Modjo - Hawassa Design and Build Highway Project; Lot3: Batu (Zeway) - Arsi Negele, ID.No.

W/03/ICB/L/IDA/2008 EFY
DESIGN PHASE (PRELIMINARY -TECHNICAL)

Overall Overall
percentage percentage from
It. Item / Description Reviewed/
from the Design the Design Stage Sumission to Resubmitted Status
Stage (100%) (2%) Commented Approved by
the Client to theClient
by Client the Client(10%)
(50%) (10%)
(30%)

1 INITIAL PROGRAM OF PERFORMANCE 0.59% 0.01% 50% 30% 10% 10% 100% 0.012%

2 CENTER LINE 0.59% 0.01% 50% 30% 10% 10% 100% 0.012%

3 ROUTE LOCATION PROPOSAL 1.76% 0.04% 50% 30% 10% 10% 100% 0.035%

4 GEOTECHNICAL SITE INVESTIGATION PROGRAM 1.18% 0.02% 50% 30% 10% 10% 100% 0.024%
5 REST AREA PROPOSED LOCATION 0.59% 0.01% 50% 30% 10% 10% 100% 0.012%
6 TRAFFIC MANAGEMENT PLAN 0.59% 0.01% 50% 30% 10% 10% 100% 0.012%
7 DESIGN QUALITY ASSURANCE PLAN 4.12% 0.08% 50% 30% 10% 10% 100% 0.082%
8 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN 1.18% 0.02% 50% 30% 10% 10% 100% 0.024%
9 TOPOGRAPHICAL SURVEY REPORT 6.47% 0.13% 50% 30% 10% 10% 100% 0.129%
10 INCEPTION REPORT 7.06% 0.14% 50% 30% 10% 10% 100% 0.141%
11 GEOMETRIC DESIGN 0.303%
11.1 Geometric Design MainHighway (Report & Drawing)
11.1.1a Preliminary Geometric Design (Plan&Profile) Segment 92+584 to 117+000 0.22% 0.00% 50% 30% 10% 10% 100% 0.004%
Geometric Design MainHighway (Report & Drawing) Segment 92+584 to
11.1.1b 4.40% 0.09% 50% 30% 10% 10% 100% 0.088%
117+000
11.1.2a Preliminary Geometric Design (Plan&Profile) Segment 117+000 to 125+000 0.22% 0.00% 50% 30% 10% 10% 100% 0.004%
Geometric Design MainHighway (Report & Drawing) Segment 117+000 to
11.1.2b 1.45% 0.03% 50% 30% 10% 10% 100% 0.029%
125+000
11.1.3a Preliminary Geometric Design (Plan&Profile) Segment 125+000 to 130+000 0.22% 0.00% 50% 30% 10% 10% 100% 0.004%
Geometric Design MainHighway (Report & Drawing) Segment 125+000 to
11.1.3b 0.77% 0.02% 50% 30% 10% 10% 100% 0.015%
130+000
11.1.4a Preliminary Geometric Design (Plan&Profile) Segment 130+000 to 150+000 0.22% 0.00% 50% 30% 10% 10% 100% 0.004%
Geometric Design MainHighway (Report & Drawing) Segment 130+000 to
11.1.4b 3.63% 0.07% 50% 30% 10% 10% 100% 0.073%
150+000
11.2 Geometric Design Interchanges (Report & Drawing)
11.2.1 Geometric Design Bulbula Interchange (Report & Drawing) 2.00% 0.04% 50% 30% 10% 10% 100% 0.040%
11.2.2 Geometric Design Langano Interchange (Report & Drawing) 2.00% 0.04% 50% 30% 10% 10% 100% 0.040%
12 GEOTECHNICAL REPORT 0.249%
12.1 Geotechnical and Subgrade Investigation 2.00% 0.04% 50% 30% 10% 10% 100% 0.040%
12.2 Earthworks Geotechnical Design and Recommendations
Earthworks Geotechnical Design and Recommendations (Segment 92+584 to
12.2.1 2.00% 0.04% 50% 30% 10% 10% 100% 0.040%
116+000)
Earthworks Geotechnical Design and Recommendations (Segment 116+000 to
12.2.2 3.00% 0.06% 50% 30% 10% 10% 100% 0.060%
150+000)
12.3 Material Report 1.25% 0.03% 50% 30% 10% 10% 100% 0.025%
Preliminary Geotechnical Assessment for Foundation of Bridges and Major
12.4 1.50% 0.03% 50% 30% 10% 10% 100% 0.030%
Structures
12.5 Geotechnical Report for Structures
