Professional Documents
Culture Documents
Failure Analysis of Crane Rope
Failure Analysis of Crane Rope
Submitted by:
Muhammad Arfan (LS1101201)
Syed Imran Jawaid (LS1105202)
PROBLEM STATEMENT
– Background
– Rope Bounce Analysis
– Visual Observations
ROPE AND SHEAVE DETAILS
The rope was a general engineering 18 strand
non-spin type designed as 12x7(6/1)/6x7(6/1)
Fig.2 Fig.3
VISUAL INSPECTION
• Cracks on both inner and inner layers were
associated with flattened regions on the
wires. Cracking was also observed on wires well
away from this region (Figure 4).
Fig.4
SECOND STEP
– Tensile Testing
– Rope Damage Analysis
– Fractography
TENSILE TESTING
• Before performing tensile testing of the rope, it was
necessary to establish the original grade and size of the
wire rope. This would indicate what degradation of
properties had taken place over the service life, and
provide an indicator of the severity of service and
quality of maintenance.
• The only information that the operator could supply,
was that the rope was a 1770 MPa grade.
• Thus it was necessary to measure the diameter of wires
near to the break (average approximately 1.5 mm) and
the rope diameter (approximately 21.5 mm).
• Information contained in the wire rope manufacturer's
table of properties has been used to find the most likely
original rope diameter and breaking force.
ROPE DIAMETER AND BREAKING LOAD
ESTIMATION
Manufacturer's data for a range of general
engineering ropes which bracket the measured size
information is given in Table 1.
ROPE DIAMETER AND BREAKING LOAD
ESTIMATION
1st Approximation: 26mm diameter
It might initially be thought that the diameter
of both rope and individual wires would have
reduced in service. However, although the rope
diameter would decrease due to bedding in of
the strands, It is unlikely that wire diameter
would change in the absence of significant
plastic deformation
ROPE DIAMETER AND BREAKING LOAD
ESTIMATION
2nd Approximation: 24mm diameter
This appears to be the correct specification for the
original load, and the error in measuring wire
diameter is at least 0.02 mm.
Original rope diameter 24 mm, wire diameter 1.5
mm and as manufactured rope breaking force = 332
kN.
ROPE DIAMETER AND BREAKING LOAD
ESTIMATION
3rd Approximation: 22mm diameter
Fig.4
ROPE DAMAGE ANALYSIS
High Strands
The damage is not due to a high strand although
at first glance the surface of wires in Figure 4 may
seem worn due to the presence of the flat spots.
Close inspection reveals cracks associated with the
flat regions. Little evidence of any severe abrasion is
evident.
ROPE DAMAGE ANALYSIS
Fatigue- Small Sheave
Although cracks are visible in the wires in Figure
4, which is likely to indicate operation of a fatigue
mechanism, no wires have been bent out of place.
Repeated bending over too small a sheave would
lead to such movement of individual wires.
ROPE DAMAGE ANALYSIS
Fatigue- Normal Sheave
The observed damage appears to correlate with
fatigue damage occurring through bending under
normal loads over a sheave of the correct size. The
flat regions are surface deformation, possibly
occurring as a result of groove wear during service.
Plastic deformation to regions of the surface of
some wires has occurred during service. Fatigue
cracks have been induced at some of these
hardened regions during bending over the sheave.
ROPE DAMAGE ANALYSIS
Inference- secondary Effect
This seems to be a correct inference from the tensile test
data. Some fatigue cracking of wires is present in the rope, and
the breaking load has been reduced by some 30%. Nonetheless,
this load of 232 kN (23.2 tonnes) is much higher than the load
reportedly being lifted at the time of failure (2.5 - 3 tonnes). The
fatigue cracking is unlikely to have been a direct contributor to
the failure, unless one rope section was more defective than
indicated by this single tensile test.
A 30% reduction in breaking load due to the presence of
fatigue cracks implies that the mechanism is unlikely to have
been a primary cause of the failure, unless the section of rope
which failed was more defective than the test piece.
ROPE DAMAGE ANALYSIS
Inference -Primary Effect
It is unlikely that fatigue cracking in the wires
was a primary contributory factor in this failure. The
observed breaking load of 232 kN (23.2 tonnes) is
much greater than the load reportedly being lifted. It
is worth keeping in mind, for possible future review,
the possibilities that either the loadwas much greater
than reported or that a particular rope section was
more defective than implied by the tensile test.
FRACTOGRAPHY
• A number of individual broken wires were cut off the fractured ends
and examined at low magnification using stereo binoculars, and at
high magnification in a scanning electron microscope (SEM).
