Professional Documents
Culture Documents
ukcsts015_iss1am01
ukcsts015_iss1am01
ukcsts015_iss1am01
Contents
Paragraph Page
Uncontrolled
1 Introduction 1
1.1 Implementation of BP Group Policy 1
1.2 HSE Risk Management 1
3 BP HSE Expectations 2
3.1 Main Objectives 2
3.2 Assessment, Assurance and Improvement 3
Contents (cont’d)
Paragraph Page
Uncontrolled
6.6 Fabrication and Installation 9
6.7 Operation 9
6.8 Abandonment 9
Addendum 1 References
Issue Authority
Name: Jon Turnbull
Signature: ________________________________________________
Date: ________________________________________________
Technical Authority
Name: David Aberdeen
Signature: ________________________________________________
Date: ________________________________________________
Amendment Record
AMOSAF.171
Amendment Summary
Distribution List
Virtual Copyholders
Copy Copyholder
Uncontrolled
Preface
Purpose
This document gives guidelines on the risk analysis procedures that should be applied to new
and existing facilities; the occasions when they are carried out and the methodologies which
can be used, and includes the role of acceptance criteria in assessing the acceptability of the
risks identified.
Document Status
Uncontrolled
This document is quite old and needs significant revision but the basic principles remain valid.
This document outlines the role of various hazard identification and risk assessment processes
used throughout the life of a facility.
The main areas requiring revision include:
• Techniques currently used by the wells/drilling community
• Including better coverage of environmental risks
• Cross-referencing with Capital Value Process (CVP)
Responsibility of Copyholders
It is the responsibility of the registered copyholder of controlled hard copy versions to
maintain the accuracy of the document by ensuring that all updates are promptly
incorporated and acknowledged.
Furthermore, the registered copyholder of controlled hard copy versions must at all times
maintain custody of this document unless prior approval is given by the relevant
Technical Authority.
The roles and responsibilities of copyholders and ‘virtual’ copyholders are detailed in Section 1
of the Document Control Procedure (UKCS-DCM-001).
Uncontrolled
List of Abbreviations
1 Introduction
1.1 Implementation of BP Group Policy
The introduction to GHSER (Addendum 1 Ref 1) states that our goal is that ‘BP will be
distinctive worldwide in our pursuit of and attainment of HSE performance’.
It also states that a key process in achieving this goal is ‘through regular risk
assessments and risk management programmes’.
This is further emphasised within the 13 elements of GHSER (Addendum 1 Ref 2) and in
the BP Group HSE Standard on Process Safety/Integrity Management (Addendum 1
Ref 3), as detailed in Paragraph 3.
2.2 Purpose
Risk analysis should be used to help make timely and informed decisions about the
acceptability of any of BP’s activities which may have implications for the health and
safety of individuals, the environment, BP’s facilities and business success. It will be
applied not just to day-to-day activities on an ongoing basis, but will be used as a
fundamental guide in all development work to help ensure that decisions on the way
forward are made at a time when any necessary changes can most easily be introduced.
2.3 Content
Paragraph 3 describes the BP overall loss control objectives. The application of risk
analysis techniques is an essential element in the achievement of these objectives.
Paragraph 4 describes the range of risk analysis techniques which may be used during
Uncontrolled
each of the phases referred to above. The approach will vary markedly from one phase
to another but will consist essentially of:
• Hazard identification
• Consequence analysis (qualitative and quantitative)
• Risk analysis (qualitative and quantitative)
• Risk assessment (comparison with risk acceptance criteria)
• Identification of risk reducing measures
• Assessment of risk reducing measures and ALARP demonstration
Paragraph 5 outlines the approach that will be adopted when assessing the risk reducing
measures identified.
The detailed approach to each of the phases of activity which should be applied is further
described in Paragraph 6.
Paragraph 7 refers to the approach to the updating of risk analyses.
3 BP HSE Expectations
3.1 Main Objectives
Summaries of the main HSE Expectations relevant to risk assessment are set out below.
Details are contained in Addendum 1 Ref 2.
• Element 2 Risk Assessment and Management
We will regularly identify the hazards and assess the risks associated with our
activities. We will take appropriate action to manage the risks.
• Element 5 Facilities Design and Construction
Potential hazards are identified and HSE risks assessed, using appropriate risk
assessment tools at specific stages of a project from concept through to startup,
and risks are mitigated through risk management techniques.
Uncontrolled
critical, based on a qualitative assessment, will be subject to a more formal review,
such as task risk assessment (Addendum 1 Ref 6). In this manner, effective controls
appropriate to all sources of loss identified with specific tasks will be implemented.
When ‘one-off’ tasks arise, these will be subject to a similar review and, if deemed
necessary, a full task risk assessment, so that a work plan can be devised which
reduces any risk to an acceptable level and as low as is reasonably practicable.
Tasks which involve operations on a hazardous process plant should include a HAZOP
to ensure identification of hazards.
Work on electrical equipment should be covered by an Electrical Task Criticality
Assessment.
