Professional Documents
Culture Documents
ukcsmal001Part2_iss1
ukcsmal001Part2_iss1
Part 2
Northern North Sea Field Information
Section 1
West of Shetland (WoS)
Paragraph Page
3 Communications 1-1-4
3.1 FPSO Vessel – Tanker – Rig – FSV – Foinaven –
Shore Communications Systems 1-1-4
3.2 FPSO Vessel – Helicopter Communications System 1-1-5
3.3 FPSO Vessel Radar System 1-1-5
3.4 FPSO Vessel Radar Transponder 1-1-5
Paragraph Page
Uncontrolled
Figure
1.1.1 Schiehallion FPSO Vessel Pre-entry Checklist 1-1-12
1.1.2 Schiehallion FPSO Vessel Elevation and
Crane Orientation 1-1-12
Schiehallion Foinaven
60° 21’ 25” N 60° 18’ 58” N
04° 3’ 58” W 04° 16’ 24” W
6 691 803m northing UTM* 6 687 460m northing UTM*
441 181m easting UTM* 429 657m easting UTM*
The following Schiehallion subsea development centres table lists the number of wells
planned to be drilled from each centre location:
Uncontrolled
1 static/1 shared
umbilical
West 439 379 E Manifold x 2 1 production
6 689 180 N (production/injection)
3 production wellheads 1 test
3 water injection wellheads 1 gas lift
1 water injection
1 static/1 shared
umbilical
North 443 498 E Water injection manifold 1 water injection
6 693 175 N 2 water injection wellheads 1 static/1 shared
umbilical
Loyal 441 926 E Manifold x 2 1 production
6 697 934 N (production/injection)
3 production wellheads 1 test
3 water injection wellheads 1 gas lift
1 water injection
1 static/1 shared
umbilical
An’Teallach 435 740 E 1 gas injection wellhead 1 gas disposal
6 685 635 N 1 static/1 shared
umbilical
None of the subsea wellheads, pipelines or anchor cables present a subsea hazard to
shuttle tanker operations. The depth of the anchor cables below the FPSO vessel turret
will not affect operations at the stern of the FPSO vessel. Xmas trees protrude some
20ft above the seabed at the head of each well completion and consist essentially of a
cluster of valves for control and isolation of the wells.
The FPSO vessel has a modified barge-type hull form, with a ‘cut-up’ stern and a
rounded bow to assist in station-keeping characteristics and to minimise the effects of
wave slam. It has a wide, flared forward section and high forecastle to minimise the
frequency of green water reaching the vessel’s upper deck and the equipment and
systems located on and above this level (including process, oil storage, utility and safety
systems).
The basic dimensions of the FPSO vessel are:
• Length 244.80m
• Breadth 45.00m
• Depth 27.25m
Each mooring leg is approximately 2100m long. A chain length is fitted at either end of
the leg at the connection to the FPSO vessel turret and to the suction anchor. A third
length of chain is fitted to provide wear resistance over the touchdown area on
the seabed.
Uncontrolled
The thrusters are not designed to propel the FPSO vessel in a forward or aft direction.
The propeller units are Schottel SRP 1212 LSU underwater-mounted type with nozzles
and fixed pitch propeller blades. The units can be rotated through 360°. Each thruster is
electrically driven from above by an Ansaldo CRV 560 X4 13.8kV motor from the main
gas-turbine driven generators.
A Simrad dynamic heading and thruster control system is provided to maintain the
vessel heading and allow for joystick control and monitoring of the azimuth thrusters
from the Central Control Room (CCR) marine console or the bridge.
3 Communications
3.1 FPSO Vessel – Tanker – Rig – FSV –
Foinaven – Shore Communications Systems
The FPSO vessel communications main bearer is based on a Ku band satellite
communications system operating through a geostationary satellite. A full duplex high
availability system with a bandwidth of 384kbit/s provides continuous communications
between Schiehallion and BP offices in Dyce, Aberdeen, with onward connection to
Partners and the public telephone system.
An Inmarsat B satellite terminal is fitted on the FPSO vessel with facsimile, calling
buzzer, voice distress pushbutton initiation, three telephones and PC/printer for telex
message preparation and sending, for emergency use and during the main bearer
systems outages.
Uncontrolled
are untrenched.
The consequences of possible contact with subsea structures, flowlines, mooring lines
and risers are very serious. Masters are therefore advised to exercise every possible
precaution when engaged in any subsea activity.
Surface currents often exceed 2 knots, flowing mostly in a north-easterly direction.
