Professional Documents
Culture Documents
CV-Saad-2024
CV-Saad-2024
EXECUTIVE SUMMARY:
Name:
SAAD ALI SIDDIQUI, PE, PMP, NEBOSH
Education status:
Master of Business Administration (Executive) - IBA, Karachi
Master of Engineering (Construction Management) – NED University, Karachi
Bachelor of Engineering (Civil Technology) – NED University, Karachi
Professional 20 years project management experience of Power Plants, Transmission structures,
Exposure: Grid-stations Office buildings, pipelines laying and Solar electric system installation
with a proven record of success in managing projects, facilities and company asset
while maintaining high standards of construction.
Specialty:
Project Management, Contracts Administration, HSE & Procurement.
Affiliations Project Management Professional (PMP, PMI)
IRCA certified “Lead Auditor”
NEBOSH IGC
Professional Engineer – PEC
Father’s Name:
Arshad Ali
Date of Birth:
December 4, 1981
Marital Status:
Married
Address:
House No. A-180 Block 3, Gulshan-e-Iqbal, Karachi 75300.
Phone #:
+923468223672, +923332120733, +922134974189,
E-Mail Address: saad81in@gmail.com , saad.ali@ke.com.pk
Objective It’s my heartiest desire to pursue challenging position in a professional, progressive &
well- reputed organization, utilizing my best of Project Management and Contract
Administration capabilities with dedication and honesty.
Managing, planning, organizing and executing civil construction projects that meet
approved cost, quality, scope, and time targets to enable the larger goals of the business
plan to be achieved.
Plan, schedule and control project implementation for costs, timeline, quality and
adherence to HES requirements.
Responsible for forming the Project Management Team (PMT) from concerned
departments and lead the PMO.
Prepare a FEED package for preparing the Cost Estimate. Prepare work package for the
required capital projects funding.
Monitor cost of project & implement program for cost reduction.
Regularly review and improve design layouts plans to ensure quality, minimize wastage,
improve construction time and increase costs savings.
Participate in continuous improvement and value engineering exercise to reduce CAPEX
and OPEX.
Ensures that Safe Work Practices are understood and implemented, by both internal and
external construction providers, as appropriate. Provides assistance to disseminate HESQ
awareness and ensures compliance of HESQ policy.
Implement ESG initiative of 5R and 5S across the network.
To prepare annual construction budget of the company for board approval.
To monitor and technical scrutiny of Project procurements.
ISO 9001:2008 certification for entire department as MR.
User satisfactions surveys and feedback
Liaison with civic agencies to obtain approvals for transmission lines ROW.
Technical designing of solar panel installation.
Continuous process improvement and cost curtailment.
Major Projects: In my 20 years association with industry, some projects are:
Construction Works
Project Manager for construction of 560MW power plant – BQPS II.
Civil works for installation of 2 x 110 MW generators at KPC power plant.
Construction of state of the art NOC for KE main SCADA facility Head office.
Construction of Tier 2 Data center comprises of 38 racks.
Led construction of K-Electric Head Offices having (24000 sft) as Project Manager. It includes
292KW solar system installation. This project is considered as sign of cultural transformation
and trend setter for the company.
Successfully manage revamping of Distribution office (45000 sft). Project features comprises
of establishment of Call Centre for 175 desks with IVR.
Construction of KE’s first LEED certified Gridstation at Gulshan-e-Mayamar.
Project Manager for Rehabilitation of abandon KESC Training Centre (Gr.+3, 26000 sft) with
contemporary features e.g 200 seats Pre-fab auditorium, Computer labs, Dummy Electric
Network, Class rooms and laboratories, Canteens, Workshops, car parking, Fire fighting
system & Air-conditioning etc. as Project Leader.
Establishment of KE Mega center having contemporary architecture and modern design.
220KW solar system installed to make it a Zero Building.
Dredging of Lagoons and Intake channel at KTPS and BQPS II on periodic basis.
Construction of Steel structures for Mechanical workshop, Filter house and temperature
controlled ware house for inventory management.
Major maintenance of Pipri, KCR, Maripur “220KV GIS Grid-station.
Laying of 18” dia gas pipeline at KPC Power plant.
Construction of Fire walls, rehabilitation of Bunkers, Gantry, Overhead towers foundation
etc . Civil Incharge of Substation construction and maintenance.