2) The Owner's Team (OT) has not been able to inspect and verify the completed gravel paving works due to FIN not
being raised, in accordance with approved FITP for Road and Paving Works. Consequently, as of now, the required
records specified in the approved FITP are not made available by Contractor. (Please refer to Attachment 1 for details on
the affected area).
3) Therefore,Contractor is required to propose remedies to the Owner and any deviation which not comply to
specification, IFC Drawings, etc. Which in the opinion of the Owner’s Engineer is unsatisfactory, shall be cut out and re-
constructed such work to the Owner’s Engineer’s approval as stated in MFS B14.2 Scope of Supply and Services
Reference Documents:
1) Project Quality Plan ,0-WD010-MZ711-00001
2) Field Inspection and Test Procedure,0-WD010-MZ711-00007
3) FITP For Road and Paving Works Rev. 1 ,0-WD800-CZ250-00019
4) MS For Road and Paving Works Rev.0,0-WD800-CC290-00030
5) MFS B0.1, B0.2 & B14
6) EPCC Contract
7) Drawing no: 0-WD800-EC115-01050_REV.E_ROAD & PAVING PLAN & SECTION (1)
8) Drawing no: 0-WD800-EC110-00003_Rev.C_CIVIL STANDARD DRAWING (3)
Issued by:
Signature: Signature:
Contractor
Issued by:
Signature: (Contractors Engineer) Signature: (Contractors QA Manager)
Name: Name:
Date: Date:
Reviewed by: Comments
Owner
Signature: (OE Engineer) Signature: (OE QA Manager/PM) (OE to state corrective action
Name: Name: acceptable or not)
Date: Date:
Corrective Action Implemented by Contractor
(Contractor's Engineer)
Actual photos of the completed gravel paving at various location within plant boundary