However, their strength and direction is unpredictable and Masters should be aware of
the speed and direction of the current before commencing any operation, and should be
prepared for sudden changes which might occur.
5 Cargo Operations
5.1 General
All cargo operations are directed by the Services Foreman.
Cargo operations shall be planned and conducted so as to reduce to a minimum the
number of occasions that the supply vessel has to approach and manoeuvre into position
alongside the FPSO vessel during any one cargo run.
During cargo operations, when it becomes apparent that there will be a significant delay
in working, the supply vessel is to be stood down and directed to withdraw from the
500m zone to enable the Master and crew to take a rest period.
5.2.1 General
Prior to being granted permission to enter the 500m zone, the supply vessel will contact
Schiehallion Control. The Master of the vessel and Schiehallion Control will jointly go
through a checklist (refer to Appendix 1A and Section 7).
Note: If the vessel develops any form of mechanical or control failure while
alongside the FPSO vessel, cargo operations will be suspended and the
vessel will move clear. Cargo operations will only resume after the
necessary repairs have been satisfactorily completed.
5.4 Cranes
The FPSO vessel is equipped with two Keny electrohydraulic deck cranes on the
starboard side. The supply vessel will be required to move between cranes as required
to work deck cargo and bulks.
All cranes are rated at a Safe Working Load (SWL) of a maximum 12 tonnes on the
whipline, although an 8 tonne limit has been established to allow for operations to
continue in reasonable sea height conditions.
Uncontrolled
100 coupling.
Bulk shipments of methanol and calcium nitrate are taken forward on the starboard side
via a 3in hose and TODO quick-close coupling stowed on hydraulic spooling reels.
(12) Co-ordinate VHF frequency control and maintain records of any microwave link
frequencies established.
(13) Provide marine support during emergencies and emergency drills.
(14) Report any marine incident/accident to BP Marine Logistics Department.
(15) Co-ordinate any oil pollution activity and reporting.
(16) Co-ordinate emergency exercises with field standby vessels.
Note: The Schiehallion OIM has responsibility for all activities and operations within the
500m zone of the FPSO vessel and all drilling centres. The OIM has delegated
responsibility for all Marine Operations within the Schiehallion development area
to the Schiehallion OME.
Uncontrolled
7 Position Reference Systems
The principal position reference systems utilised between the shuttle tanker and the
FPSO vessel are DARPS and Artemis. Differential Global Positioning Systems (DGPS) on
the tanker and FPSO vessel also provide each vessel with geographical position
references, which are independent of DARPS and Artemis. The tanker and FPSO vessel
are both also fitted with a FANBEAM laser guidance and monitoring system.
Pre-entry check to be completed in conjunction with Schiehallion prior to entry into 500m zone
Master to confirm to Schiehallion Control: Yes/No Comments
The Master is fully aware of procedures for vessel entry (10 minute
settling period).
Uncontrolled
Schiehallion Control to confirm to vessel: Yes/No Comments
UKCSMAL001.129
Flare
Black Start
Generator (Rep) Cranes (OME)
Turret
MV & HV
Switchboard
Rooms Moonpool
BP Schiehallion Blocks 284 & 285
Fwd
MV
SW
Rm
Turret
Production Deck
Plan
UKCSMAL001.090
Paragraph Page
3 Communications 1-2-4
3.1 Land Communications 1-2-4
3.2 Marine and Aviation Communications 1-2-4
Paragraph Page
Uncontrolled
10.3 Mooring Operations 1-2-13
10.4 Cargo Transfer 1-2-13
10.5 Unmooring Operations 1-2-14
10.6 Emergency Stations 1-2-15
Figure
1.2.1 Foinaven Pre-entry Checklist 1-2-6
1.2.2 Foinaven Orientation and Crane Details 1-2-8
1.2 Location
FPSO Vessel
The geographical co-ordinates are:
• Latitude 60° 18’ 58.24” N
• Longitude 04° 16’ 23.85” W
The UTM co-ordinates are:
• Eastings 429657
• Northings 6687460
DC1
The geographical co-ordinates are:
• Latitude 60° 18’ 39.79” N
• Longitude 04° 20’ 16.00” W
The UTM co-ordinates are:
• Eastings 426083.13
• Northings 6686960.00
Water depth is 507m.
DC2A
The geographical co-ordinates are:
Uncontrolled
• Latitude 60° 20’ 37.46” N
• Longitude 04° 14’ 43.31” W
The UTM co-ordinates are:
• Eastings 431257.6
• Northings 6690499.6
Water depth is 476m.
