Professional Documents
Culture Documents
ukcssop018_iss1
ukcssop018_iss1
Contents
Paragraph Page
Uncontrolled
3 Shift Handover 6
Issue Authority
Name: John Watson
Signature: ________________________________________________
Date: ________________________________________________
Technical Authority
Name: Dave Wall
Signature: ________________________________________________
Date: ________________________________________________
Amendment Record
AMOSAF.171
Amendment Summary
Distribution List
Virtual Copyholders
Copy Copyholder
Uncontrolled
Preface
All holders of this document are registered so that they can be sent updates and be kept
informed of changes or reviews.
Responsibility of Copyholders
It is the responsibility of the registered copyholder of controlled hard copy versions to
maintain the accuracy of the document by ensuring that all updates are promptly
incorporated and acknowledged.
Furthermore, the registered copyholder of controlled hard copy versions must at all times
maintain custody of this document unless prior approval is given by the relevant
Technical Authority.
The roles and responsibilities of copyholders and ‘virtual’ copyholders are detailed in Section 1
of the Document Control Procedure (UKCS-DCM-001).
• Valuable production time is saved by being able to repair leaks prior to the ‘startup’
date and without the requirement to gas free
• Does not wet equipment surfaces and so reduces corrosion potential
• Used with helium tracer leak detection is reliable
Uncontrolled
this purpose. However, if full flow pressure relief is not available via a plant system, then
consideration should be given to the use of temporary PSVs supplied by the leak test
contractor. If full flow pressure relief is not provided, then a Stage 2 risk assessment
should be completed, and assurance gained that there is sufficient control in place to
manage the HP/LP interface.
If it has been identified that the leak test contractor will have to supply PSVs,
consideration should be given to the location that these PSVs would vent to in an
emergency. The vent location should be surveyed and approved by the Installation Area
Authority with guidance from the leak test contractor on expected nitrogen plume.
2.6 Accountabilities
The BP Area Authority will be accountable for the Installation plant and equipment and
ensuring that BP standards have been applied prior to commencement of the leak
testing activity.
The BP Area Authority will be accountable for managing the overall activity on their
Installation but will be specifically accountable for valve line-up and control of valves.
The leak test contractor will be accountable for their leak test equipment and working to
their company standards and procedures. The leak test crew are normally held
accountable by their companies for valve checks and ensuring valve line-up is as detailed
in the procedure. This will not detract from the accountabilities of the BP Area Authority
with respect to the management of the BP plant and equipment. The BP Area Authority
should ensure that a BP Isolating Authority has checked the position of all valves in the
system prior to the introduction of nitrogen.
Uncontrolled
The BP Area Authority will approve the leak test procedure prior to the leak test.
Prior to pressurisation, the BP Area Authority or delegate and Leak Test Supervisor shall
walk through the system to be tested with the marked up P&IDs and verify
the following:
• Battery limits are as specified
• Isolations including valve positions are as specified
• Secondary isolations are as specified
• Injection points are as specified
• Overpressurisation protection and monitoring positions are as specified
• Sufficient provision is made for the rapid and safe depressurisation of a system
should it be required as indicated on the P&IDs
• The test area is adequately barriered off
• Leak test contractor’s relief valve is on line and settings are as specified
• Overpressure protection skid is set to the pre-determined setting
• All precautions specified on the permit are in place
Uncontrolled
• The manual valves in the safety routes, PSVs and depressurisation routes should be
locked under Installation isolation control
• High Pressure/Low Pressure (HP/LP) interfaces (with the exception of interface to
flare and pressure rated closed drains systems) should be protected by double block
and bleed isolation
• Attached HP systems can be isolated by single valve isolation but there must be a
locked open vent path under Installation isolation control to ensure there is no
pressure buildup in the attached system
Note: The following drawing is an example only.
TO OPP CHART
RECORDER
TO FLARE
TO FLARE
LO LO LO
PSV TO FLARE
LO
FROM WELLS
HP SEP
LC
TO LP SEP
LC LC
NITROGEN
INJECTION LO
UKCSSOP018.008
A minimum safe practical distance for barriers shall be set at a distance where it is
physically impossible for an individual to touch any part of the system under pressure
without crossing the barrier.
