Box Culvert Estimate
Box Culvert Estimate
EXISTING DESIGN
S.NO. TYPE OF PROPOSAL TYPE OF STRUCTURE SPAN ARRANGMENT
CHAINAGE CHAINAGE
1
PROJECT : CONSULTANCY SERVICES FOR FEASIBILITY STUDY AND PREPARATION OF DPR IMPROVEMENT AND UP-GRADATION OF " IN-
PRINCIPLE DECLARED AS NEW NATIONAL HIGHWAY IN THE STATE OF GUJRAT.
2 PCC M-15 for leveling course cum 1747.86 4005 3778.30 6,603,957.85
3 PCC M-20 for curtain wall & Toe wall cum 1472.06 4619 4357.55 6,414,588.32
4 RCC M-30 grade conc. For foundation cum 1598.69 4752 4483.02 7,166,948.47
5 RCC M-30 grade conc. For sub-structure cum 3134.99 5001 4717.92 14,790,655.65
6 RCC M-30 grade conc. For super-structure (box) cum 912.58 5125 4834.91 4,412,218.87
13 450mm thk floor apron (Rigid) cum 936.96 4072 3841.51 3,599,340.68
14 750 mm thk Stone Apron (Flexible) cum 2073.60 1516 1430.19 2,965,639.25
20 Filter media under stone pitching cum 540.76 869 819.81 443,325.20
Total 106,772,378.31
ROAD:-Ranavav-Bhanvad-Khambhaliya Road
3 PCC M-20 for curtain wall & Toe wall cum 4166.93 4619 19,247,026.58
4 RCC M-30 grade conc. For foundation cum 3900.40 4752 18,534,710.30
5 RCC M-30 grade conc. For sub-structure cum 6722.52 5001 33,619,337.52
6 RCC M-30 grade conc. For super-structure (box) cum 2412.68 5125 12,364,990.13
Total 244,753,745.25
ROAD:-Ranavav-Bhanvad-Khambhaliya Road