Gas Well
The geographical co-ordinates are:
• Latitude 60° 17’ 25.10” N
• Longitude 04° 06’ 59.48” W
The UTM co-ordinates are:
• Eastings 438268.30
• Northings 6684421.80
Water depth is 332m.
• Northings 6691112.16
Water depth is 520m.
2.2 Propulsion
The FPSO vessel propulsion unit consists of two fore and aft main propellers, bow
thruster and stern thruster, and steering performed by high performance Schilling
rudders. All of this equipment can be controlled manually by joystick or automatically by
a Simrad automatic dynamic positioning system.
Uncontrolled
shuttle tankers.
3 Communications
3.1 Land Communications
Communications to shore will normally be routed by a Ku band satellite link. This link
will carry telephone, fax, electronic messaging and video conference channels.
Shore telephone and fax links can also be routed by satellite Inmarsat B systems or MF
ship-to-shore through a coast station.
Telephone numbers to the vessel by the Ku band link are through the BP Exploration
offices in Aberdeen and are (01224) 835108 and 835109. The Inmarsat B telephone
number is 871-330949910.
are untrenched.
The consequences of possible contact with subsea structures, flowlines, mooring
lines and risers are very serious. Masters are therefore advised to exercise every
possible precaution when engaged in any subsea activity.
Surface currents often exceed 2 knots, flowing mostly in a north-easterly direction.
However, their strength and direction is unpredictable and Masters should be aware of
the speed and direction of the current before commencing any operation, and be
prepared for sudden changes which might necessitate aborting that activity.
5 Cargo Operations
5.1 General
All cargo operations are directed by the Deck Foreman.
Cargo operations shall be planned and conducted so as to reduce to a minimum the
number of occasions that the supply vessel has to approach and manoeuvre into position
alongside the FPSO vessel during any one cargo run.
During cargo operations, when it becomes apparent that there will be a significant delay
in working, the supply vessel is to be stood down and directed to withdraw from the
500m zone to enable the Master and crew to take a rest period.
5.2.1 Checklist
General
Prior to being granted permission to enter the 500m zone, the supply vessel will contact
the FPSO vessel Deck Foreman. The Master of the vessel and the Deck Foreman will
jointly go through a checklist (refer to Figure 1.2.1 and Section 7) – for mobile drilling
units, the Master will complete the checklist with the person appointed by the
Offshore Installation Manager (OIM) (normally the Control Room Operator).
Pre-entry check to be completed in conjunction with Petrojarl Bridge prior to entry into 500m zone
Master to confirm to Petrojarl Bridge: Yes/No Comments
The Master is fully aware of procedures for vessel entry (10 minute
Uncontrolled
settling period).
UKCSMAL001.130
Completion of Checklist
The checklist will be completed and signed by the Deck Foreman confirming that the
vessel has reported in before approach and that the checks have been carried out by the
vessel immediately prior to permission being granted to enter the 500m zone.
Deck Foreman
The Deck Foreman will confirm to the standby vessel that supply vessel working is
about to commence, indicating which side and the estimated duration, and requesting
that the standby vessel be suitably positioned to provide appropriate cover.
5.4 Cranes
The FPSO vessel is equipped with three deck cranes, two located on the port side and
one on the starboard side (refer to Figure 1.2.2). The radius of coverage of the cranes
overlaps for cargo transfer. There is, however, very limited landing space on the FPSO
vessel, and supply vessels may be required to move from crane to crane. The forward
crane on the port side has a telescopic boom to assist positioning of cargo in the forward
landing area and helideck.
Port Forward
Crane
42m
Turret
Methanol
Manifold
42m
Uncontrolled
Starboard
Crane
Port Aft
Crane
42m
Bunker
Manifold
UKCSMAL001.092
Prior to any helicopters landing or taking off from the FPSO vessel, the standby vessel
will be notified and will take up a suitable position.
During helicopter operations, all overside crane working ceases until the helicopter has
either cleared the Installation or has shut down.
Supply or support vessels working alongside the FPSO vessel will keep clear of the flight
path of a landing or departing aircraft.
Uncontrolled
(7) Monitor and co-ordinate environmental recording equipment including subsea
current meters and wave-rider buoys.
(8) Maintain records of all equipment lost on the seabed and advise survey branch of
these losses immediately he is notified of them.
(9) Ensure that all standby vessels operating in the area maintain records of all vessel
traffic, and that the necessary warnings and information are given to fishing
vessels.
(10) Liaise with BP Survey Department on the deployment of subsea acoustic
transponder beacon frequencies, and maintain records of frequencies deployed.
