1.5 Providing and laying plain cement concrete of mix 1:3:6 over well compacted soil for
all depths including shuttering, ramming, curing etc. complete with all leads and lifts as Cum. 84.6 4354.34 368,413.11
per drawing and as directed by engineer in charge.
1.6 Supply and placing in position to lines and levels in situ concrete of grade M25 with
approved admixtures for rectangular drains in all heights and depths, types and size,
including watering, placing (pouring), necessary scaffolding, staging, hoisting,
formwork, leaving pockets for the pipe flanges, sockets, etc. as directed keeping drip Cum. 237 7952.53 1,882,406.24
moulds, grooves if any including curing, testing, etc. complete as per drawing and as
directed by engineer in charge.
Page 1 of 2
ABSTRACT OF RA Bill-01
Item BOQ
Description of Item Unit
No. Qty. Rate Amount
1.7 Providing, placing and fixing in position Fe415 grade reinforcement (conferming to
IS:1786), for insitu RCC work including straightening, cleaning, cutting, bending to
required shapes and lengths as per details, welding with apkproved electrodes, binding
Kg 24224 78.66 1,905,424.98
wires etc. complete for all heights and depths etc. as per drawing and as directed by
Engineer-In-Charge.
12,510,754.12