12.5.1 Geotechnical Report for Structures (Segment 92+584 to 117+000) 2.10% 0.04% 40% 0% 0% 0% 40% 0.017%
12.5.2 Geotechnical Report for Structures (Segment 117+000 to 125+000) 0.70% 0.01% 50% 30% 10% 10% 100% 0.014%
12.5.3 Geotechnical Report for Structures (Segment 125+000 to 130+000) 0.44% 0.01% 50% 30% 10% 10% 100% 0.009%
12.5.4 Geotechnical Report for Structures (Segment 130+000 to 150+000) 1.76% 0.04% 40% 0% 0% 0% 40% 0.014%
13 HYDROLOGY&HYDRAULIC REPORT 0.180%
13.1 Hydrology /Hydraulic Report (Sub-Section 1 from 93+000 to 114+000) 3.00% 0.06% 50% 30% 10% 10% 100% 0.060%
13.2 Hydrology /Hydraulic Report (Sub-Section 2 from 114+000 to 131+000) 3.00% 0.06% 50% 30% 10% 10% 100% 0.060%
13.3 Hydrology /Hydraulic Report (Sub-Section 3 from 131+000 to 150+000) 3.00% 0.06% 50% 30% 10% 10% 100% 0.060%
14 DRAINAGE REPORT 0.123%
14.1 Drainage Report & Drawing (Segment 92+584 to 117+000) 2.50% 0.05% 50% 30% 10% 10% 100% 0.050%
14.2 Drainage Report & Drawing (Segment 117+000 to 125+000) 1.00% 0.02% 50% 30% 10% 10% 100% 0.020%
14.3 Drainage Report & Drawing (Segment 125+000 to 130+000) 0.65% 0.01% 50% 30% 10% 10% 100% 0.013%
14.4 Drainage Report & Drawing (Segment 130+000 to 150+000) 2.00% 0.04% 50% 30% 10% 10% 100% 0.040%
15 TRAFFIC AXLE LOAD SURVEY REPORT 2.35% 0.05% 50% 30% 10% 10% 100% 0.047%
16 PAVEMENT DESIGN REPORT 2.50% 0.05% 50% 30% 10% 0% 90% 0.045%
17 STRUCTURES DESIGN 0.213%
17.1 Major Structures and Bridges 1.50% 0.03% 50% 30% 10% 10% 100% 0.030%
17.2 Structural Design Calculations (Report&Drawings) 0.183%
Overpasses Structural Design Calculations (Report&Drawings) Segment
17.2.1a 2.00% 0.04% 35% 0% 0% 0% 35% 0.014%
92+584 to 117+000
Underpasses Structural Design Calculations (Report&Drawings) Segment
17.2.1b 0.75% 0.02% 50% 30% 10% 10% 100% 0.015%
92+584 to 117+000
Overpasses Structural Design Calculations (Report&Drawings) Segment
17.2.2a 2.00% 0.04% 50% 30% 10% 0% 90% 0.036%
117+000 to 125+000
Underpasses Structural Design Calculations (Report&Drawings) Segment
17.2.2b 0.75% 0.02% 50% 30% 10% 10% 100% 0.015%
117+000 to 125+000
17.2.2c Bulbula Bridge Structural Design Calculations (Report&Drawings) 1.50% 0.03% 50% 30% 10% 0% 90% 0.027%
Overpasses Structural Design Calculations (Report&Drawings) Segment
17.2.3a 0.75% 0.02% 50% 30% 10% 0% 90% 0.014%
125+000 to 130+000
17.2.3b Hora Kelo Bridge Structural Design Calculations (Report&Drawings) 1.50% 0.03% 50% 30% 10% 0% 90% 0.027%
Overpasses Structural Design Calculations (Report&Drawings) Segment
17.2.4a 2.00% 0.04% 50% 0% 0% 0% 50% 0.020%
130+000 to 150+000
Underpasses Structural Design Calculations (Report&Drawings) Segment
17.2.4b 0.75% 0.02% 50% 30% 10% 10% 100% 0.015%
130+000 to 150+000
18 SIGNING AND ANCILLARY WORKS 0.162%
18.1 Permanent Signing concept Plan 3.00% 0.06% 50% 30% 10% 0% 90% 0.054%
18.2 Permanent Signing 6.00% 0.12% 50% 30% 10% 0% 90% 0.108%
19 RAP 0.070%
19.1 Updated Resettlement Action Plan (Draft) 1.50% 0.03% 50% 30% 10% 10% 100% 0.030%
19.2 Updated Resettlement Action Plan (Final) 2.00% 0.04% 50% 30% 10% 10% 100% 0.040%
Design Stage Accomplished percentage (2% based) 1.87%