(11) Maintain contact with, and co-ordinate activities of, construction vessels with
particular reference to Dynamic Positioning (DP) reference systems (Artemis, HPR,
Fan Beam etc).
(12) Co-ordinate VHF frequency control and maintain records of any microwave link
frequencies established.
(13) Provide marine support during emergencies and emergency drills.
(14) Report any marine incident/accident to BP Marine Logistics Department.
(15) Co-ordinate any oil pollution activity and reporting.
(16) Co-ordinate emergency exercises with field standby vessels.
Uncontrolled
The OIM of the FPSO vessel will pass relevant operational information to the tanker
Master. This will include other vessel activity within the field, and weather and
current details.
Based on the weather experienced, and on the weather forecast and details of current
received, the Tanker Master will decide whether to proceed with berthing at the FPSO
vessel. If the decision is to go ahead, clearance to proceed will then be given by the OIM
of the FPSO vessel.
The OIM or Marine Co-ordinator will then instruct other vessel(s) to keep well clear of
the approaching tanker.
The speed of the tanker, when approaching closer than 5 nautical miles to the FPSO
vessel, shall not exceed 5 knots, and the final approach, when within one mile of the
FPSO vessel, shall be made at a speed sufficient to maintain steering only.
Mooring hawser tensions are monitored and, at certain tension levels, alarms will sound
in the FPSO vessel Navigation Control Centre (NCC). Should the hawser tension reach
200mt three times in any one hour, the cargo pumps will be stopped and preparations
made for disconnection. If the hawser tension reaches 240mt, the cargo pumps will
automatically be stopped. Should hawser tension reach 280mt, the hose and hawser
should be disconnected.
To avoid damage to the hosereel, a breakaway coupling is fitted between hose lengths
2 and 3, counting from the Pusnes coupling. This breakaway coupling has a breaking
load of 75 tonnes and, to avoid surge pressure, it incorporates a slow closing valve
which takes less than 20 seconds to close.
During berthing/unberthing and cargo transfer operations, the FPSO vessel will run its
main propulsion on forward thrust at approximately 25% to 30% pitch to create a current
away from the FPSO vessel, unless there is sufficient wind or current already.
Uncontrolled
Non-DP tankers should operate stern thrust sufficient to maintain a tight hawser and to
reduce fishtailing. Typically this would be 0% to 75% thrust.
In the event that the shuttle tanker has difficulty in maintaining station, the FSV can be
used in the towing mode by attaching a line to the stern of the tanker.
The tanker shall maintain a separation distance of between 60 and 85m during cargo
transfer. Should the distance reduce to less than 65m, the FPSO vessel NCC must be
informed immediately.
The maximum cargo transfer rate will be 5000m3 per hour. Should the tanker require an
adjustment rate, the FPSO vessel NCC must be informed.
Appendix 1A
West of Shetland Field Arrangements
UKCSMAL001_134.ai
Uncontrolled
Part 2 Northern North Sea Field Information West of Shetland Field Arrangements
September 2001 Issue 1 App 1A-1/2
Marine Operations Manual UKCS-MAL-001
Section 2
East of Shetland (EoS)
Paragraph Page
2 Communications 2-1-2
Uncontrolled
Paragraph Page
Uncontrolled
9 Role of the On-scene Commander 2-1-13
9.1 Magnus Platform 2-1-13
9.2 Installation Abandonment 2-1-14
9.3 Role of the Standby Vessel 2-1-14
9.4 Catastrophic Incident 2-1-14
9.5 Dyce ERC – Actions 2-1-14
Figure
2.1.1 Magnus Profiles 2-1-4
2.1.2 Magnus Pre-entry Checklist 2-1-7
2.1.3 Magnus Task Risk Assessment 2-1-8
2.1.4 Magnus Orientation Cranes/Risers/Exclusion Zone 2-1-15
transfers the oil to Ninian Central Platform and thence to Sullom Voe. The entrenched
20in gas exporting line transfers the gas to Brent Alpha and thence to the mainland at
St Fergus.
The associated trenched flowlines and umbilicals to the wellheads are in a general
north-east/south-west direction.
