due to fatigue is low, of the order of 1 x 10-7, and due to corrosion is
considered negligible.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_065.ai
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_066.ai
Uncontrolled
(5) Applicable to QRA Type:
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_067.ai
Handling of escalation is determined largely by the sophistication of the event tree modelling
approach.
Would normally address wall, floor, ceiling collapse; internal fire escalation within a module;
escalation to risers; escalation to a blowout; BLEVE of condensate/LPG vessels.
Uncontrolled
Escalation is only usually taken into account at concept design and later.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
PLATO (Addendum 1 Ref 24) offers a much better approach to the handling of escalation. It has been
reviewed in detail and would need significant upgrading to be best practice in other areas.
UKCSTS014_068.ai
TR impairment is usually taken as the final escalation event. Events that could impair the TR are
identified, together with escalation mechanisms by which these events could be realised.
Typically worst case fires and explosions in each 'area' of an Installation are considered together with
fires in multiple adjacent areas.
The mechanism by which smaller explosion and fire events would lead to these 'worst cases'
is also considered.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Again PLATO (Addendum 1 Ref 34) handles better.
UKCSTS014_069.ai
In conventional fault tree analysis it is difficult to consider more than three or perhaps four time
stages: time to detection; immediate; personnel mustered in the TR; personnel evacuating by
lifeboat.
Smoke and gas impairment calculations do need to take account of time more rigorously, as impairment
is a combination of concentration and exposure time.
Uncontrolled
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Again PLATO (Addendum 1 Ref 34) handles better.
UKCSTS014_070.ai
Relatively simple calculations may be possible if primary load paths can be identified. For multi-load
paths, cantilevers etc USFOS type modelling would be carried out to model progressive collapse.
Tall structure support and collapse to be included. In a fire most structures will be OK for 5 minutes but
will be impaired after 15 minutes. With blowdown the critical period in a jet fire is within those limits.
For local area collapse, use ABACUS or USFOS but engineering judgement is still a vital part of the
analysis. Steel sheet (approximately 6mm) will not collapse and form holes if subjected to a jet fire
(red hot curtain). Use SCI and JIP guidance.
Uncontrolled
Consider what strength is required as a minimum to avoid escalation.
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very x Not at all
(12) How subjective is its application? Very x Not at all
(13) How auditable is it? Easily x Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_071.ai
Local area: Explosion, jet fires and pool fires are assumed to have the potential to result in
escalation to the 'worst' possible fire in the area (usually an extensive oil fire).
Adjacent areas: Explosion, jet fires and pool fires are assumed to have the potential to result in
escalation to the 'worst' possible fires in adjacent areas.
Uncontrolled
Relatively simple ruler sets have to be established to make the analysis manageable.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_072.ai
ESD and blowdown usually assumed to work with account perhaps taken of local valve failure.
To date vunerability of other safety systems has been considered in order to assist in optimising
their design but has not typically fed back into overall risk assessment.
Uncontrolled
(5) Applicable to QRA Type:
(18) Other:
There may be increased focus in this area of escalation with the introduction of the PFEER Regulations
(Addendum 1 Ref 37) in the middle of 1995.
UKCSTS014.073
• By smoke when carboxyhaemoglobin exceeds 15%, the exposure to air temperature exceeds an (TBA)
• By flammable gas if it is credible for gas at flammable concentrations to ingress into the TR
• By toxic gas if limits rise above those specified in Table 4 of the reference
• By significant damage to TR walls
• By significant damage to the TR supporting structure
Uncontrolled
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_074.ai
MODVENT or a detailed CFD model, is used to calculate the concentration at the points of interest
and then SGICALC calculates the ingress and the time dependent effect.
Determines whether TR is impaired by smoke, flammable gas or toxic gas.
Estimates the frequency of impairment.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_075.ai
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_076.ai
Basic approach is presented in guidelines of forthwith EER studies for existing Installations.
Will be seeking advice from consultants on current industry best practice.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
(10) Can a consultant's model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
There may be increased focus on this area with the introduction of the PFEER Regulations
(Addendum 1 Ref 37) in the middle of 1995.
UKCSTS014_077.ai
Basic approach is presented in guidelines of forthwith ESR studies for existing Installations.
Will be seeking advice from consultants on current industry best practice.
Uncontrolled
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18)Other:
There may be increased focus on this area with the introduction of the PFEER Regulations
(Addendum 1 Ref 37) in the middle of 1995.
UKCSTS014_078.ai
Limited internal experience – looking for guidance from pre-qualified QRA consultants.
Uncontrolled
(5) Applicable to QRA Type:
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_079.ai
Limited internal experience – looking for guidance from pre-qualified QRA consultants.
Uncontrolled
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_080.ai
Ref (Addendum 1 Ref 26) gives Accident Rates/100,000 of 1.35 per flight hour cruise and 0.74 per
flight stage departure/arrival: Conditional probability of injury accident of 0.15 cruise and 0.35 departure/
arrival; and probability of an injury in an injury accident of injury 0.11/fatality 0.82 cruise, and injury 0.2/
fatality 0.48 departure/arrival. The serious injury or fatality rate is the product of the three appropriate
numbers. Lower rates may be justified depending on the aircraft type eg Dauphin but the available data
Uncontrolled
and hence robustness of the results is lower.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_081.ai
All.
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
Needs to be amended and brought up to date.
UKCSTS014_082.ai
Potential loss of life (statistical number of average fatalities per year) and the individual risk of various
worker groups have typically been calculated.
FN results have not historically been produced but would be useful in the future.
Uncontrolled
(5) Applicable to QRA Type:
(18) Other:
UKCSTS014_083.ai
Whilst the focus has in recent years been primarily on personnel risk, there is a growing awareness that
QRA work should be extended to address the broader business risk issues to all safety and
environmental incidents. Some provisional outline guidance is available in (Ammendum 1 Ref 41).
Uncontrolled
Comments: 1 2 3 4
(9) Does BP impose its preference? Always Never
,
(10) Can a consultant s model be substituted? Easily No
(11) How sensitive are models to this rule set? Very Not at all
(12) How subjective is its application? Very Not at all
(13) How auditable is it? Easily Not at all
(14) How has it been verified/validated (ref)?
(18) Other:
UKCSTS014_084.ai
Addendum 1
References
(1) Model for Predicting the Risk of a Blowout During Offshore Operations, Scandpower,
Procedure No 21.75.73, February 1994. Phase II Report, December 1994.
(2) PARLOC 92 The Update of Loss Containment Data for Offshore Pipelines, Advanced
Mechanics and Engineering Ltd, 362.1, Feb 1993.
(3) CIRRUS.
(4) PLAC.
Uncontrolled
References
November 2001 Issue 1 Add 1-1
UKCS-TS-014 Best Practice QRA
Uncontrolled
(33) Risk of Structural Failure due to Fatigue or Corrosion, BP Engineering,
221099/ESR.93.ER,066, July 1993.
(34) PLATO.
(35) ABACUS.
(36) USFOS.
(37) Offshore Installations (Prevention of Fire and Explosion and Emergency Response)
Regulations 1995.
(38) Forthwith Study; Evaluation, Escape and Rescue Analysis Methodology, Cullen Team.
(39) Forthwith Study; Emergency Systems Review Methodology, Cullen Team.
(40) Occupational Risk, HSQ/SE/93/004 rev 1 , April 1993.
(41) XEU HSE Exposure Management – Position Paper, HSQ.
References
Add 1-2 November 2001 Issue 1
Best Practice QRA UKCS-TS-014
Addendum 2
HSQ Controlled Documents
Addendum 3
Safety Engineering Guidance Documents