A maximum safe practicable distance must be maintained in all circumstances given the
nature and location of the pressurising medium.
The BP Area Authority or his delegate will walk through the system to be tested and
agree the location of all of the barriers to ensure the above standards are satisfied.
Tannoy announcements should be made prior to commencing the leak test and at
regular intervals throughout the leak test programme.
Uncontrolled
for 1 year after the leak test has been completed.
The completed test pack shall include the following information:
• Marked up P&IDs showing the detected leaks location
• Certificate of test completion
• Leak description reports
• Pressure recorder chart (where applicable)
3 Shift Handover
At every shift change the leak test contractor will be expected to conduct a verbal and
written account of the previous shift’s operations. The oncoming BP Isolating Authority
for the area of plant under leak test must attend the shift handover.
The shift handover period should include (when appropriate) a complete ‘walk through’
of the systems under test in order to identify strategic areas or points.
Addendum 1
Liquid Nitrogen Spillage Containment Procedure
The purpose of the containment facility is to fully contain any liquid nitrogen in the unlikely
event of a spillage from the bulk storage vessels, cryogenic hoses, pipework and connections.
The containment area insulates the steel deck from the extremely low temperature of the liquid
nitrogen (-196°C) and therefore protects the steel deck from any shrinkage and subsequent
cracking. The containment facility should be large enough to house the nitrogen storage tanks,
the nitrogen pump unit and the liquid nitrogen transfer hoses that connect these two items.
A charged fire hose should also be onsite to help vaporise any spillage within the bund.
The following procedure should be followed to ensure compliance with the above:
Uncontrolled
(1) Cover the steel deck of the equipment laydown area with timber (scaffold boards).
These should be placed as flat as possible so as not to create a trip hazard to personnel.
Uncontrolled
(2) Build the outer perimeter of the containment facility up by a further two scaffold boards
in height.
(3) Place tarpaulins over the entire area on top of the scaffold boards. Allow the tarpaulin to
drape over the raised boards at the perimeter of the containment facility.
(4) To help retain the tarpaulin in position, place further scaffold boards onto the perimeter,
trapping the tarpaulin between the scaffold boards.
(5) The nitrogen equipment can now be placed in position leaving sufficient space between
the units to allow access.
Uncontrolled
(6) Further scaffold boards should be placed around the operating panel (inside containment
facility) to prevent personnel slipping on a wet tarpaulin.
Addendum 2
Nitrogen Leak Test Checklist
The following points are the key points that should be applied when working with nitrogen. They have been
extracted from each of the sections in this document:
Check the inspection records to confirm the system pressure envelope integrity is good.
Reduce the volume of nitrogen by liquid filling vessels when possible.
There should be three levels of system pressure protection – manual pressure monitoring and pump
control, automatic shutdown via an Over Pressure Protection Device and full flow PSV relief.
If the leak test contractors temporary PSVs are used, a site survey should be conducted to determine
a safe location for emergency venting.
Ideally, depressurisation should be via the platform flare system.
An emergency depressurisation route should be identified and ideally this depressurisation route will
be remote operated and automatically operated on a platform trip and blowdown event.
Check for NRVs in the system and understand the implications of their position relative to
pressurisation and depressurisation.
Every leak test will be individually risk assessed.
The BP Area Authority is accountable for valve line-up and isolation on BP equipment and for the final
approval of the leak test procedures.
Decanting of nitrogen from one system to another will be subject to a written procedure approved by
the Process Engineering Technical Authority.
The isolations for the leak testing should be reviewed in the risk assessment. Leak test isolations may
deviate from the SIRP procedures as the leak test isolations are not intended to make plant safe for
intrusive maintenance.
The pumping unit shutdown system should be connected to a platform power source that will
automatically trip the unit during a platform emergency.
The recommended maximum acceptable leak rate is 40scf/year.
Leaks should only be repaired with the system fully depressurised.
System pressurisation should be done at an initial low pressure to check for gross leakage followed
by 25% increments of final test pressure.
Barriers should be erected around the leak test site with warning signs at all access points and at
suitable points around the boundary.
Shift handovers will include the attendance of the BP Isolating Authority for the area being tested.
UKCSSOP018.007