The Magnus heading is 045° (T). The geographical positions of the platform, wells and
subsea valves are as follows:
• Magnus 61° 37’ 12.45” N
01° 18’ 25.96” E
• 211/12A-13 61° 35’ 15.43” N
01° 16’ 44.43” E
• 211/12A-12A 61° 34’ 34.41” N
01° 17’ 12.60” E
• 211/12A-11 61° 35’ 13.23” N
01° 18’ 35.86” E
• 211/12-5 61° 36’ 21.12” N
01° 17’ 41.53” E
Uncontrolled
• 211/12-6 61° 39’ 07.84” N
01° 20’ 31.99” E
• 211/7A-3 61° 40’ 05.63” N
01° 22’ 11.17” E
• 211/12A-10 61° 39’ 34.98” N
01° 21’ 59.74” E
• NLGP subsea valve cover 61° 35’ 58.00” N
01° 20’ 40.00” E
2 Communications
2.1 Land Communications
Communications to shore will normally be routed over microwave links to the Thistle
platform and then via tropospheric scatter to Scousburgh (Shetland), Mormond Hill
(Banffshire) and then via a microwave link to Granite Hill, Aberdeen, plus British Telecom
(BT) lines to Dyce and public network. These links will carry telephone, data and
telex channels.
The oil and gas export risers are located on the east side of the south-west face of
the Installation (refer to Figure 2.1.1). Their locations are marked by a large
warning sign. The risers are located within the jacket but are still at risk to
vessel impact.
WARNING: THE POSSIBLE CONSEQUENCES OF VESSEL CONTACT WITH THESE
RISERS ARE VERY SERIOUS, AND THERE IS A ‘NO GO’ RESTRICTED
ZONE AREA EXTENDING 300M IN CORRIDOR FASHION FROM THE
SOUTH-WEST FACE. ACCESS TO THIS AREA WILL ONLY BE
CONSIDERED IN EXCEPTIONAL CIRCUMSTANCES BY THE MAGNUS
OIM FOLLOWING A HAZID RISK ASSESSMENT AND COLLECTIVE
APPROVAL OF PLATFORM MANAGEMENT AND THE VESSEL
MASTER. MASTERS ARE ADVISED TO MANOEUVRE WITH
EXTREME CAUTION WITHIN THIS RESTRICTED AREA.
There is an area of aerated water off the south-west face of the platform. This aeration is
present at all times but is particularly bad when the water injection pumps are on
recirculation. This can cause problems with station keeping on the south side of
the platform.
The well risers are situated in the centre of the platform and are not exposed to risk in
the event of minor marine collision.
The main oil and gas export lines are not trenched.
The flowlines and umbilicals, though trenched, are not buried.
4 Recommended Anchorage
The dedicated vessel anchorage is bounded by the following co-ordinates:
• 61° 38’ N 01’ 12” E
• 61° 40’ N 01’ 12” E
• 61° 38’ N 01’ 16” E
• 61° 40’ N 01’ 16” E
'C' CRANE
Uncontrolled
EXPORT
RISERS
UKCSMAL001.031
99m
5m
32.5m
27.5m
24m
Uncontrolled
LAT
210m
MUD LINE
UKCSMAL001.032
5 Cargo Operations
5.1 General
All vessel movements within the Magnus field are directed by the GSS.
All cargo operations are co-ordinated by the GSS.
Cargo operations shall be planned and conducted to reduce the number of occasions
that the vessel has to approach and manoeuvre into position alongside the platform
during any one cargo run to the platform.
During cargo operations, when it becomes apparent that there will be a significant delay
in working, the vessel is to be stood down and directed to withdraw from the 500m
zone to enable the Master and crew to take a rest period.
Uncontrolled
5.2 Procedures for Vessels Working
within the Magnus 500m Zone
5.2.1 Introduction
These procedures are to be followed by all vessels working within the 500m zone of the
Magnus platform.
Pre-entry check to be completed in conjunction with Magnus Deck Co-ordinator prior to entry into 500m zone
Master to confirm to Deck Co-ordinator: Vessel new to Master.
Master new to vessel. Yes/No Comments
Master new to Magnus.
Supply vessel pre-entry procedure issued to vessel by ASCO.
Master has read and understood procedures.
Main engines tested – ahead and astern.
Steering gear – fully function tested (main and emergency).
Bow, stern and azimuth thrusters (as applicable) – running and tested, to be fully
Uncontrolled
operational.
Joystick (poscon) – fully functional.
Communications – VHF sets and deck speakers tested.
Master is aware of platform procedure for vessel entry (steering an offset course,
speed and manoeuvring);and two men on bridge while inside the 500m zone.
Master to state if vessel has travelled through heavy seas, such that his cargo
has shifted.
Deck Changehand to confirm to vessel: Yes/No Comments
Deck and crane communication systems have been successfully tested.
Safety latches on crane pendants are free.
That oil and gas risers are on the south face and are clearly marked as a
major hazard.
Produced water outfall is on the north face with potential for gas and possible
visibility impairment.
The vessel’s deck crew are not required or expected to climb on top of cargo units to
gain access to units within the stow.