• Other Analyses
In the UK it is a legal requirement that all risks are assessed. These assessments
should be documented unless they are so self-evident and repeatable that
the assessment can be readily reproduced by non-specialists. Specific required risk
assessments include COSHH, Noise, Manual Handling and Environmental Impact
assessments.
4.2.1 Modifications
All process and facility modifications should be subject to the Facilities Change Process
(Addendum 1 Ref 4) in which qualified personnel review all such proposals and assess
the impact on the levels of risk, utilising the results from other studies they may
commission, eg HAZOP. Changes to mode of operation and procedures will also be
subject to a similar level of review.
4.2.2 HAZOP
Hazard and Operability Studies (HAZOPs) will be applied to engineering drawings
(P&IDs) pre-sanction and at a detailed design stage. This is a team-based approach
intended to identify all the conceivable hazards and problems that could prevent safe and
efficient operation of a plant (Addendum 1 Ref 8).
Uncontrolled
QRA associated with major hazard events will be undertaken in two phases of
the development of a major project – a concept safety evaluation at concept
design stage, and a more detailed approach at the final design stage (refer to
Paragraph 6 for more details).
The need for further QRA on existing Installations/operations will be selectively
undertaken when circumstances suggest it is appropriate, eg new knowledge;
in examining significant hardware or operational modifications, changes of use or
extensions to existing plant or where a major accident either within BP or elsewhere in
the industry suggests the possible need to retrofit additional safety equipment.
4.4.1 General
Uncontrolled
Prior to carrying out a risk analysis, suitable risk acceptance criteria will be defined to
enable decisions to be made on the basis of the analysis. These criteria will clearly
reflect the risk assessment method employed. Consequently they may range from
purely qualitative at one extreme through to fully quantitative at the other. In all cases
risk analysis should not be used in isolation or in a mechanistic way. It provides one input
into the decision-making process.
Priority should also be given to passive or inherently safe options. Active protection
options which rely on a number of devices to operate and/or human intervention
may fail.
6.1 Seismic
The potential for safety, environmental and financial losses should normally be assessed
using qualitative techniques.
6.2 Drilling
The nature of drilling requires substantial materials handling and interfacing with
operational machinery. The potential for injury and discharge to the environment is high,
as reflected in historical accident statistics. Rigorous task risk assessments should
therefore be carried out to help ensure that drilling operations are carried out with
exposures to loss suitably controlled.
Drilling also presents major hazards which are divided into those connected with
structural integrity and stability, and those connected with uncontrolled releases of
hydrocarbons. For the latter the emphasis is normally placed on maintaining barriers to
contain the reservoir fluids and the risks associated with barrier failure. These risks
should be systematically analysed using quantified techniques where appropriate to
ensure that all measures to prevent, control and mitigate accidental events are taken to
reduce residual risks below the maximum tolerable levels and further reduce them to as
low as is reasonably practicable.
Other risks include dropped objects and those associated with simultaneous or
combined operations.
Uncontrolled
existing development, all of the safety, environment and financial loss exposures should
be reviewed and incorporated in the concept selection process. A ranking of possible
concepts in terms of these issues should be made which, with appropriate weightings,
can be taken into account along with other technical and financial factors.
6.5 Design
More specific and deeper studies will be undertaken at the detailed design stage,
eg to define ‘design scenarios’ for active/passive fire protection and explosion design,
and assess reliability of critical systems. For each area of use, pre-defined standards of
acceptability will be used to assist in evaluating the results. The objective will be
to assess if remedial measures are clearly worthwhile, unnecessary or marginal.
In the latter case, a cost benefit analysis may be employed to assist decisions on
high-cost options.
At the end of design the continuing validity of the concept safety evaluation will be
reviewed and if necessary, the study updated.
6.7 Operation
Occupational hazards associated with the operational phase will be identified, ranked and
evaluated using a formalised review such as task risk assessments.
Any one-off tasks are considered on an individual basis as they arise and will be subject
to review using task risk assessment or HAZOP approaches.
The overall QRA available at the end of design will be regularly reviewed and updated,
Uncontrolled
6.8 Abandonment
When decisions on abandonment are made, a review will be made at the time to identify
the appropriate risk analysis methodology.
As with concept selection the HSE and financial loss exposures of each option should be
evaluated prior to selecting the abandonment route.
Addendum 1
References
(6) Task Risk Assessment Procedure as described in Integrated Safe System of Work
(UKCS-SSW-002).
(7) Engineering Technical Practice ETP SP 48-1 HSE Review of Projects.
(8) Guidelines for HAZOP Studies (UKCS-TS-001).
(9) Technical Integrity Performance Standards (UKCS-TI-001).
(10) Guidelines for HAZID Studies (UKCS-TS-002).
(11) Use and Value of Quantified Risk Assessment, GN 91/13.
(12) Guidelines on the Application of Risk Acceptability Criteria (UKCS-TS-003).
(13) Methodology for Rapid Concept Risk Assessment (UKCS-TS-010).
References
March 2002 Issue 1/AM01 Add 1-1/2