Rate comparision with DSR 2023

Construction of Type-III Quarter (No. of Unit -8) and Boundary wall at Ghazipur Ghat between Ghazipur City – Yusufpur section in connection
with Mau-Tarighat New B.G. Line Project.

SN Item Description Qty Unit Rate in Rs. Total (in Rs.) Rate in Rs. Total (in Rs.)
Rate as per budgetary
A Building Rate as per DAR
quotations
Building Construction (G+1) including
plaster of celling, inside and outside wall,
1 and bottom slab casting. Note: i) Rate is 819.00 sqm 3302.00 27,04,338.00 4,280.02 35,05,335.54
inclusive of supply and fixing of
shuttering material.

B Boundary Wall

1 Construction of boundary

2 Brick Work with 1:6 or 1:4 mortar 66.00 Cum 1400.00 92,400.00 2,117.39 1,39,747.65

3 Concrete Work (PCC/RCC) 25.00 Cum 1830.00 45,750.00 2,917.67 72,941.70

4 Supply and fixing of shuttering 186 Sqm 450.00 83,700.00 639.80 1,19,003.32

6 Plaster work 470 Sqm 160.00 75,200.00 224.85 1,05,680.95


7 reinforcement Steel cutting binding 420 Kg 9.00 3,780.00 19.99 8,395.89

Total 30,05,168.00 39,51,105.04

Saving 9,45,937.04

Note:

ii) Rate is inclusive of 18% GST.


Cost for one building(204 sqm) as per DAR
Description Unit Quantity Rate Total
1 PLASTER WORK SQM 1411.7 224.9 317416.1
2 PCC 1:3:6 CUM 10.0 2334.4 23437.0
3 RCC M25 CUM 125.1 2917.7 364912.7
4 REINFORCEMENT KG 8372.0 20.0 167358.0
5 Total 873123.9
6 Per sqm 4280.02
DAR ITEM 6.1.1(BRICKWORK)

Code Description Unit Quantity Rate Rs. Amount Rs.


Details of cost for 1 cum
MATERIAL
9999 Sundries L.S. 2.73 2.27 6.2
LABOUR 0.0
0123 Mason (brick layer) 1st class day 0.36 897 322.9
0124 Mason (brick layer) 2nd class day 0.36 816 293.8
0115 Coolie day 1.37 736 1008.3
0101 Bhisti day 0.20 816 163.2
TOTAL 1794.4
18% GST 323.0
Cost of 1 Cum. 2117.4
PCC (1:3:6)
Code Description Unit Quantity Rate Rs. Amount Rs.
295 MTERIAL
LABOUR
155 Mason (average) day 0.1 857 85.7
114 Beldar day 1.63 736 1199.68
101 Bhisti day 0.7 816 571.2
Hire charges of Concrete Mixer
2 day 0.07 900 63
0.25 to 0.40 cum with hooper
12 Vibrator(Needle type 40mm) day 0.07 400 28
9999 Sundries L.S. 13.52 2.27 31
TOTAL 1978.27
GST 18% 356.09
Cost of 1 cum. 2334.36
Plaster
Column1 Column2 Column3 Column4 Column5 Column6 Column7
12 mm cement plaster of mix
13.1 :1:4 (1 cement: 4 fine sand)
13.1.1
Code Description Unit Quantity Rate Rs. Amount Rs.
3.4 Material cum 0.144 0 0
LABOUR
0155 Mason (average) day 0.67 857 574.2
0115 Coolie day 0.75 736 552.0
0101 Bhisti day 0.92 816 750.7
9999 Scaffolding and sundries L.S. 12.61 2.27 28.6
TOTAL 1905.5
Cost of 10.00 sqm 1905.5
Cost of 1.00 sqm 190.6
GST 18% 34.3
TOTAL 224.9
DAR Item Concrete of M25 grade with minimum cement
4.20.2.4 content of 300 kg /cum
no
Code Description Unit Quantity Rate Rs. Amount Rs.
Details of cost for 1.00 cum
MATERIAL
Production cost, pumping to respective floors and
0
laying in
position 0
Hire charges of Concrete Mixer 0.25 to 0.40 cum
2 day 0.07 900 63
with Hopper

Labour for pouring, consolidating & curing 0

0155 Mason (average) day 0.17 857 145.69


0114 Beldar day 2 736 1472
0101 Bhisti day 0.9 816 734.4
0012 Vibrator(Needle type 40mm) day 0.07 400 28
9999 Sundries L.S. 13.00 2.27 29.51
TOTAL 2472.60
GST 18% 445.068
Cost per 1.00 cum 2917.67
Reinforcement cutting binding placing
DAR item no 5.22A.1
code Description Unit Quantity Rate Rs. Amount Rs.
Details of cost for 1 quintal
MATERIAL 0
LABOUR
102 Blacksmith 1st class day 1 897 897
114 beldar day 1 736 736

9999 Sundries and biding wire L.S. 26.91 2.27 61.0857

TOTAL(for 100 KG) 1694.1


GST 18% 304.9
Details of cost for 100 kg 1999.0
Cost of 1 kg 20.0
SHUTTERING
DAR Item
Description Rate per SQM 18% GST TOTAL
No
5.9.1 Foundation footing base of coulmn 2756.4 275.64 49.62 325.26
5.9.3 Suspended floor, roofs, landings, 91201 675.56 121.60 797.16
5.9.5 lintel beam plinth beam 42619.6 546.40 98.35 644.76
5.9.6 Coulmn piller 30407.4 675.72 121.63 797.35
5.9.7 Stairs 31132.9 537.70 96.79 634.49
Average rate 639.80