All ships crew are required to wear full protective equipment when on deck.
Smoking is prohibited on the deck of the vessel when within the 500 metre zone.
Magnus has a strict safety regime and encourage the Master to comply with
all requirements
Deck Changehand to confirm to standby vessel (only when authorised Yes/No Comments
by OIM):
That supply vessel working is about to take place on the south face and to be
positioned to provide appropriate cover.
If there are any loads over 11 tonnes and to clarify weight and position of unit etc
on vessel.
Vessel: Date:
Master's Name:
CRT Name:
CRT Signature:
UKCSMAL001.110
Ref Procedures:
Uncontrolled
Is the prevailing seastate such that the vessel would be
driven away from the platform, if it lost power?
We have considered the need for engineering change before this task is carried out. We believe, however, that the measures we
have specified above and in the Procedure for supply vessel working with Magnus platform 500m zone are adequate to reduce
the overall risk to an acceptable level without further safeguards, and that the work can proceed.
Signed:
OIM:
GSS:
Deck Chargehand:
Dated:
UKCSMAL001_111.ai
5.3 Cranes
The three cranes on the platform are diesel driven and are independent of any electrical
power supply.
One crane is situated on the north-west corner, one in the middle of the south face and
one in the middle of the north face.
Supply vessels are normally worked on the south and west faces.
Uncontrolled
Note: Sea lifts are denoted as (s) and are for good to moderate weather conditions.
Platform deck lifts are denoted as (d).
* Maximum lift allowed in seas up to 3 metres.
Uncontrolled
7.2 Syledis
Magnus carries a slave station for the Northern North Sea Syledis Chain. The system is
capable of accommodating up to four simultaneous range mobiles and an unlimited
number of hyperbolic users. The operational frequency is 432.144MHz.
Details of beacon positioning can be obtained from the radio room.
The GSS is responsible for the day-to-day operations of the standby vessel.
8.4 Surveillance
The standby vessel will maintain an efficient surveillance of passing marine traffic to
combat the significant risk to Installation personnel from ship collision. Such surveillance
must be efficiently maintained at all times, including when on close standby (refer to
Part 1 Section 9 Paragraph 7).
In the event that any vessel is detected as having too close an approach to the
Installation, the Master of the standby vessel will immediately inform the OIM of
the Installation.
Note: It is recommended that surveillance is carried out with one radar set on the
24-mile range and one radar set on the 12-mile range. This will assist the standby
vessel to detect potential errant vessels as early as possible, allowing it to take
action to protect the Installation. It will also give sufficient warning to the
Installation OIM who requires at least 20 minutes to take appropriate action.
Uncontrolled
On being notified of an emergency on Magnus, the standby vessel will:
(1) Close up to the Installation, muster all crew as required and ensure that all vital
equipment is made ready.
(2) Monitor the situation, providing assistance when requested.
On receipt of decision to abandon the Installation:
(1) Take over as OSC and inform Coastguard immediately that he has done so.
(2) Monitor the situation, provide assistance where possible and attempt to contact
the Magnus OIM if applicable.
(3) Relay, if necessary, any distress messages direct to a coast radio station or
Coastguard Maritime Rescue Control Centre (MRCC).
(4) Keep the MRCC fully updated as the incident progresses.
(5) Apply Fi-Fi cooling to the platform where required.
(6) As far as possible maintain a log of events.
(7) Carry out all other OSC functions as necessary until relieved, giving priority to the
saving of life.
Platform
North
TRUE 50m Radius
NORTH
50m Radius
Export
Risers
No Go Area
(Extends 300m
in Corridor Fashion)
Supply Vessel Operations
Supply vessels can work on the
west and north faces. Working on
the south side of the platform will 50m
only be considered in exceptional Radius
circumstances.
UKCS-MAL-001
UKCSMAL001.030
2-1-15/16
Magnus
Marine Operations Manual UKCS-MAL-001
Paragraph Page
2 Communications 2-2-2
Uncontrolled
4 Anchoring 2-2-3
Paragraph Page
Uncontrolled
9.5 Conoco Shore Base – Actions 2-2-11
9.6 Dyce ERC – Actions 2-2-11
Figure
2.2.1 Thistle Orientation/Cranes/Risers 2-2-4
2.2.2 Thistle Pre-entry Checklist 2-2-5
Oil is transported ashore by an 8 mile, 16in pipeline to Dunlin Alpha and then via the
Cormorant system to Sullom Voe. Two 16in pipelines exist between the platform and
the Single Anchor Leg Mooring (SALM) base, but the mooring leg has been removed.