• The total number of wires in all strands was 108, and 20 wires were
selected from the outer strands and 11 from the inner strands.
• The wires were de-rusted and ultrasonically cleaned in a de-greasing
agent.
FRACTOGRAPHY
• Summary of fracture types observed with number of occurrence is
presented in Table below;
31 1 2 3 0 2 2 9 17 26
FRACTOGRAPHY
• Typical SEM observations of the fracture surfaces are given below at
both a low and a high magnification.
Low magnification fractograph of cup-and-cone. High magnification fractograph from the central
region of the cup-and-cone fracture.
FRACTOGRAPHY
Type 2: Flat Twisted Failure
– Summary
– Conclusion
– Recommendations
SUMMARY
• Overall, the strength of the rope was reduced by the presence of fatigue cracks -
this is evidenced by the observed tensile strength of 232 kN compared with the
manufacturers stated breaking load of 332 kN.
• The observed breaking load is still very much higher than the stated load being
lifted at the time of failure (some 25 - 30 kN). Thus the rope must still have failed
through application of an overload relative to its current strength level. The failure
was not solely due to the presence of fatigue cracks (whose existence is fairly
normal in wire ropes and explains the requirement for regular maintenance and
high factors of safety).
• The cause of this overload is not clear, but bouncing of the load might have
allowed the rope to jump from its groove and jam between sheave and boom
during winding. If this state of affairs could exist for a short time undetected, and
the rope winding was continued, a very significant overload could be applied to the
rope.
SUMMARY
The cause of the fatigue cracks needs clarification. They can initiate as a result of
bending stresses induced by too small a sheave diameter. The recommended
diameter is 18x rope diameter which equals 432 mm for the resent rope. The
actual sheave diameter was 520 mm, which should have been sufficient. As the
sheave was older than the rope, however, it is possible that wear of the sheave
groove has had an influence. Fatigue cracks can result from deformed surface
regions where ductility thus becomes exhausted, particularly if surface damage
from abrasion occurs. This would be exacerbated by any decrease in sheave groove
diameter, which could occur by wear during service, and by poor lubrication
practice (which was apparently the case).
CONCLUSION
• The conclusion to be drawn from this investigation is that the
presence of fatigue cracks has lowered the breaking load of the rope
by some 30%. However, the breaking load is still 232 kN, very much
higher than the stated lifting load of 25 - 30 kN. The fractographic
work has indicated ductile fracture in all wires, demonstrating that
the rope metallurgy is up to specification. The most likely cause of
the fracture seems to be rope jamming between sheave and groove,
probably due to bounce during lifting. The cause of the bouncing is
unknown.
• In insurance terms, poor maintenance is not a prime cause of the
failure, which would have been "sudden and unexpected" when it
occurred. Cover should exist for such circumstances.
RECOMMENDATIONS
Recommendations in the present case are:
• Ensure adequate lubrication is maintained in the rope.
• Re-groove the sheave at regular intervals and, particularly, when the
rope is replaced by a new one.
• Control lifting to avoid bouncing and install detectors which are
activated by rope coming off the sheave.
• Monitor condition of rope by surface inspection and tensile testing.
REFERENCES
1. J Llorca and V Sanchez-Galvez (1989) Fatigue and Fracture of Engineering Materials and Structures
Vol. 12 No. 1 pp31-45
2. RE Hobbs and K Ghavami (1982) International Journal of Fatigue April 1982 pp69-72
3. NF Casey and WK Lee (1989) International Journal of Fatigue Vol. 11 No. 2 pp78-84.
4. M Alani and M Raoof (1997) Effect of mean axial load on axial fatigue life of spiral strands,
International Journal of Fatigue Vol. 19 No. 1 pp1-11
5. K Coultate (1997) Magnetic attraction of wire rope testing, Materials World Vol. 5 September 1997
pp519-520.
6. K Schrems and D Maclaren (1997) Failure analysis of a mine hoist rope, Engineering Failure Analysis,
Vol. 4 No. 1 pp25-38.
7. MD Kuruppu, A Tytko and TS Golosinski (2000) Loss of metallic area in winder ropes subject to
external wear, Engineering Failure Analysis, Vol. 7 No. 3 pp199-207.
8. J-I Suh and SP Chang (2000) Experimental study on fatigue behaviour of wire ropes, International
Journal of Fatigue Vol. 22 pp339-347.
9. M Torkar and B Arzensek (2002) Failure of crane wire rope, Engineering Failure Analysis, Vol. 9 No. 2
pp227-233.