Gas is exported by pipeline to join up with the Magnus and Murchison lines and, from
there, into the Northern Leg Gas Pipeline (NLGP) system.
There is no fair weather small craft access platform facility on any of the legs.
However, there are three suitable sites for landing emergency gangways, all at the
production deck (81ft) level as follows:
(1) South-east face beneath the east corner of the helideck, between lifeboats ‘1’
and ’E’.
(2) South-west face at west corner adjacent to number 3 Artemis station.
(3) North-east face midway along the face adjacent to PC1 crane pedestal.
2 Communications
2.1 Land Communications
Uncontrolled
There is a tropospheric scatter radio link to Scousburgh (Shetland), Mormand Hill
(Banffshire) and then, via a microwave link, to Granite Hill Aberdeen. British Telecom
provides lines to BP Dyce and the public network.
The above tropo link is duplicated on North Cormorant and the two Installations take
turns in hosting the traffic.
There is also an additional backup Inmarsat satellite system.
VHF Channel 11
VHF Channel 16
Thistle to the tanker loading template. The SALM buoy is stored onshore.
The geographical position of the gravity base is:
• Latitude 60° 22’ 40” N
• Longitude 01° 36’ 21” E
4 Anchoring
Anchoring is not normally allowed within the development area due to the proximity of
pipelines and underwater obstructions.
5 Cargo Operations
5.1 General
All vessel movements and cargo operations within the Thistle field are directed by the
Offshore Services Co-ordinator (OSC).
5.2 Cranes
Supply vessels are worked on the north-east and south-west faces. Both faces are
served by a pedestal crane, designated PC1 (north-east face) and PC2 (south-west face).
A third crane PC3 is situated in the centre of the platform. The south-west crane is
worked only in exceptional circumstances and then with the Offshore Installation
Manager’s (OIM’s) permission.
Platform
North
35m
Radius
Oil Riser
35m
Radius
UKCSMAL001.033
Uncontrolled
Marine Operations Manual UKCS-MAL-001
Pre-entry check to be completed in conjunction with Thistle prior to entry into 500m zone
Master to confirm to Offshore Services Co-ordinator (M): Yes/No Comments
Main engines: tested ahead and astern.
Steering gear fully function tested (main and emergency) running and tested to be
fully operational.
Bow, stern and azimuthing thrusters (as applicable) running and tested to be
fully operational.
Uncontrolled
Vessel: Date:
Master's Name:
CRT Name:
CRT Signature:
UKCSMAL001.112
Uncontrolled
helicopter has cleared the Installation or has shut down. However, where there is a
requirement to operate the cranes they shall comply with the following procedures:
(1) PC2 must be shut down during all helicopter operations.
(2) PC1 can continue to operate during helicopter operations providing the boom does
not literally operate in the direction of the helideck.
(3) PC3 can continue to operate during helicopter operations providing it operates in a
180° sweep towards the north-west face. If this cannot be guaranteed then it must
be shut down.
(4) In bad weather conditions, should any helicopter Captain, in making his final
approach, find crane movements distracting his vision from the target circle, then
he is within his rights to request that the cranes are shut down.
Aircraft are not permitted to land on, or take off from, vessels positioned less than 50m
from the nearest point of the platform.
Note: The hose must be visible to the person driving the vessel at all times. If this
cannot be achieved, then a crew member with suitable communications
must be posted to observe the hoses.
(9) Ensure that cargo transfer commences slowly and that the rate is increased only
when the lines have been proved.
(10) Confirm regularly with the control room the amount of cargo which has been
transferred.
When working scaffolding overside and underdeck around the platform the following
guidelines must be followed:
(1) Diving may take place on the opposite side of the platform to a limit of -150ft. This
is within the air dive range and either basket or bell may be used as a
transport vehicle.
(2) If scaffolding operations are taking place around a corner (leg area) section, then
diving may take place behind the other leg on that face provided that the operation
is screened by the leg.
(3) Prior to any diving operations the OIM and the OSC must be satisfied that all
conditions are safe.
(4) Prior to every instance of overside/underdeck scaffolding during diving operations,
the Diving Superintendent must be consulted.
Uncontrolled
(5) Saturation diving will not be permitted whilst any overside/underdeck scaffolding is
taking place.
7.2 Artemis
There are two calibrated Artemis station positions.
• On the east corner of the platform:
- Latitude 61° 21’ 47.74” N
- Longitude 01° 34’ 50.50” E
• On the west corner of the platform:
- Latitude 61° 21’ 46.28” N
- Longitude 01° 34’ 42.53” E
8.1 General
The Thistle standby vessel is jointly shared with the Murchison platform. For details of
the operation of the vessel, reference is to be made to the Standing Instructions and
Guidelines for the Operation of the Murchison Thistle Standby Vessel (MLS-PRO-311),
which describes the general duties and responsibilities of the vessel.
Reference shall also be made to Part 1 Section 9.
Uncontrolled
(3) Update Murchison OIM as often as practicable.
Paragraph Page
3 Communications 2-3-2
3.1 General 2-3-2
Uncontrolled
Figure
2.3.1 North West Hutton General View 2-3-6
2.3.2 North West Hutton Orientation/Cranes 2-3-7
2.3.3 North West Hutton Pre-entry Checklist 2-3-7
2 Platform Overview
Uncontrolled
North West Hutton is a single steel jacket supported platform of modular construction,
which was designed by McDermott Engineering, London. It was installed in September
1981 and production startup commenced in April 1983.
The purpose of the Installation is to provide facilities to drill wells to the producing
reservoir and extract, separate and process the reservoir fluids, a mixture of oil, gas and
water. After processing, oil is exported, via the Cormorant A platform, through the Brent
system oil pipeline to the onshore terminal at Sullom Voe. Gas is utilised for fuel gas and
gas lift purposes, and produced water is treated prior to being discharged overboard. The
Hutton tension leg platform produces via the North West Hutton platform. Fuel gas is
imported from Ninian.
Development drilling began through a template in October 1979 using a
semisubmersible rig, prior to installation of the platform; drilling from the platform
commenced in June 1983.
The platform comprises a steel jacket framework of cross-braced design, piled into the
seabed. A Module Support Frame (MSF) is positioned directly on top of the jacket and
supports the topsides facilities, which are of modular construction and comprise three
main decks, namely a cellar deck, a production deck and a drilling deck.
Two drilling rigs, two mud modules and an accommodation module are located on the
drilling deck and a flare boom extends from the cellar deck. Drilling operations are no
longer undertaken from the platform but the associated derrick(s) may be used to assist
wireline operations.
The accommodation module provides accommodation and recreation facilities for up to
209 persons, though the number of personnel onboard does not normally exceed 180.
A general view of the platform is shown in Figure 2.3.1.
The platform is designed to be self-supporting with facilities installed for the production
and/or storage of the supplies necessary for life support and the day-to-day running of
systems and equipment. Facilities are provided to enable platform stocks to be
replenished from supply boats, as required.
Safety systems and equipment are installed throughout the platform to provide
protection to personnel and equipment. Sufficient personnel protection facilities are
provided to adequately cover all persons onboard at any time. An extensive
communications system is installed on the platform and provides both internal and
external communication during both normal and emergency situations.
3 Communications
3.1 General
All marine movements within the NW Hutton 500m safety zone are controlled by the
North West Hutton Crane Operator.
Initial communications for all vessels (seismic, diving, survey, supply etc) shall be with
Uncontrolled
the North West Hutton Radio Operator or control room.
Note: UHF will be used when the vessel is alongside the platform.
4.4 Surveillance
The standby vessel will maintain an efficient surveillance of passing marine traffic to
combat the significant risk to Installation personnel from ship collision. Such surveillance
must be efficiently maintained at all times, including when on close standby (refer to
Part 1 Section 9 Paragraph 7).
In the event that any vessel is detected as having too close an approach to the
Installation, the Master of the standby vessel will immediately inform the OIM of
the Installation.
Note: It is recommended that surveillance is carried out with one radar set on the
24-mile range and one radar set on the 12-mile range. This will assist the standby
vessel to detect potential errant vessels as early as possible, allowing it to take
action to protect the Installation. It will also give sufficient warning to the
Installation OIM who requires at least 20 minutes to take appropriate action.
Uncontrolled
If the situation reaches a stage where the NW Hutton OIM has no other recourse but to
abandon the Asset, then he, or his deputy, shall carry out the following actions:
(1) Inform the Master of the standby vessel of the decision to abandon and request
that he now takes over as On-scene Commander (OSC). If possible, the OIM
should indicate the method of leaving the platform and if he is going to be
contactable once he has left.
(2) Make all contacts as per NW Hutton emergency procedures for abandonment.
(3) Cover all actions required for platform abandonment.
Uncontrolled
TRUE
NORTH
50m Radius
Platform
Flare
North
Uncontrolled
50m Radius
UKCSMAL001.035
Pre-entry check to be completed in conjunction with Hutton prior to entry into 500m zone
UKCSMAL001.113